Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth.

1997 Ohio 202, 78 Ohio St. 3d 353
CourtOhio Supreme Court
DecidedMay 14, 1997
Docket1995-2467
StatusPublished
Cited by71 cases

This text of 1997 Ohio 202 (Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth., 1997 Ohio 202, 78 Ohio St. 3d 353 (Ohio 1997).

Opinion

[This opinion has been published in Ohio Official Reports at 78 Ohio St.3d 353.]

FOSTER WHEELER ENVIRESPONSE, INC., APPELLEE AND CROSS-APPELLANT, v. FRANKLIN COUNTY CONVENTION FACILITIES AUTHORITY, APPELLANT; LAWHON & ASSOCIATES, INC., CROSS-APPELLEE. [Cite as Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth., 1997-Ohio-202.] Contracts—Removal and disposal of hazardous waste from construction site— Action by excavator for breach of contract and negligent misrepresentation—Motions for summary judgment by defendants proper, when. (No. 95-2467—Submitted January 7, 1997—Decided May 14, 1997.) APPEAL and CROSS-APPEAL from the Court of Appeals for Franklin County, No. 95APE04-401. __________________ {¶ 1} This action arises out of a contract for the removal and disposal of hazardous waste from the construction site of the Greater Columbus Convention Center. {¶ 2} Defendant-appellant, Franklin County Convention Facilities Authority (“CFA”), is a public agency governed by a volunteer public board pursuant to R.C. 351.04. Defendant and cross-appellee, Lawhon & Associates, Inc. (“Lawhon”), is an environmental consulting firm engaged by CFA on April 1, 1990, to perform hazardous material consulting services at the construction site of the convention center. Plaintiff-appellee and cross-appellant, Foster Wheeler Enviresponse, Inc. (“Enviresponse”), is an environmental hazards remediation contractor engaged by CFA on October 1, 1991, to excavate and dispose of certain hazardous waste discovered at the convention site. SUPREME COURT OF OHIO

{¶ 3} During the early phase of construction, a drain line was being installed in the southeast section of the property. The excavator tore the corner of a large wooden box buried beneath the surface, and coal tar waste was released from the box and into the sewer trench. Upon further investigation, the box was found to be sixty-one feet long, thirty-one feet wide and eleven feet deep, and filled with dirt and creosote. The area in which the box was located was formerly a railroad depot. It was believed that the box had been used as a pit in which railroad ties were creosoted, and that when the site was no longer used for this purpose the remaining creosote was left in the pit and covered with dirt. {¶ 4} Laboratory analysis indicated that the constituent benzene was present in sufficient quantities to characterize the material in the box as hazardous waste. Upon the advice of Lawhon, and with the concurrence of the Ohio Environmental Protection Agency, CFA elected a plan of remediation which involved removing the clean soil above the creosote and contaminated soil, solidifying and removing the waste remaining in the box, excavating and transporting “[t]he solidified waste, waste contaminated earth, and all contaminated areas *** to a hazardous waste landfill for disposal,” and backfilling the excavated area with clean fill. {¶ 5} In July 1991, the contract for the disposal of the coal tar waste was publicly bid. The bid specifications stated: “[T]he contents of the box consisted of 8 to 8.5 ft. of earth on top of 1.5 to 2 ft. of tar and tar contaminated material. *** The material has not moved into the soil, and there is little contamination outside of the box except in areas of recent disturbance. The quantity of tar and tar contaminated soil is estimated to be 140 cubic yards. “Samples of the soil over the waste were taken *** down to 8 feet depth. Samples were composited from 0-3, 3-6, and 6-8 feet. *** The results show that

2 January Term, 1997

the soil above the waste has negligible contamination and can be placed back in the excavation.” {¶ 6} The cost for disposing of the coal tar waste was estimated at $175,000. Bidders were instructed to submit proposals for a base price to remove and dispose of the estimated one hundred forty cubic yards of contaminated waste, and for a unit price, to be used in the event that “the quantity of coal tar waste and contaminated soil that must be treated as hazardous waste is more or less than 140 cubic yards, the consultant’s estimate.” {¶ 7} Enviresponse was found to be the lowest responsive and responsible bidder with a base bid of $165,000 and a unit price bid of $265 per cubic yard of waste. Accordingly, on October 1, 1991, CFA and Enviresponse entered into a contract on these terms for disposal of the coal tar waste. {¶ 8} The contract between CFA and Enviresponse consists of an eleven- page writing entitled “CONTRACT,” and several other writings specifically “made part of this Contract.” The contract documents are identified as “[t]he plans, Specifications, General Conditions, Special Conditions, Addenda and other Contract Documents.” {¶ 9} The contract describes the work to be performed as “ITEM NO. 1— COAL TAR WASTE DISPOSAL—BASE BID,” and sets forth that the “TOTAL AMOUNT OF THIS CONTRACT IS $165,000.00 subject to any additions or deductions during construction.” {¶ 10} Article 3 of the contract, entitled “CHANGE ORDERS, ADDITIONS, AND DEDUCTIONS,” provides: “No alterations shall be made in the work shown or described by the plans and specifications, except upon the written order of the Owner, and when so made, the value of the work added or omitted shall be computed for approval by the Owner, and the amount so ascertained shall be added to or deducted from the base bid amount.”

