Lathrop Co. v. City of Toledo

214 N.E.2d 408, 5 Ohio St. 2d 165, 34 Ohio Op. 2d 278, 1966 Ohio LEXIS 403
CourtOhio Supreme Court
DecidedFebruary 16, 1966
DocketNo. 39416
StatusPublished
Cited by37 cases

This text of 214 N.E.2d 408 (Lathrop Co. v. City of Toledo) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lathrop Co. v. City of Toledo, 214 N.E.2d 408, 5 Ohio St. 2d 165, 34 Ohio Op. 2d 278, 1966 Ohio LEXIS 403 (Ohio 1966).

Opinions

Herbert, J.

The basic question presented here is whether Lathrop may recover for the extra work it performed.

Under section 19 of the contract, Lathrop was obligated to perform whatever extra work was ordered by the City. Under section 12(c), the City promised to pay for the extra work at the contract rate. However, the obligation to pay would attach only after certain restrictive conditions specified in the Toledo charter were met. In brief, the charter required (1) a written order of the city manager as to what extra work was to be done, (2) an agreement in writing as to the cost of the work and material, and (3) a certificate of the city auditor that funds were available to pay for the extra work. These conditions could only be fulfilled by the City. All involved the co-operation of city officers. As a matter of general contract law, if the promisor city were to make no promise, express or implied, to fulfill such a potestative condition precedent within its power, the general obligation to pay would be illusory. However, “ [i]t is very clear indeed that promissory words are not nullified by making the promise conditional on some event within the promisor’s own power, if at the same time he impliedly promises to make reasonable effort to bring the event about * * 1 Corbin (1963), Contracts, Section 149.

However, the above potestative conditions did not make the bridge contract or the extra-work provisions illusory since section 19 of the contract shows that the city intended to fulfill the potestative conditions precedent to its obligation, [171]*171expressly assumed, to pay for the extra work it might order if it was obligated under the contract to do so. It is our opinion that the city made an implied promise to fulfill the potestative conditions provided that it was contractually found obligated to pay for extra work. Since the proviso takes the potestative conditions out of the power of the City and makes it dependent on the legal fact of contractual obligation to pay, the promise to pay is not illusory but binding.

Both parties realized that haggling over contract rights and obligations concerning extra work would defeat the City’s desire to repair the bridge as soon as possible. So the parties put themselves in the following contractual relation if extra work were to become necessary; Lathrop was to do whatever work the City ordered; the determination of rights and obligations was reserved until the completion of the work; and the City would pay its obligation and take the necessary steps under the charter to do so.

The City did not take those steps because it mistakenly believed that the guarantee clause of the contract placed the burden of the extra work on Lathrop. We agree with the trial court’s interpretation, in its charge to the jury, that Lathrop guaranteed not that the City’s paint specifications were adequate but rather that it would follow the specifications given. It would be unreasonable to construe this provision to mean that Lathrop was the virtual insurer of the City’s choice of paints. Lathrop warranted only its own performance. Moreover, since it was the City that selected the language of the guarantee clause, any doubt or ambiguity will be resolved in favor of Lathrop. See, e. g., Bellish v. C. I. T. Corp. (1943), 142 Ohio St. 36, paragraph one of the syllabus; 3 Corbin, Contracts (1960), 262, Section 559.

Thus at the trial level, the complexity of the case had settled down to one fact issue — was the paint failure due to the City’s specifications or was it due to Lathrop’s workmanship. The jury found that the City was at fault.

Thus the City learned that the extra work was not owed to it by Lathrop, and that, since it had ordered it and agreed to pay for it, it was faced with a contract obligation.

If the City had been a private party, the finding of a con[172]*172tractual obligation would terminate this opinion. However, such a finding merely poses the issue: Although the City is obliged by contract law to fulfill the potestative conditions and pay its obligation, can the City assert its own breach of contract as a defense?

