Aquatic Renovations Sys., Inc. v. Vill. of Walbridge

2018 Ohio 1430, 110 N.E.3d 877
CourtOhio Court of Appeals
DecidedApril 13, 2018
DocketWD-17-038
StatusPublished
Cited by5 cases

This text of 2018 Ohio 1430 (Aquatic Renovations Sys., Inc. v. Vill. of Walbridge) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aquatic Renovations Sys., Inc. v. Vill. of Walbridge, 2018 Ohio 1430, 110 N.E.3d 877 (Ohio Ct. App. 2018).

Opinion

SINGER, J.

{¶ 1} This case is before the court on the appeal of appellant, Aquatic Renovations Systems, Inc., from the May 15, 2017 judgment of the Wood County Court of Common Pleas. For the reasons that follow, we affirm the trial court's judgment.

{¶ 2} Appellant sets forth the following assignment of error:

The trial court erred in denying the Motion for Summary Judgment of Plaintiff-Appellant, Aquatic Renovation Systems, Inc., as to Plaintiff-Appellant's claims against the Defendant-Appellee, Village of Walbridge.

Facts

{¶ 3} This case concerns the validity of an agreement between appellee, village of Walbridge ("the village"), and appellant for a new liner for the village's swimming pool ("the pool").

{¶ 4} On April 18, 2012, the village council adopted an ordinance which authorized the village's mayor to enter into an agreement with appellant for a new liner for the pool in the sum of $52,720.08.

{¶ 5} On May 2, 2012, a Contract Agreement Form between the village and appellant was signed by Edward Kolanko, the acting mayor of the village, and a representative of appellant and witnessed by Janice Sawaya, of the village, and another person. The contract provided for the installation of a new liner for the pool in the sum of $52,720.08, with the work to be substantially completed by May 21, 2012.

{¶ 6} On May 9, 2012, before appellant began work on the pool, the village had an engineer conduct a preliminary evaluation of the condition of the pool. An engineering field service report, completed on that day, stated the pool was in need of significant maintenance and repairs, which needed to be undertaken before the liner was installed.

{¶ 7} On May 25, 2012, Kenneth Frost, the village's administrator, wrote to appellant's representative indicating appellant's work on the pool could not be completed by May 21, 2012, through no fault of appellant, but the village wanted to go forward with the project after the pool was inspected and repaired.

{¶ 8} On June 1, 2012, appellant submitted to the village an application and certificate for payment of $15,763.30, for liner material as well as work for design and submittals, less eight percent retainage. On July 16, 2012, the village issued a check to appellant for $15,763.30. Thereafter, the village had repairs to the pool completed; appellant was not involved in the repair work.

{¶ 9} On April 8, 2013, appellant submitted a quotation to the village for installation of the pool liner for the balance due of $36,956.78. Mayor Kolanko signed and initialed the quotation on April 12, 2013.

{¶ 10} On June 13, 2013, a change order submitted by appellant to the village in the amount of $3,142.60 was signed by Frost, for the village. The order was also signed by a representative of appellant.

{¶ 11} On June 28, 2013, the mayor and appellant's representative conducted a walk-through of the work appellant had performed. Mayor Kolanko and a representative of appellant signed a New Installation, Multi-Division Work Order Form, which set forth that appellant arrived at the pool on June 4, 2013, and completed work on the pool on June 28, 2013.

{¶ 12} On July 3, 2013, Frost notified appellant that the liner had lifted away from the walls and floor of the pool due to a water leak. Appellant sent a representative to the pool to address the issue. The representative surmised part of the problem was a leaking pipe. Appellant provided a pump to the village to remove the water from the liner.

{¶ 13} In the fall of 2013, appellant's representative suggested to Frost that a pressure test should be performed. The test was undertaken and the result was "unable to achieve pressure." Appellant's representative informed Frost of the test result and made other suggestions to resolve the issue, to no avail. Appellant requested payment from the village for the completed and approved work, but the village refused to pay.

{¶ 14} On January 15, 2016, appellant filed its complaint against the village setting forth three causes of action. Appellant alleged it entered into two contracts with the village: the first contract was dated May 2, 2012 ("first contract"), and the second contract was dated April 12, 2013 ("second contract"). Appellant alleged in its first cause of action that the village breached the second contract, and sought damages in the amount of $36,956.78. Appellant alleged in its second cause of action that the village was liable to it under the legal theory of quantum meruit. In its third cause of action, appellant alleged the village received a benefit as a result of the work appellant performed, thus the village was liable to appellant for unjust enrichment.

{¶ 15} On March 24, 2016, the village filed its answer as well as a counterclaim for breach of contract by appellant. In the answer, the village admitted the parties entered into the first contract, but denied there was a second contract between the parties. In the counterclaim, the village alleged the parties entered into the first contract, and appellant breached that contract.

{¶ 16} On October 28, 2016, appellant filed a motion for summary judgment on its claims and the village's counterclaim. On November 14, 2016, the village filed a motion for summary judgment on its counterclaim as well as appellant's claims. Appellant responded to the village's motion.

{¶ 17} On May 15, 2017, the trial court issued its judgment, finding neither the first contract nor the second contract constituted a valid contract as neither agreement complied with the statutory law. The court further found appellant was not entitled to recover under the theory of quantum meruit or unjust enrichment. The court granted summary judgment to the village on appellant's claims, and granted summary judgment to appellant on the village's counterclaim. Appellant appealed the court's decision to grant summary judgment to the village on appellant's claims. The village did not appeal.

Standard

{¶ 18} We review a trial court's summary judgment decision on a de novo basis. Grafton v. Ohio Edison Co. , 77 Ohio St.3d 102 , 105, 671 N.E.2d 241 (1996). Accordingly, we undertake our own independent examination of the record and make our own decision as to whether the moving parties are entitled to summary judgment. Dupler v. Mansfield Journal , 64 Ohio St.2d 116 , 119-120, 413 N.E.2d 1187 (1980). Pursuant to Civ.R. 56, the moving party bears the initial burden of informing the trial court of the basis for the motion and presenting evidence in support thereof. Vahila v. Hall , 77 Ohio St.3d 421

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Kinkaid
Ohio Court of Appeals, 2026
Sutton v. Scarborough
2025 Ohio 4690 (Ohio Court of Appeals, 2025)
KN Excavation, L.L.C. v. Rockmill Brewey, L.L.C.
2022 Ohio 3414 (Ohio Court of Appeals, 2022)
Blausey v. Blausey
2019 Ohio 4506 (Ohio Court of Appeals, 2019)
Oberlin v. Lorain Cty. Joint Vocational School Dist. Bd. of Edn.
2019 Ohio 3977 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 1430, 110 N.E.3d 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aquatic-renovations-sys-inc-v-vill-of-walbridge-ohioctapp-2018.