AMEC Civil, LLC v. Commonwealth of Virginia, etc.

CourtCourt of Appeals of Virginia
DecidedJune 16, 2009
Docket1961082
StatusPublished

This text of AMEC Civil, LLC v. Commonwealth of Virginia, etc. (AMEC Civil, LLC v. Commonwealth of Virginia, etc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AMEC Civil, LLC v. Commonwealth of Virginia, etc., (Va. Ct. App. 2009).

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Judges Kelsey, Haley and Senior Judge Bumgardner Argued at Richmond, Virginia

COMMONWEALTH OF VIRGINIA AND COMMONWEALTH OF VIRGINIA, DEPARTMENT OF TRANSPORTATION

v. Record No. 2061-08-2 OPINION BY AMEC CIVIL, LLC JUDGE D. ARTHUR KELSEY JUNE 16, 2009 AMEC CIVIL, LLC

v. Record No. 1961-08-2

COMMONWEALTH OF VIRGINIA AND COMMONWEALTH OF VIRGINIA, DEPARTMENT OF TRANSPORTATION

FROM THE CIRCUIT COURT OF MECKLENBURG COUNTY Charles E. Poston, Judge Designate

Richard Tyler McGrath, Senior Assistant Attorney General (Robert F. McDonnell, Attorney General; Maureen Riley Matsen, Deputy Attorney General; Randall H. Wintory, Assistant Attorney General; William R. Mauck, Jr.; Stephen G. Test; Matthew S. Sheldon; Williams Mullen, on briefs), for the Commonwealth of Virginia and the Commonwealth of Virginia, Department of Transportation.

Gregory S. Martin (Brian P. Heald; Roger C. Brown; J. William Watson, Jr.; Moye, O’Brien, O’Rourke, Pickert & Martin, LLP; Watson & Morrison, P.C., on briefs), for AMEC Civil, LLC.

Pursuant to Code § 33.1-387, AMEC Civil, LLC filed suit against the Virginia

Department of Transportation (VDOT) for cost overruns on a government contract. 1 In

response, VDOT argued AMEC failed to provide timely “written notice of its intention to file

1 AMEC is the successor-in-interest to Morse Diesel Civil, LLC, the original contractor. such claim” when the problems arose during the management of the contract — a statutory

requirement under Code § 33.1-386(A). VDOT also challenged several of AMEC’s claims as

unrecoverable under the contract and some aspects of AMEC’s claimed damages as unavailable

as a matter of law.

The circuit court rejected all of VDOT’s arguments and awarded AMEC a general verdict

of $21,181,941, the entire amount AMEC sought at the time of trial. AMEC requested, but the

court disallowed, an award of prejudgment interest. The parties’ cross-appeals bring each of

these issues to us for review. We reverse in part, affirm in part, and remand for further

proceedings consistent with this opinion.

I.

In 2000, VDOT awarded AMEC a contract for the construction of the Route 58

Clarksville Bypass in Mecklenburg County. The contract price, approximately $72.5 million,

included widening four miles of roadway, constructing interchanges and overpasses, and

building four new bridges, the largest spanning the John H. Kerr Reservoir. The contract called

for completion of the project in November 2003. The contract’s actual completion occurred in

2005. During the five-year project, AMEC encountered difficulties meeting deadlines and

completing tasks within its original cost estimates.

After the completion of the project, AMEC requested an additional $24 million in cost

overruns. Though bundled as a single administrative claim, AMEC’s request for damages

included over a dozen specific allegations arising out of various aspects of the five-year project.

When VDOT rejected AMEC’s administrative claim, AMEC filed suit in the circuit court. In its

amended complaint, AMEC alleged damages caused by:

“differing site conditions” involving the drilled shaft work on the Kerr Reservoir bridge, Amended Complaint ¶¶ 36-63,

-2- high lake water levels in the Kerr Reservoir, id. ¶¶ 64-71,

Work Orders 4, 6, 7, 12, and 16 authorizing deadline extensions, id. ¶¶ 72-80, 2

work performed during two “winter periods,” id. ¶¶ 81-89,

“differing site conditions” involving “boulders at the B640 bridge,” id. ¶¶ 90-95,

work site interference from “overhead power lines” at bridge B641, id. ¶¶ 96-104,

problems with the “drilled shaft concrete mix design,” id. ¶¶ 105-16,

replacing the pier 17 foundation cap on the Kerr Reservoir bridge, id. ¶¶ 117-22,

a pier cap plan error involving pier 23 on the Kerr Reservoir bridge, id. ¶¶ 123-27,

shaft layout problems with pier 18 on the Kerr Reservoir bridge, id. ¶¶ 128-33,

repair to a pier 2 column on bridge B643, id. ¶¶ 134-36, and

acceleration efforts, id. ¶¶ 144-50.

