Johnson Construction, Inc. v. Rugby Municipal Airport Authority

492 N.W.2d 61, 1992 N.D. LEXIS 224, 1992 WL 317517
CourtNorth Dakota Supreme Court
DecidedNovember 5, 1992
DocketCiv. 910325
StatusPublished
Cited by6 cases

This text of 492 N.W.2d 61 (Johnson Construction, Inc. v. Rugby Municipal Airport Authority) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Construction, Inc. v. Rugby Municipal Airport Authority, 492 N.W.2d 61, 1992 N.D. LEXIS 224, 1992 WL 317517 (N.D. 1992).

Opinion

VANDE WALLE, Justice.

Johnson Construction, Inc. (Johnson), appealed from a district court judgment entered in its action against Rugby Municipal Airport Authority (Rugby) to recover damages under a construction contract. We affirm.

In October 1985, Rugby awarded Johnson a contract to construct a new runway *62 and related improvements for $548,142.90. Johnson was required to excavate a trench where the new runway would be located, replace the excavated “subcut” from the trench with suitable “backfill” or “embankment” material, compact the embankment material, spread a 6" layer of crushed rock or gravel, and lay asphalt pavement.

After completing the project, Johnson sought additional compensation. Negotiations were unsuccessful and Johnson sued Rugby for additional compensation. Johnson’s claims involved two primary elements — excavation and paving. Johnson maintains that it was required to do more excavation and embankment work than had been anticipated. Johnson also asserts that Rugby employed an improper method of testing for pavement density uniformity, resulting in Johnson receiving a lower price than warranted.

The trial court disposed of Johnson’s $131,331 excavation claim by granting Rugby’s motion for partial summary judgment. Johnson’s paving claim was tried to the court, which determined that Johnson did not meet the required density standard and upheld Rugby’s downward price adjustment. The court concluded that Johnson was due money on other matters not here at issue and entered judgment in Johnson’s favor for $86,668.83. Johnson appealed, contending that the trial court erred in granting Rugby’s motion for partial summary judgment dismissing the excavation claim and erred in concluding that Johnson was not entitled to additional payment on the asphalt paving claim.

1. Excavation

On the excavation claim, Rugby argued: (1) the additional excavation was caused by rainfall and Johnson was not entitled to additional compensation because contractors are responsible for weather-related expenses; (2) Johnson failed to provide notice, under § 50-16 1 of the specifications, of its intention to seek additional compensation for excavation of subcut material; (3) there was no change order or supplemental agreement, as required by §§ 40-02 2 and 40-04 3 of the specifications; (4) *63 the contract does not contain a “differing site conditions” or “changed conditions” clause, which would “shift the risk of unknown subsurface conditions (such as groundwater) from the contractor to the owner”; and (5) that Johnson chose to excavate additional material below the planned depth to quickly dry the subcut, and that excavation should be at Johnson’s expense.

In its memorandum in opposition to Rugby’s motion, Johnson summarized its position as follows:

“1. The additional excavation for which Johnson seeks compensation was not weather-related but rather, was caused primarily by the fact that substantial quantities of the excavation which was to be used for fill under the runway (‘select embankment’) was not suitable for that purpose. See Affidavit of Curtis L. Erickson.
“2. The notice of claim for additional compensation is not required because the basis of the claim is not ‘extra work’ as defined in Section 10-20 of the specifications. The claim relates only to the final quantity of excavation for which Johnson is entitled to compensation. See Affidavit of Joe Metz-ger and Section 50-16 (p. 1.032) of the specifications (copy attached.). 4
“3. No change order or supplemental agreement is required, again because the basis of the claim is not ‘extra work’ as defined in the specifications. See Affidavit of Joe Metzger and Section 50-16 (p. 1.032) of the specifications (copy attached).”

In granting Rugby’s motion for a partial summary judgment dismissing Johnson’s excavation claim, the trial court concluded that notice of an intention to seek additional compensation was required, and that by failing to provide such notice, Johnson waived its right to make a claim:

“As a matter of law, the contract language clearly requires notice, a change order or supplemental agreement as a prerequisite to Plaintiff's excavation claim for additional compensation. The consequences for failure to give timely written notice or some type of written alteration of the contract, without a valid exception, constitutes a waiver of the right to make the claim. Therefore, Defendant’s Motion for Partial Summary Judgment is meritorious as a matter of law and is granted.”

The notice provision in § 50-16 of the specifications is similar to the notice provision in § 24-02-26.1, N.D.C.C., which we construed in Byron’s Constr. Co. v. North Dakota State Highway Dep’t, 448 N.W.2d 630 (N.D.1989). We observed that the notice statute protects important underlying concerns “by permitting early investigation of the validity of a claim when evidence is still available, by allowing the Highway Department to compile records of the contractor’s costs, and by allowing the Highway Department to consider alternate methods of construction to prevent unnecessary expenditures.” Id. at 633. We held that the notice provision required a contractor to provide written notice if it intended to seek additional compensation: “If Byron’s was requested to perform work or supply materials for which it did not believe it was being compensated under the contract, it was required to notify the engineer in writing of its intent to make a claim for additional compensation.” Id. at 634. See also, Herman v. Magnuson, 277 N.W.2d 445 (N.D.1979), in which we observed that notice requirements for presenting claims against a municipality foster prompt investigation while the evidence is still fresh, the adjustment of claims without the expense of litigation if the circum *64 stances warrant it, and the preparation of fiscal planning to meet possible liability. We do not believe that there is a significant distinction between the notice requirement in § 24-02-26.1, N.D.C.C., and § 50-16 of the specifications. We conclude that if Johnson believed it was being requested by Rugby’s engineer to perform more excavation and embankment work than it had anticipated, and for which it did not believe it was being compensated under the contract, it was required by § 50-16 of the specifications to notify the engineer in writing of its intent to make a claim for additional compensation. By failing to provide that written notice, Johnson waived all claims for additional compensation for excavation and embankment work.

Johnson argues that excavation and embankment “are clearly ‘provided for in the awarded contract’ and cannot be classified as ‘extra work' ” as defined in § 10-20 of the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mountrail Bethel Home v. Lovdahl
2006 ND 180 (North Dakota Supreme Court, 2006)
Gratech Co. v. North Dakota Department of Transportation
2004 ND 61 (North Dakota Supreme Court, 2004)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Minex Resources, Inc. v. Morland
518 N.W.2d 682 (North Dakota Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
492 N.W.2d 61, 1992 N.D. LEXIS 224, 1992 WL 317517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-construction-inc-v-rugby-municipal-airport-authority-nd-1992.