Main v. Department of Highways

142 S.E.2d 524, 206 Va. 143, 1965 Va. LEXIS 180
CourtSupreme Court of Virginia
DecidedJune 14, 1965
DocketRecord 5986
StatusPublished
Cited by32 cases

This text of 142 S.E.2d 524 (Main v. Department of Highways) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Main v. Department of Highways, 142 S.E.2d 524, 206 Va. 143, 1965 Va. LEXIS 180 (Va. 1965).

Opinion

Eggleston, C. J.,

delivered the opinion of the court.

On this appeal we are to determine whether the lower court erred in sustaining demurrers to and dismissing the original and amended petitions which Robert T. Main, Jr., and Kathryn M. Main, partners trading as Robert T. Main Company, hereinafter called the plaintiffs, filed in the lower court against the Department of Highways and the State Comptroller to recover the amounts alleged to be due by virtue of a contract which the plaintiffs entered into with the Department of Highways for the construction and improvement of a section of an interstate highway in Fairfax and Prince William counties.

The allegations of the original petition may be summarized thus:

During November, 1958 the Department of Highways advertised for bids for the construction and improvement of 8.480 miles of Interstate Route 66 in Fairfax and Prince William counties. Included *145 among the contract bid items was the placement and stabilization of approximately 196,000 cubic yards of select material “of a minimum CBR value of 12” upon that portion of the roadway prepared to receive its foundation and surface courses.

In the preparation of their bid the plaintiffs and the authorized representatives of the Department met on the site of the proposed construction, at which time these representatives designated on the ground and delineated upon the project plans a number of sources of material located within the roadway limits, which material the Department assured and represented to the plaintiffs was of sufficient “CBR value” and of suitable quality to be employed for the select material requirements of the contract.

Relying upon these assurances and representations, the plaintiffs submitted to the Department a bid proposal in the sum of $1,841,-787.39. The plaintiffs’ proposal was accepted by the Department and a contract was executed in writing on December 29, 1958. The plaintiffs commenced work under the contract on January 5, 1959.

During the latter part of 1959 and early part of 1960, the plaintiffs, in the course of their work, began to excavate and place as select material that which had been designated by the Department. After a portion of this material had been excavated and placed, the Department notified the plaintiffs that the sources originally designated were not of sufficient “CBR value,” were not of suitable quality, and could no longer be used by the plaintiffs for the procurement of such material.

The Department thereupon directed the plaintiffs to secure from sources outside the limits of the project another type of select material and to finish the graded roadway with the iatter material to a depth of six inches. Further, the Department directed the plaintiffs to place beneath the select material other material than that specified in the contract.

The plaintiffs complied with these directions of the Department and performed all conditions of the contract on their part. The extra work thus required of the plaintiffs was performed at a cost of $509,468.97 over and above the original contract price of the project.

In the further course of performance the plaintiffs laid a section of 36-inch corrugated metal pipe, in a manner expressly approved by the Department. From causes beyond the control of the plaintiffs a failure subsequently occurred in this pipe and the Department required them to excavate the pipe and replace the section which had failed, at a cost of $2,360,34.

*146 All of the work required of the plaintiffs was accepted by the Department as of August 3, 1962. Thereafter the Department, in measuring for payment the quantities of select material excavated, placed and stabilized by the plaintiffs, failed to measure the same in the manner provided for in the contract. As a result, the plaintiffs were paid a sum for such material which was $47,253.65 less than that to which they were entitled under the contract.

The Department also deducted and withheld from payment to the plaintiffs the sum of $5,310 as liquidated damages for an alleged delay of 118 days in the completion of the contract. The delay in the completion of the project resulted directly from the modifications, changes and breaches of the contract by the Department and from the opening of the project to traffic by the Department prior to the date set for the completion of the work.

Upon completion of the contract the plaintiffs made timely and proper demands for payment of the sums due them, but these demands were refused.