Seeking damages for each of these claims, AMEC relied on Code § 33.1-387. Under the

statute, a government contractor may institute a “civil action” claiming damages “under the

contract” so long as (i) the civil action seeks only “costs and expenses” caused by VDOT, and

(ii) the contractor submits its claim to VDOT “within the time and as set out” in Code

§ 33.1-386, which “shall be a condition precedent” to filing suit. Only administrative claims

submitted to VDOT, and denied by it, can be asserted in the civil action. See Commonwealth v.

2 Prior to trial, the circuit court dismissed AMEC’s claim relating to Work Order 12. AMEC has not appealed this ruling.

-3- Yeatts, Inc., 233 Va. 17, 20, 353 S.E.2d 717, 719 (1987) (noting the statute authorizes a civil

action “for any portion of the claim” denied by VDOT). 3

In its responsive pleadings, VDOT asserted that AMEC failed “to satisfy legal and

contractual conditions precedent to the initiation of legal action” and failed to “exhaust

administrative remedies.” Prior to trial, VDOT filed a “Motion for Leave to File Pleas in Bar.”

The pleas in bar contended that many of AMEC’s claims violated Code § 33.1-386(A), which

authorizes the assertion of an administrative claim “provided that written notice of the

contractor’s intention to file such claim shall have been given to the Department at the time of

the occurrence or beginning of the work upon which the claim and subsequent action is based.”

VDOT proffered that AMEC never provided timely, written notice of its intention to file many of

the claims asserted in the civil action. 4

AMEC resisted the motion for leave on several grounds, including the assertion that the

pleas in bar would involve a “full blown evidentiary hearing, based on a year’s worth of

voluminous discovery, which will properly occur at trial anyway.” AMEC Brief in Response to

VDOT’s Motion for Leave to File Pleas in Bar at 6. For this reason, AMEC argued, “a full and

fair determination of whether notice was provided is best suited for trial.” Id. at 8.

On December 13, 2007, the circuit court held a hearing on VDOT’s motion for leave.

Without addressing the merits of the underlying pleas, the court held the motion for “leave to file

3 For this reason, we do not address AMEC’s allegation that VDOT breached a “duty of good faith” by refusing to grant “time extensions,” by “blaming” AMEC for the lack of progress, by expressing “indifference” to settlement, or by rejecting AMEC’s claim “in bad faith.” Amended Complaint ¶¶ 137-43. AMEC did not assert a breach of any “duty of good faith” in its administrative claim. 4 VDOT also asserted AMEC similarly violated a provision of the contract which VDOT interpreted to require a written statement of the “claimed damage” during, but not after, the period of contract performance. See VDOT Road and Bridge Specification § 105.16.

-4- pleas in bar will be denied.” On January 23, 2008, the court entered a written order denying

VDOT’s motion for leave to file the pleas in bar. 5 About a month later, the parties received a

letter opinion from the circuit court addressing the merits of the pleas in bar which the court

earlier held could not be filed. The letter began with a reference to “oral argument” on “July 10,

2007” and ended with this conclusion: “Accordingly, the court finds that AMEC’s actual notice

was sufficient enough to satisfy the statutory and written notice provisions a[t] issue.” AMEC

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hallstrom v. Tillamook County
493 U.S. 20 (Supreme Court, 1990)
Barnhart v. Sigmon Coal Co.
534 U.S. 438 (Supreme Court, 2002)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Martin Bros. Contractors v. MILITARY INST.
675 S.E.2d 183 (Supreme Court of Virginia, 2009)
George v. Com.
667 S.E.2d 779 (Supreme Court of Virginia, 2008)
Little v. Cooke
652 S.E.2d 129 (Supreme Court of Virginia, 2007)
Haley v. Haley
636 S.E.2d 400 (Supreme Court of Virginia, 2006)
XL Specialty Ins. Co. v. Dept. of Transp.
611 S.E.2d 356 (Supreme Court of Virginia, 2005)
Billups v. Carter
604 S.E.2d 414 (Supreme Court of Virginia, 2004)
Welding, Inc. v. Bland County Service Authority
541 S.E.2d 909 (Supreme Court of Virginia, 2001)
Lockheed Information Management Systems Co. v. Maximus, Inc.
524 S.E.2d 420 (Supreme Court of Virginia, 2000)
Fairfax County Redevelopment & Housing Authority v. Worcester Bros.
514 S.E.2d 147 (Supreme Court of Virginia, 1999)
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)
Sabre Construction Corp. v. County of Fairfax
501 S.E.2d 144 (Supreme Court of Virginia, 1998)
County of Fairfax v. Century Concrete Services, Inc.
492 S.E.2d 648 (Supreme Court of Virginia, 1997)
Bd. of Supervisors v. FCS Bldg. Association
492 S.E.2d 634 (Supreme Court of Virginia, 1997)
Halberstam v. Commonwealth
467 S.E.2d 783 (Supreme Court of Virginia, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
AMEC Civil, LLC v. Commonwealth of Virginia, etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/amec-civil-llc-v-commonwealth-of-virginia-etc-vactapp-2009.