Sabre Construction Corp. v. County of Fairfax

501 S.E.2d 144, 256 Va. 68, 1998 Va. LEXIS 82
CourtSupreme Court of Virginia
DecidedJune 5, 1998
DocketRecord 971895
StatusPublished
Cited by19 cases

This text of 501 S.E.2d 144 (Sabre Construction Corp. v. County of Fairfax) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sabre Construction Corp. v. County of Fairfax, 501 S.E.2d 144, 256 Va. 68, 1998 Va. LEXIS 82 (Va. 1998).

Opinion

JUSTICE LACY

delivered the opinion of the Court.

In this appeal, we consider whether the trial court correctly held that Code §§ 11-66 and -70 of the Public Procurement Act, Code §§ 11-35 through -80, require that a bidder who seeks to challenge a public body’s determination that its bid was non-responsive institute legal action protesting the bid award within ten days after the public body’s written decision on the bidder’s protest.

On February 20, 1997, the County of Fairfax (the County) received bids for the construction of Phase II of the Fairfax County Public Safety Facility. Sabre Construction Corporation (Sabre) submitted a timely bid. On February 27, 1997, the County notified Sabre *70 by letter that its bid was “determined to be non-responsive” because Sabre had failed to bid on “Alternate No. 5.” In the same letter, the County informed Sabre that it would recommend awarding the contract to another bidder,’ the V.F. Pavone Construction Company (Pavone), and that its decision would be final, unless Sabre filed a protest within ten days of receiving the letter. After seeking clarification from the County regarding the appropriate procedures, 1 Sabre filed a protest with the County on March 7, arguing that the omission of Alternate No. 5 from its bid was “de minimus’'’ and should not constitute grounds for a finding of non-responsiveness. Sabre further argued that if the County added the amount of Pavone’s bid on Alternate No. 5 to Sabre’s bid, Sabre’s bid would be the lowest, and Sabre should, therefore, be awarded the contract. On March 13, the County issued its written decision denying Sabre’s protest.

On March 12, one day before the County denied Sabre’s protest, Sabre filed the instant action. In its motion for judgment, Sabre sought a determination that it was the low bidder, that its bid was responsive, and that the County’s decision to award the contract to Pavone was arbitrary and capricious.

The County filed a motion to dismiss arguing that under § 11-66, the County’s decision on a protest is final unless the bidder appeals or files legal action “within ten days of the written decision.” Since Sabre filed its legal action before the County issued its written decision on the protest, Sabre did not comply with the provisions of § 11-66 and, therefore, the court could not entertain Sabre’s motion for judgment. The trial court agreed and dismissed the case with prejudice.

On appeal, Sabre asserts that the trial court erred because 1) Sabre complied with the filing requirements of § 11-66, 2) any failure to comply with the filing requirements of § 11-66 was “procedural only” and should not defeat Sabre’s claim, and 3) Sabre’s motion for judgment was properly filed under § 11-70(A). We consider these assertions in order.

*71 I.

Section 11-66 creates the procedure for protesting a public body’s decision to award a contract. Under that section, a disappointed bidder must first protest the award or decision to award “in writing to the public body ... no later than ten days after the award or announcement of the decision to award.” The public body must respond in writing to the protest within ten days. The decision of the public body “shall be final unless the bidder or offeror appeals within ten days of the written decision by invoking administrative procedures meeting the standards of § 11-71, if available, 2 or in the alternative by instituting legal action as provided in § 11-70.” § 11-66(A). Subsection (C) of § 11-70 describes the procedure for filing an action in circuit court when the public body denies a bidder’s protest of the award of a contract or proposed award of a contract.

In the instant case, Sabre instituted its legal action before the County issued its written decision on Sabre’s protest. Nevertheless, Sabre claims that it complied with the § 11-66 requirement that it institute legal action “within ten days” of the County’s written decision on its protest. To reach this conclusion, Sabre interprets the phrase “within 10 days” as allowing an unsuccessful bidder to institute an action up to ten days before the public body releases its written response to a protest, as well as up to ten days after the decision. This interpretation, however, cannot stand when the phrase is read in the context of the entire provision.

