Sherman R. Smoot Co. v. Ohio Department of Administrative Services

736 N.E.2d 69, 136 Ohio App. 3d 166, 2000 Ohio App. LEXIS 180
CourtOhio Court of Appeals
DecidedJanuary 27, 2000
DocketNo. 98AP-1497.
StatusPublished
Cited by26 cases

This text of 736 N.E.2d 69 (Sherman R. Smoot Co. v. Ohio Department of Administrative Services) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sherman R. Smoot Co. v. Ohio Department of Administrative Services, 736 N.E.2d 69, 136 Ohio App. 3d 166, 2000 Ohio App. LEXIS 180 (Ohio Ct. App. 2000).

Opinion

Kennedy, Judge.

Plaintiff-appellant, The Sherman R. Smoot Company of Ohio (“Smoot”), appeals from a judgment of the Ohio Court of Claims awarding it $749,017.13 on its breach of contract claims against defendant-appellee, the Ohio Department of Administrative Services.

This action arises out of the state’s construction of the Belmont Correctional Institution in Belmont County, Ohio. Construction of the prison was planned in several distinct phases. Although the entire project was overseen by a single project manager, the prime contracts, those for the general trades, the plumbing, the electrical, and the heating and cooling work, were bid separately for each phase of the project.

Smoot, a large construction company with expertise in concrete and masonry work, won the contracts to serve as the prime general trades contractor on phases III and IV of ,the project, for $8,436,600 and $3,828,000, respectively. Phase III involved the construction of seven prison support buildings, including the prison administration building, the infirmary, a segregated housing unit, and a large-food services building. Phase IV involved the construction of eight identical housing units.

The state issued a notice to proceed with phase III on September 18, 1993. The contract originally required work on phase III to be complete within four hundred twenty days, or by November 2, 1994. However, a thirty-day extension granted by the state moved the completion date to December 2,1994.

*171 The state issued a notice to proceed with phase IV on November 26,1993. The contract originally required work on phase IV to be complete within three hundred thirty days, or by October 23, 1994. However, the state granted a thirty-day extension on phase IV as well, pushing the completion date to November 20, 1994.

During the course of its work on both phases III and IV, Smoot sought numerous change orders for additional compensation or an extension of time from the state. Several of Smoot’s change order requests were granted, but most were not. It is these ungranted change orders that form the basis of Smoot’s claims against the state. While Smoot’s claims will be discussed in detail under their corresponding assignments of error, at issue herein are Smoot’s claims for additional compensation for (1) differing site conditions that necessitated the use of “form footings,” rather than “trench footings,” for the wall footings on four of the seven phase III buildings; (2) the constructive acceleration of work on phases III and IV necessitated by the state’s refusal to grant Smoot a time extension for weather-related delays occurring after January 31, 1994; (3) increased costs on phase III caused by the failure of Power City Plumbing and Heating (“Power City”), the prime heating and cooling contractor on phase III, to complete its work on schedule; and (4) increased costs on phase IV caused by Power City’s failure to complete its work on schedule.

Smoot filed its complaint against the state in the Court of Claims on May 15, 1996. Smoot’s complaint contained claims for breach of contract, equitable adjustment, breach of warranty, negligence, unjust enrichment, and quantum meruit, and sought damages in the amount $2,200,000, plus interest and costs.

Smoot’s claims against the state were tried by the court beginning on April 20, 1998. On October 22, 1998, the Court of Claims issued a decision and a judgment entry awarding Smoot $749,017.13. Specifically, the Court of Claims awarded Smoot $350,866.84 on its claims for increased costs on phase III arising out of Power City’s failure to complete its work on schedule, and a total of $202,183.50 on several minor claims that are not the subject of this appeal, plus prejudgment interest of $195,966.79 on these amounts. However, the Court of Claims found for the state on Smoot’s claims for differing site conditions, constructive acceleration on phases III and IV necessitated by the state’s refusal to grant a time extension for weather-related delays occurring after January 31, 1994, and increased cost on phase IV arising out of Power City’s failure to complete its work on schedule.

Smoot appeals from the decision and entry of the Court of Claims assigning the following errors:

*172 Assignment of Error No. 1
“The trial court erred in denying recovery to Smoot of the additional costs it incurred on Phase III of the Project due to subsurface conditions which were materially different from those represented in the contract documents and soil-boring logs provided by the owner, the Department of Administrative Services.”
Assignment of Error No. 2
“The trial court erred in denying recovery to Smoot of the additional costs it incurred on the Project due to the refusal of the Department of Administrative Services to recognize contractually required, weather-related, time extensions on Phase III of the Project.”
Assignment of Error No. 3
“The trial court erred in denying recovery to Smoot of the additional costs it incurred on Phase IV of the Project due to the failure of the Department of Administrative Services to properly manage Power City, one of the Phase III prime contractors, and the refusal of the Department of Administrative Services to recognize contractually required, weather-related, time extensions on Phase III of the Project.”
Assignment of Error No. 4
“The trial court erred in denying recovery to Smoot of all of the additional costs it incurred on Phase III of the Project due to decreased labor productivity resulting from the failure of the Department of Administrative Services to properly manage Power City, one of the other Phase III prime contractors.”

Preliminarily, the issues raised by Smoot’s assignments of error involve the interpretation of contract language, as well as the review of the trial court’s factual findings. Issues of contract construction and interpretation are questions of law. Latina v. Woodpath Dev. Co. (1991), 57 Ohio St.3d 212, 214, 567 N.E.2d 262, 264-265 Questions of law are subject to de novo review on appeal. Wiltberger v. Davis (1996), 110 Ohio App.3d 46, 51-52, 673 N.E.2d 628, 631-632. The trial court’s findings of fact, however, are entitled to deference on appeal and will not be overturned so long as there is competent, credible evidence to support them. State v. Harris (1994), 98 Ohio App.3d 543, 546, 649 N.E.2d 7, 9.

Smoot’s first assignment of error challenges the trial court’s denial of its differing site conditions claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SNC-Lavalin America, Inc. v. Alliant Techsystems, Inc.
858 F. Supp. 2d 620 (W.D. Virginia, 2012)
Cent. Allied Ents., Inc. v. Adjutant General's Dept.
2010 Ohio 3229 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Envir. Netwrk v. Goodman, Unpublished Decision (3-1-2007)
2007 Ohio 831 (Ohio Court of Appeals, 2007)
In Re Kelly Ferraro, Unpublished Decision (5-26-2005)
2005 Ohio 2608 (Ohio Court of Appeals, 2005)
Joel Lehmkuhl Excavating v. Troy, Unpublished Decision (4-29-2005)
2005 Ohio 2019 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
736 N.E.2d 69, 136 Ohio App. 3d 166, 2000 Ohio App. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sherman-r-smoot-co-v-ohio-department-of-administrative-services-ohioctapp-2000.