J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm.

2012 Ohio 5298
CourtOhio Court of Claims
DecidedFebruary 10, 2012
Docket2010-07644
StatusPublished

This text of 2012 Ohio 5298 (J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm., 2012 Ohio 5298 (Ohio Super. Ct. 2012).

Opinion

[Cite as J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm., 2012-Ohio-5298.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

J & H REINFORCING & STRUCTURAL ERECTORS, INC.

Plaintiff/Counter Defendant

v.

OHIO SCHOOL FACILITIES COMMISSION

Defendant/Counter Plaintiff

Case No. 2010-07644

Judge Joseph T. Clark Referee Thomas R. Yocum

DECISION OF THE REFEREE

{¶ 1} Plaintiff/Counter Defendant, J & H Reinforcing & Structural Erectors, Inc. (J&H), brought this action against Defendant/Counter Plaintiff, Ohio School Facilities Commission (OSFC), alleging breach of contract.1 OSFC has asserted a counterclaim for breach of contract and breach of express and implied warranties. The issues of liability and damages were not bifurcated and the case proceeded to trial on both issues. {¶ 2} In 2007, OSFC and the Wheelersburg Local Schools Board of Education (Wheelersburg) solicited bids for the construction of a school that was to house grades K-12. OSFC had previously contracted with Tanner Stone Holsinger Donges & Company (Tanner Stone) to act as project architect and Bovis Lend Lease Company (Bovis) to act as its construction manager. {¶ 3} J&H secured two separate contracts for the project. The first involved the pre-construction site work (Joint Exhibit O), and the second (the “Contract” which is

1 The court finds that both Count II of plaintiff’s complaint seeking an “equitable adjustment to the contract” and Count III seeking damages for “breach of express and implied warranty,” state essentially the same claim asserted in Count I. Accordingly, those counts will not be separately addressed in this subject of this litigation) involved the combination of general trades work, masonry, and interior case work (Joint Exhibit F - Joint Exhibits are referred to herein as “JX”). Notice to J&H to proceed was issued by Bovis on October 2, 2006. (Plaintiff’s Exhibit 91 - Plaintiff’s Exhibits are referred to herein as “PX.”) However, shortly after work was to begin, J&H encountered soil conditions which were unexpected and which proved to be too unstable to support the structure. J&H subsequently performed lime stabilization work pursuant to a contract change order. (JX P.) According to J&H, the delay caused by the poor soil conditions pushed the start of building construction out to December 26, 2006. {¶ 4} The general trades work progressed at a steady pace from January 2007 through July 2007. However, J&H learned that several Air Handling Units (AHUs) supplied by another contractor which were originally scheduled to be delivered in May 2007, were not going to arrive until September 2007. In order to accommodate the untimely delivery of the AHUs, J&H was required to leave a number of large gaps in the masonry walls as a means of ingress and egress for the oversized vehicles, cranes and structural steel that would be needed to deliver, set in place, and install the AHUs. In other areas, J&H’s roofing subcontractor was unable to perform its work due to the untimely delivery of the AHUs. The parties agree that the sequence of the masonry and roofing work was affected by the late delivery of the AHUs, but OSFC argues that this delay did not impact J&H’s efficiency or costs. {¶ 5} On or about January 2008, it became clear to J&H, Bovis and OSFC that the March 17, 2008 project completion date would be impossible to meet and that project completion before the start of the next school year in September was also in jeopardy. Following negotiations, the parties executed Change Order 29 (CO 29) (JX G- 29) whereby J&H agreed to extend the project completion date from March 17, 2008, to July 15, 2008, in return for additional compensation. There is considerable disagreement whether CO 29 represents an accord and satisfaction of all pending issues between the parties or just a partial settlement thereof. There is no dispute that work on the project continued in earnest following the execution of CO 29.