The defendants demurred to the petition on the grounds that (1) the matters complained of are among those upon which the plaintiffs agreed in their contract that the decision of the State Highway Commissioner would be final and binding; (2) the plaintiffs failed to allege compliance with § 105.12 of the contract with respect to claims for adjustment and disputes, compliance with which is a prerequisite to the right to recover.

It was stipulated and agreed that the construction contract between the Department of Highways and the plaintiffs and the Department’s Road and Bridge Specifications should be considered in determining the issues raised by the demurrer.

The specifications, which were integral parts of the contract, contained among others these pertinent provisions. 1

*147 The lower court sustained the demurrer, with leave to the plaintiffs to file an amended petition. In sustaining the demurrer it held that since the petition had failed to allege that the plaintiffs had complied Avith certain provisions of the Department’s specifications Avhich Avere embodied in the contract, their suit against the Department could not be maintained.

The plaintiffs filed an amended petition alleging that the Department had waived and was estopped to assert the various contractual provisions which the lower court had relied upon in sustaining the demurrer to the original petition. Further, the plaintiffs asserted that the arbitration clause embodied in § 105.13 of the specifications,, relied upon by the defendants in their demurrer, was unenforceable as a matter of law.

The defendants again demurred on substantially the same grounds as those asserted in their demurrer to the original petition, and on the additional ground that the factual allegations in the amended petition were insufficient in law to raise an estoppel or to constitute a waiver by the Department of the provisions in the contract relied upon by the latter.

The lower court sustained the demurrer to the amended petition and the plaintiffs having declined leave to file a further amendment, the petition was dismissed.

*148 In their amended petition the plaintiffs base their right to recover the cost of the. extra work in excavating and placing suitable material on the roadway, $509,468.97; the alleged shortage in the amount paid them for excavating materials, $47,253.65; the cost of relaying the pipe, $2,360.34, and the sum of $5,310 wrongfully withheld from the payment due the plaintiffs, on the breach of the express contract between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Canter v. Commonwealth of Virginia
Court of Appeals of Virginia, 2024
JT's Hauling, LLC v. Commonwealth of Virginia
Court of Appeals of Virginia, 2024
Montalla, LLC V. Commonwealth of Virginia
Court of Appeals of Virginia, 2023
Harki v. Department of Criminal Justice Services
91 Va. Cir. 387 (Norfolk County Circuit Court, 2015)
Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009
Pennsylvania Electric Coil, Ltd v. City of Danville
329 F. App'x 399 (Fourth Circuit, 2009)
Kroger, Ltd. Partnership I v. City of Richmond
69 Va. Cir. 62 (Richmond County Circuit Court, 2005)
Billups v. Carter
604 S.E.2d 414 (Supreme Court of Virginia, 2004)
Stevens v. Lemmie
40 Va. Cir. 499 (Petersburg County Circuit Court, 1996)
R. J. Crowley, Inc. v. Fairfax County School Board
41 Va. Cir. 55 (Fairfax County Circuit Court, 1996)
D. R. Hall Construction, Inc. v. Spotsylvania County Board of Supervisors
40 Va. Cir. 260 (Spotsylvania County Circuit Court, 1996)
General Excavation, Inc. v. Fairfax County Board of Supervisors
33 Va. Cir. 120 (Fairfax County Circuit Court, 1993)
Sink v. Commonwealth
413 S.E.2d 658 (Court of Appeals of Virginia, 1992)
Byron's Construction Co. v. North Dakota State Highway Department
448 N.W.2d 630 (North Dakota Supreme Court, 1989)
Westminster-Canterbury of Hampton Roads, Inc. v. City of Virginia Beach
385 S.E.2d 561 (Supreme Court of Virginia, 1989)
McIntosh v. Almaca, Inc.
8 Va. App. 124 (Court of Appeals of Virginia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
142 S.E.2d 524, 206 Va. 143, 1965 Va. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/main-v-department-of-highways-va-1965.