Dugan & Meyers Construction Co. v. State Department of Administrative Services

834 N.E.2d 1, 162 Ohio App. 3d 491, 2005 Ohio 3810
CourtOhio Court of Appeals
DecidedJuly 28, 2005
DocketNo. 03AP-1194.
StatusPublished
Cited by6 cases

This text of 834 N.E.2d 1 (Dugan & Meyers Construction Co. v. State Department of Administrative Services) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dugan & Meyers Construction Co. v. State Department of Administrative Services, 834 N.E.2d 1, 162 Ohio App. 3d 491, 2005 Ohio 3810 (Ohio Ct. App. 2005).

Opinions

Sadler, Judge.

{¶ 1} Defendants-appellants, the Ohio Department of Administrative Services (“ODAS”) and the Ohio State University (“OSU”), appeal from a judgment of the Ohio Court of Claims against appellants and in favor of plaintiff-appellee, Dugan & Meyers Construction Co., Inc. (“D & M” or “appellee”) in the amount of $2,749,069.37, plus prejudgment interest in the amount of $752,623.37. D & M has filed a cross-appeal, arguing that it is entitled to additional damages that it unsuccessfully sought below.

{¶ 2} This appeal arises from a contract with respect to which ODAS engaged D & M to perform lead-contractor services and to act as the prime contractor for the general-trades portion of a project involving the construction of three buildings that constituted Phase II of the Fisher College of Business on the OSU campus. The plans and specifications for the project were first made available to bidders the week of May 16, 1997, and competitive bidding for the project occurred during the week of June 18, 1997. As a result thereof, in accordance with R.C. Chapter 153 and R.C. 9.312, ODAS awarded the contract to D & M, which was the lowest responsive and responsible bidder.

{¶ 3} The parties entered into the contract on August 15, 1997. As lead contractor, appellee was required to coordinate the work of all of the prime contractors, including preparing and maintaining the project’s schedule. Appellee’s scope of work as prime contractor for general trades included the construction of the concrete shells for all three buildings, as well as the buildout for the buildings’ interiors. The original contract price was $20,932,500. The value of all prime contracts was $32,988,379 and was to be paid from $24,400,000 in funds appropriated for the project by the Ohio General Assembly, plus additional, private funding.

*495 {¶ 4} A notice to proceed was issued on August 15, 1997. The contract between ODAS and D & M specified that the Resource Center Building would be completed within 630 days of the notice to proceed, or by May 13, 1999, and that the Undergraduate and Executive Education Buildings would be completed within 660 days of the notice to proceed, or by June 12, 1999. The contract included a provision that time was of the essence and another provision for the assessment of liquidated damages in the amount of $3,000 per day, in the event that completion was delayed.

{¶ 5} ODAS was responsible for general administration of the project, and Karlsberger & Associates (“Karlsberger”) was engaged as the associate architect. In that capacity, Karlsberger was responsible for preparing the construction drawings and specifications, visiting the job site to observe the project as built, approving shop drawings, responding to requests for information (“RFIs”) sent by the contractors, and administering any design changes necessitated by any conflicts or discrepancies in the plans or specifications that were identified through the RFI process.

{¶ 6} Korda/Nemeth Engineering, Inc. (“Korda”) prepared the engineering plans and specifications, as a subconsultant to Karlsberger. Pursuant to its contractual duties to OSU, Karlsberger certified, by letter dated April 30, 1997, that it had completed coordination of the structural and architectural drawings with the mechanical, electrical, plumbing, and fire-protection drawings prepared by Korda. Tom Snearey of Karlsberger served as the senior project coordinator and had the primary responsibility for responding to RFIs from the contractors. Todd Cooper served as project manager on behalf of appellee, and Robert Fredelake was appellee’s project executive.

{¶ 7} ODAS retained Gilbane Building Company (“Gilbane”) to act as the construction manager. In that capacity, Gilbane was responsible for reviewing and approving the lead contractor’s (D & M’s) initial construction schedule, monitoring the schedule, processing and negotiating change orders, assisting the associate architect and OSU with processing of payment applications, assisting in the review and approval of shop drawings, and overseeing job-site safety and cost controls. Gilbane was charged with holding weekly progress meetings, which included representatives of the prime contractors, associate architect, and owner (OSU) and to resolve any scheduling issues that arose at these meetings.

{¶ 8} Pursuant to its contract with ODAS, D & M, in its capacity as lead contractor, was responsible for coordinating the work of all of the contractors and for developing a critical-path-method construction schedule. D & M was required to publish monthly schedule updates and to propose an affirmative recovery plan in the event that it appeared that any activities along the critical path, certain schedule milestones, or contract completion dates would not be met.

*496 {¶ 9} Commencement of work was delayed due to the temporary unavailability of structural steel. This precipitated an agreed no-cost change order that extended the contract completion dates to June 11, 1999, for the Resource Center and July 12, 1999, for the Undergraduate and Executive Education Buildings. D & M made no further written requests for extensions of time.

{¶ 10} The initial or baseline construction schedule was not approved until January 1998, but work did commence on the project in August 1997, shortly after issuance of the notice to proceed. In February 1998, ODAS assigned to OSU its responsibility for administering Phase II construction contracts on behalf of the state. This was done in order to save OSU $418,000 in administrative fees that OSU would otherwise have owed to ODAS for providing such contract administration services. All Phase II prime contractors, including D & M, executed no-cost change orders acknowledging that assignment. After February 27,1998, ODAS had no on-site representative in place for the project.

{¶ 11} The construction work progressed on schedule throughout the first year of the project, and appellee’s monthly schedule updates consistently forecast completion of the project within the extended completion dates for each building. However, beginning in June 1998, work was delayed significantly. Between June 1998 and the end of September 1998, for instance, 176 RFIs had been submitted, and 48 field work orders (“FWOs”) and 15 architect supplemental instructions (“ASIs”) had been issued.

{¶ 12} This process took place as follows. Contractors or subcontractors would initiate RFIs. For each RFI that did not require a change to the contract, the RFI would be returned to the issuing contractor with the response written directly thereon. If the response required a change to the plans or specifications but did not involve additional time or an increase in the contract price, an ASI would be issued. If the response required a change to the plans or specifications and did involve additional time or an increased contract price, an FWO would be issued, followed by a written change order. A contractor was not permitted to proceed with work involving a change to the plans or specifications until an ASI or FWO had been issued that authorized the change. Responses to RFIs were due within three days of receipt of the RFIs.

{¶ 13} Each RFI form contained a space within which the issuing contractor could indicate any effect the RFI was expected to have on the construction schedule or the cost of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G.A.I. Capital Group v. Lisowski
2023 Ohio 4802 (Ohio Court of Appeals, 2023)
Wagner-Smith Co. v. Ruscilli Construction Co.
2006 Ohio 5463 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
834 N.E.2d 1, 162 Ohio App. 3d 491, 2005 Ohio 3810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dugan-meyers-construction-co-v-state-department-of-administrative-ohioctapp-2005.