Many times this court has held that no recovery can be had on a contract that is entered into contrary to one or more of the legislated requirements. State, ex rel. Baen, v. Yeatman, Aud. (1872), 22 Ohio St. 546 (where contract was made in disregard of “competitive bidding” statutes, no recovery); McCloud & Geigle v. City of Columbus (1896), 54 Ohio St. 439 (where the statute prescribing the mode and time of advertising for bids was not complied with, no recovery on the contract); City of Lancaster v. Miller (1898), 58 Ohio St. 558 (where contract was made in complete disregard of statutes requiring competitive bidding and auditor’s certificate that funds are available, no recovery); Buchanan Bridge Co. v. Campbell et al., Commrs. (1899), 60 Ohio St. 406 (where the contract was made in complete disregard of provisions requiring advertising of offer and competitive bidding, no recovery); City of Findlay v. Pendleton and Whitely (1900), 62 Ohio St. 80 (where contract for services was made without the auditor’s certificate, no recovery, even though sufficient funds were available); Pittinger v. City of Wellsville (1907), 75 Ohio St. 508 (no recovery on a contract for personal services where contract was made without appropriation by city council and certification by auditor); Frisbie Co. v. City of East Cleveland (1918), 98 Ohio St. 266 (where contract was made in complete disregard of statutes requiring advertising and competitive bidding, no recovery); State v. Kuhner & King (1923), 107 Ohio St. 406 (state cannot recover money paid to contractor for performing a contract void from its inception because of failure to comply with the advertising statutes); State, ex rel. Allen, v. Lutz, Aud. (1924), 111 Ohio St. 333 (where statute puts an express limitation on amount of the debt that the government can incur, a contract for a larger amount is not enforceable beyond the limitation); Pincelli v. Ohio Bridge Corp. (1966), 5 Ohio St. 2d 41 (where contract was made in complete disregard of statutes requiring competitive bidding and an auditor’s certificate, no recovery).

[173]*173A thread running throughout the many eases the court has reviewed is that the contractor must ascertain whether the contract complies with the Constitution, statutes, charters, and ordinances so far as they are applicable. If he does not, he performs at his peril, e. g., City of Wellston v. Morgan (1901), 65 Ohio St. 219, paragraph four of the syllabus; Frisbie Co. v. City of East Cleveland, supra, paragraph five of the syllabus; State, ex rel. Allen, v. Luts, supra. The most articulate explanation of this principle was given in McCloud & Geigle v. City of Columbus, supra, at 452 and 453, where the court, in referring to private contractors, said:

“We think there is no hardship in requiring them, and all other parties who undertake to deal with a municipal body in respect of public improvements, to investigate the subject and ascertain at their peril whether the preliminary steps leading up to contract and prescribed by statute have been taken. No high degree of vigilance is required of persons thus situated to learn the facts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradley v. Islamic Ctr. of Peace, Inc.
2021 Ohio 3756 (Ohio Court of Appeals, 2021)
Musial Offices, Ltd. v. Cuyahoga Cty.
2020 Ohio 5426 (Ohio Court of Appeals, 2020)
Willacy v. Cleveland Bd. of Income Tax Rev. (Slip Opinion)
2020 Ohio 314 (Ohio Supreme Court, 2020)
Aquatic Renovations Sys., Inc. v. Vill. of Walbridge
2018 Ohio 1430 (Ohio Court of Appeals, 2018)
Alexander Local Sch. Dist. Bd. of Educ. v. Vill. of Albany
2017 Ohio 8704 (Ohio Court of Appeals, 2017)
White v. Cuyahoga Falls
2016 Ohio 1200 (Ohio Court of Appeals, 2016)
The CIT Group/Equipment Fin., Inc. v. Brown Cty.
2014 Ohio 5489 (Ohio Court of Appeals, 2014)
Sylvester Summers, Jr. Co., L.P.A. v. E. Cleveland
2013 Ohio 1339 (Ohio Court of Appeals, 2013)
Union Stock Yards Co. v. City of Hillsboro
2010 Ohio 5975 (Ohio Court of Appeals, 2010)
Enviro-Flow Co. v. Village of Chauncey, 07ca5 (2-15-2008)
2008 Ohio 698 (Ohio Court of Appeals, 2008)
Gralewski v. Ohio Bureau of Workers' Compensation
855 N.E.2d 879 (Ohio Court of Appeals, 2006)
CommuniCare, Inc. v. Wood County Board of Commissioners
829 N.E.2d 706 (Ohio Court of Appeals, 2005)
Current Source, Inc. v. Elyria City School District
813 N.E.2d 730 (Ohio Court of Appeals, 2004)
Seneca Valley, Inc. v. Village of Caldwell
808 N.E.2d 422 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
214 N.E.2d 408, 5 Ohio St. 2d 165, 34 Ohio Op. 2d 278, 1966 Ohio LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lathrop-co-v-city-of-toledo-ohio-1966.