Byron's Construction Co. v. North Dakota State Highway Department

448 N.W.2d 630, 1989 N.D. LEXIS 231, 1989 WL 143420
CourtNorth Dakota Supreme Court
DecidedNovember 29, 1989
DocketCiv. 880326
StatusPublished
Cited by14 cases

This text of 448 N.W.2d 630 (Byron's Construction Co. v. North Dakota State Highway Department) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Byron's Construction Co. v. North Dakota State Highway Department, 448 N.W.2d 630, 1989 N.D. LEXIS 231, 1989 WL 143420 (N.D. 1989).

Opinion

GIERKE, Justice.

Byron’s Construction Company (Byron’s) appealed from a district court judgment affirming the decision of a three-person arbitration panel denying all claims of Byron’s against the North Dakota State Highway Department (Highway Department). We affirm in part, reverse in part, and remand for further proceedings.

Byron’s entered into a contract with the Highway Department on November 14, 1985, to reconstruct about twelve miles of State Highway No. 3 north of Rugby. Byron’s started the project during the Spring of 1986 and completed it on September 11, 1987, at which time the project was accepted by the Highway Department. The contract price for the project was $2,255,925.

On October 29, 1987, Byron’s submitted a request to the Highway Department for “an equitable adjustment” which was denied. On February 11, 1988, Byron’s submitted a demand for arbitration requesting additional compensation of $1,192,523. Byron’s submitted to the arbitrators five claims underlying its request for additional compensation. Claims 1 through 4 addressed three major issues with numerous subissues. The main issues were: (1) delay, disruption, and additional work allegedly caused by improper testing and specification interpretation by the Highway Department, (2) the required soil type and amount of borrow quantity, and (3) the tolerance requirements for gravel spread on the reconstructed roadbed. In Claim 5 Byron’s alleged that the Highway Department unjustifiably imposed sanctions against it for violation of a contract provision requiring a minimum of 10 percent minority business enterprise participation.

The arbitrators bifurcated the proceedings to first consider a notice issue. Following an evidentiary hearing on April 25-26, 1988, the arbitrators determined that for Claims 1 through 4 Byron’s failed, under Section 24-02-26.1, N.D.C.C., 1 to give the Highway Department timely written notice of its intent to claim additional compensation. The statute makes notice a precondition to arbitration, and for that reason the arbitrators dismissed those claims. The arbitrators determined that Claim 5 involved a tort issue, rather than a contract issue, and dismissed that claim for lack of jurisdiction.

The Highway Department subsequently filed a motion with the district court, under Section 32-29.2-11, N.D.C.C., to confirm the arbitrators’ dismissal of all Byron’s claims against the Highway Department. Byron’s resisted that motion and filed a motion to vacate the arbitrator’s decision under Section 32-29.2-12, N.D.C.C. The district court agreed with the arbitrators that Byron’s failed to provide timely written notice of intent to claim additional compensation for Claims 1 through 4 and that Claim 5 involved an issue of tort over which the arbitrators did not have jurisdiction. The district court entered a judgment confirming the arbitrators’ dismissal of Byron’s claims.

The following dispositive issues were raised by Byron’s on appeal:

(1) Whether the arbitrators erred in bifurcating the hearing to first consider the notice issue;
(2) Whether the arbitrators erred in concluding that Byron’s did not give timely notice of claim for additional compensation;
(3) Whether the Highway Department should be estopped from asserting that Byron’s violated the notice requirements; and
(4) Whether the arbitrators erred in determining that they had no jurisdiction to hear Claim 5.

Subsection 32-29.2-12(1), N.D.C.C., provides the grounds upon which a court can vacate an arbitration award:

*632 “1. On application of a party, the court shall vacate an award if:
“a. The award was procured by corruption, fraud, or other undue means; “b. There was evident partiality by an arbitrator appointed as a neutral, corruption in any of the arbitrators, or misconduct prejudicing the rights of any party;
“c. The arbitrators exceeded their powers;
“d. The arbitrators refused to postpone the hearing after sufficient cause was shown to postpone it or refused to hear evidence material to the controversy or otherwise so conducted the hearing, contrary to section 32-29.2-05, as to prejudice substantially the rights of a party; or “e. There was no arbitration agreement and the issue was not adversely determined in proceedings under section 32-29.2-02 and the party did not participate in the arbitration hearing without raising the objection.
“The fact that the relief was such that it could not or would not be granted by a court of law or equity is not grounds for vacating or refusing to confirm the award.”

Byron’s asserts that the arbitrators erred in bifurcating the hearing to first consider the notice issue and then to consider the merit issues, if necessary. Byron’s asserts that the relevant facts on the merits are so intertwined with the notice issue that the arbitrators could not properly decide the notice issue without first receiving evidence on the merits or substance of Byron’s claims. Byron’s asserts, in effect, that the arbitrators improperly conducted the hearing thereby substantially prejudicing Byron’s rights for which the trial court should have vacated the arbitrators’ award, under Subsection 32-29.2-12(l)(d), N.D.C.C. We disagree that the arbitrators’ conduct of the hearing was improper.

When the hearing commenced, arbitrator 'Mike Foss stated that although the arbitrators would first decide the notice issue Byron’s “can certainly bring up other things.” The arbitrators did not preclude Byron’s from introducing whatever evidence it thought necessary for the arbitrators to consider in deciding the notice issue. We conclude, therefore, that the arbitrators did not err in bifurcating the hearing and did not prejudice or compromise Byron’s right to introduce relevant evidence.

The arbitrators concluded that Byron’s was precluded from arbitrating Claims 1 through 4, and all subissues raised therein, because it did not give notice as required under Section 24-02-26.1, N.D.C.C.

Byron’s asserts that by precluding its claims, the arbitrators’ acted irrationally and exceeded their powers which, under Subsection 32 — 29.2—12(l)(c), N.D.C.C., constitutes grounds for the court to vacate the arbitrators’ decision.

When a court is requested to vacate an arbitration award because the arbitrators “exceeded their powers,” the award will be vacated only if it is “completely irrational.” Scherbenske Excavating v. North Dakota State Highway Department, 365 N.W.2d 485 (N.D.1985). “The mistakes that will void an award are those appearing on its face or gross mistakes of the arbitrators extraneously appearing as to their powers or duties, which result in real injustice or constructive fraud.” Nelson Paving Co., Inc. v. Hjelle, 207 N.W.2d 225, 230 (N.D.1973). 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gratech Co. v. North Dakota Department of Transportation
2004 ND 61 (North Dakota Supreme Court, 2004)
Gratech Co., Ltd. v. WOLD ENGINEERING
2003 ND 200 (North Dakota Supreme Court, 2003)
State v. Gratech Co., Ltd.
2003 ND 7 (North Dakota Supreme Court, 2003)
Superpumper, Inc. v. Nerland Oil, Inc.
2003 ND 33 (North Dakota Supreme Court, 2003)
Higgins v. Trauger
2003 ND 3 (North Dakota Supreme Court, 2003)
Allstate Insurance Co. v. Nodak Mutual Insurance Co.
540 N.W.2d 614 (North Dakota Supreme Court, 1995)
Little v. Tracy
497 N.W.2d 700 (North Dakota Supreme Court, 1993)
Johnson Construction, Inc. v. Rugby Municipal Airport Authority
492 N.W.2d 61 (North Dakota Supreme Court, 1992)
Byron's Construction Co. v. North Dakota Department of Transportation
463 N.W.2d 660 (North Dakota Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
448 N.W.2d 630, 1989 N.D. LEXIS 231, 1989 WL 143420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/byrons-construction-co-v-north-dakota-state-highway-department-nd-1989.