decision. For the same reason, Count II of the counterclaim will not be separately addressed. {¶ 6} In connection with the execution of CO 29, Bovis had drafted a new project schedule incorporating the agreed July 15, 2008 completion date. In an email correspondence sent to project contractors dated February 28, 2008, William Palonis, Bovis’ project manager, stated, “[we] feel at this time the schedule is displaying an accurate approach of how the project team is going to meet the completion date of July 15, 2008.” (See PX 129.) {¶ 7} However, even before Palonis sent his email, the accuracy of the new schedule was called into question by J&H Project Manager, Mark Rollins. In fact, beginning on or about February 14, 2008, Rollins began sending letters to Palonis informing Bovis that the schedule did not accurately reflect the progress that was being made in the field and asking Bovis either for additional time to complete specific tasks or for a corresponding extension of the project completion date. Rollins estimated that he sent 12-14 such letters over the next four months. (See PX 286.) In his last such letter dated June 30, 2008, Rollins requested an extension of the completion date to December 16, 2008. {¶ 8} Bovis ignored many of the letters, and in those instances where a response was made, J&H was informed that its requests were not in compliance with Article 6 of the contract. However, as a direct result of the letters, Bovis issued a “72-hour notice” to several other contractors on April 11, 2008. (See PX 140, 140A & 140B.) In the notices, Bovis states: {¶ 9} Bovis Lend Lease has received notification of delay from J&H Erectors that specifically addresses your scope of work as cause of delay. Let this notification serve as 72 hour notice that any scope of work directly related to your contract that is impacting the completion of J&H Erectors work will be your responsibility.

{¶ 10} A contemporaneous series of emails between Bovis Vice President, Jim Swartzmiller, and Palonis evidence Bovis’ desire to use the 72-hour notices as a means to paint J&H as the bad guy in the minds of the other contractors. Swartzmiller stated that he was getting tired of letters from J&H. The Bovis strategy (as the representative of OSFC) was to pit other contractors against J&H by sending 72-hour notices to other prime contractors, attach a copy of J&H correspondence, “paint J&H as instigator,” and “watch fireworks.” OSFC’s Construction Manager viewed this as a “win win.” (PX 137.) The concept of “winning” by sowing conflict and dissension among the project contractors represents the antithesis of what the Construction Manager should have been doing. It represents a lack of good faith and makes a mockery of the concept “partnering.” The tenor of these communications do not indicate that the Construction Manager was working as part of a team to timely complete the project for the good of all concerned. This sort of adversarial, disrespectful, and even demeaning attitude on the part of not only the Construction Manager, but also, OSFC’s own project manager is reflected in other conduct and communications including reference to Mark Rollins as “Don Jr.” (PX 153), and OSFC’s project manager dressing in a Halloween costume as a caricature of J&H’s owner, Don Hadsell (the photograph of which was widely distributed). (PX 299-003.) {¶ 11} What Rollins, J&H, and the other contractors on the project did not know at this time was that Bovis had deliberately manipulated its own scheduling software by switching to a “project override mode” so that a schedule could be produced with a July 15, 2008 completion date, even though Bovis knew that such a schedule was both unrealistic and unmanageable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
Shifrin v. Forest City Enterprises, Inc.
597 N.E.2d 499 (Ohio Supreme Court, 1992)
Galmish v. Cicchini
734 N.E.2d 782 (Ohio Supreme Court, 2000)
City of St. Marys v. Auglaize County Board of Commissioners
875 N.E.2d 561 (Ohio Supreme Court, 2007)
Shifrin v. Forest City Ent., Inc.
1992 Ohio 28 (Ohio Supreme Court, 1992)
Chicago Title Ins. Co. v. Huntington Natl. Bank
1999 Ohio 62 (Ohio Supreme Court, 1999)
Hamilton Ins. Serv., Inc. v. Nationwide Ins. Cos.
1999 Ohio 162 (Ohio Supreme Court, 1999)
Galmish v. Cicchini
2000 Ohio 7 (Ohio Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 5298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-reinforcing-structural-erectors-inc-v-ohio-scho-ohioctcl-2012.