3 SUPREME COURT OF OHIO

{¶ 11} Under Article 5, Section h of the general conditions, “it is understood that the scheduled quantities of work to be done and materials to be furnished may each be increased or decreased as hereinafter provided.” Article 7, Section b of the general conditions provides: “In instances involving a unit price Contract, the Owner may, by written instructions to the Contractor, make alterations in the Plans involving increases or decreases in the quantity of work as may be necessary. Such alterations shall not be considered a waiver of any conditions of the Contract, nor invalidate any of the provisions thereof, unless the alterations materially change the scope of the work. The cost of increases or decreases in quantities of items shall be computed at the unit price bid and shall be added to or deducted from the original Contract by the endorsement of Change Order forms.” {¶ 12} In a document entitled “CONTRACT ATTACHMENT A,” the following is provided: “UNIT PRICES “*** The unit prices will apply to the net difference in quantities on any given change[.] “The unit prices may be used to adjust the Contract sum should there be an authorized increase or decrease in the scope of work stated. “DESCRIPTION OF ITEM UNIT UNIT PRICE* “All activities associated with Cubic Two Hundred Sixty Five disposal of coal tar waste in Yards and 00/100 Dollars quantities either in excess of ($265.00) or less than the base bid of 140 cubic yards. “* The unit price will be used to adjust the contract sum up or down depending on whether the quantity of coal tar waste and contaminated soil that must be treated as hazardous waste is more than or less than 140 cubic yards, the

4 January Term, 1997

consultant’s estimate. Adjustments will not be made for less than one cubic yard and will be made to the closest cubic yard. Contractor shall make measurements observed by a representative of the consultant.” {¶ 13} On October 15, 1991, Enviresponse commenced excavation of the soil above the waste. However, it began to encounter odors and saturated soil sooner than anticipated based on the bid specifications. On the same day, David “Mike” Finton, then manager of Enviresponse’s Ohio office, telephoned Claire A. Sawaya, then Executive Director of CFA, to inform her that there was more coal tar waste than originally estimated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apple-Chamberlain v. Apple
2025 Ohio 5388 (Ohio Court of Appeals, 2025)
Harder Invests., L.L.C. v. Perin-Tyler Family Found., L.L.C.
2025 Ohio 4706 (Ohio Court of Appeals, 2025)
EAP Ohio, L.L.C. v. Sunnydale Farms, L.L.C.
2024 Ohio 4522 (Ohio Court of Appeals, 2024)
Queen City Cleaning, L.L.C. v. I74 Wired, L.L.C.
2024 Ohio 1761 (Ohio Court of Appeals, 2024)
Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
King v. Newton Falls
2024 Ohio 782 (Ohio Court of Appeals, 2024)
SJBK, L.L.C. v. Northwood Energy Corp.
2023 Ohio 4729 (Ohio Court of Appeals, 2023)
Menard, Inc. v. DiPaolo Indus. Dev., L.L.C.
2023 Ohio 1188 (Ohio Court of Appeals, 2023)
Vandercar, L.L.C. v. Port of Greater Cincinnati Dev. Auth.
2022 Ohio 3148 (Ohio Court of Appeals, 2022)
DN Reynoldsburg, L.L.C. v. Maurices Inc.
2022 Ohio 949 (Ohio Court of Appeals, 2022)
In re Estate of Millstein
2021 Ohio 4610 (Ohio Court of Appeals, 2021)
Kent State Univ. v. Bradley Univ.
2019 Ohio 2088 (Ohio Court of Appeals, 2019)
BANK OF NEW YORK MELLON v. RHIEL, Trustee.
2018 Ohio 5087 (Ohio Supreme Court, 2018)
K & D Farms, Ltd v. Enervest Operating, L.L.C.
2015 Ohio 4475 (Ohio Court of Appeals, 2015)
H & C Ag Servs., L.L.C. v. Ohio Fresh Eggs, L.L.C.
2015 Ohio 3714 (Ohio Court of Appeals, 2015)
PNC Bank, N.A. v. Springboro Med. Arts, Inc.
2015 Ohio 3386 (Ohio Court of Appeals, 2015)
M & G Automotive Serv., Inc. v. Bouscher
2014 Ohio 5370 (Ohio Court of Appeals, 2014)
Yoder v. Artex Oil Co.
2014 Ohio 5130 (Ohio Court of Appeals, 2014)
Cleveland Clinic Found. v. Internatl. Portfolio, Inc.
2014 Ohio 700 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Ohio 202, 78 Ohio St. 3d 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-wheeler-enviresponse-inc-v-franklin-cty-convention-facilities-ohio-1997.