Section 11-66 provides that the public body’s written decision is final unless a bidder “appeals” within ten days. By describing the alternatives available to the protesting bidder as “appeals,” the General Assembly made it clear that the purpose of the action is to review the public body’s written decision regarding the bidder’s protest. 3 If, as Sabre contends, the legal action could be filed prior to the release of the written decision, then the bidder would be “appealing” a decision which has not yet been issued. We conclude, therefore, that the phrase “within ten days” does not allow an “appeal” pursuant to § 11-66 to be filed prior to the public body’s release of its written decision.

*72 n.

Sabre next argues that even if it failed to comply with the filing requirements of § 11-66, its failure was “procedural only” and, under the rationale of Morrison v. Bestler, 239 Va. 166, 387 S.E.2d 753 (1990), did not require the trial court to dismiss the motion for judgment with prejudice. Sabre’s reliance on Morrison is misplaced.

The Public Procurement Act not only creates the substantive right to file an action against a county, but also imposes a special limitation on that right, namely appealing the written decision of the public body within ten days. When a special limitation is part of the statute creating the substantive right, the limitation is not merely a procedural requirement, but a part of the newly created substantive cause of action. Barksdale v. H.O. Engen, Inc., 218 Va. 496, 498-99, 237 S.E.2d 794, 796 (1977). The special limitation is a condition precedent to maintaining the claim and failure to comply with it bars the claim. Id.

Morrison did not involve the application of procedural requirements which were part of a substantive cause of action. The cause of action in Morrison was a common law tort based on medical malpractice. The procedural requirements at issue were part of a statute addressing procedures for pursuing medical malpractice claims, Code § 8.01-581.2. Thus, these procedural requirements were not special limitations and the principles applied in Morrison are not relevant to the issue in this case.

m.

Finally, Sabre argues that it had “a second, independent remedy” under Subsection (A) of § 11-70. That subsection provides, in relevant part, that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. AMEC CIVIL, LLC
699 S.E.2d 499 (Supreme Court of Virginia, 2010)
General Excavation, Inc. v. City of Harrisonburg
80 Va. Cir. 273 (Rockingham County Circuit Court, 2010)
Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009
Livingston v. Fairfax County
78 Va. Cir. 283 (Fairfax County Circuit Court, 2009)
Advance Transportation & Logistics, Inc. v. Botetourt County
77 Va. Cir. 164 (Botetourt County Circuit Court, 2008)
Alexandria City School Board v. Fox-Seko Construction, Inc.
74 Va. Cir. 92 (Alexandria County Circuit Court, 2007)
Amaram v. Virginia State University
476 F. Supp. 2d 535 (E.D. Virginia, 2007)
Board of Supervisors v. BOARD OF ZONING
626 S.E.2d 374 (Supreme Court of Virginia, 2006)
John T. Moore & Associates, P.C. v. Virginia Commonwealth University
69 Va. Cir. 200 (Richmond County Circuit Court, 2005)
Specialty Mechanical, L.L.C. v. Virginia Commonwealth University
61 Va. Cir. 121 (Virginia Circuit Court, 2003)
Fowler v. Winchester Medical Center, Inc.
59 Va. Cir. 216 (Virginia Circuit Court, 2002)
Virginia Retirement System v. Avery
551 S.E.2d 612 (Supreme Court of Virginia, 2001)
DR. WILLIAM ES FLORY v. Com.
541 S.E.2d 915 (Supreme Court of Virginia, 2001)
Dugan v. Childers
539 S.E.2d 723 (Supreme Court of Virginia, 2001)
Brown v. Ford Motor Co.
67 F. Supp. 2d 581 (E.D. Virginia, 1999)
NBS Imaging Systems, Inc. v. Virginia Department of Motor Vehicles
46 Va. Cir. 165 (Richmond County Circuit Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
501 S.E.2d 144, 256 Va. 68, 1998 Va. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sabre-construction-corp-v-county-of-fairfax-va-1998.