Com. v. AMEC CIVIL, LLC

699 S.E.2d 499
CourtSupreme Court of Virginia
DecidedSeptember 16, 2010
Docket091430
StatusPublished
Cited by6 cases

This text of 699 S.E.2d 499 (Com. v. AMEC CIVIL, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Com. v. AMEC CIVIL, LLC, 699 S.E.2d 499 (Va. 2010).

Opinion

699 S.E.2d 499 (2010)

COMMONWEALTH of Virginia, et al.
v.
AMEC CIVIL, LLC
AMEC Civil, LLC
v.
Commonwealth of Virginia, et al.

Record Nos. 091430, 091662.

Supreme Court of Virginia.

September 16, 2010.

*502 Richard Tyler McGrath, Senior Assistant Attorney General (Kenneth T. Cuccinelli II, Attorney General; Wesley G. Russell, Jr., Deputy Attorney General; Randall H. Wintory, Assistant Attorney General; William R. Mauck, Jr.; Stephen G. Test, Virginia Beach; Matthew S. Sheldon, Washington, DC; Williams Mullen, on briefs), for the Commonwealth of Virginia and the Commonwealth of Virginia, Department of Transportation.

Anne Marie Whittemore (Robert L. Hodges; J. Tracy Walker IV, Richmond; Gregory *503 S. Martin; McGuireWoods; Martin & Associates, on briefs), for AMEC Civil, LLC.

Present: KOONTZ, KINSER, LEMONS, GOODWYN, and MILLETTE, JJ., and CARRICO and RUSSELL, S.JJ.

Opinion by Justice LEROY F. MILLETTE, JR.

This appeal concerns the performance of a construction contract between AMEC Civil, LLC (AMEC)[1] and the Commonwealth of Virginia, and the Department of Transportation (collectively, VDOT). In addressing AMEC's twenty-two assignments of error and VDOT's two assignments of error and seven assignments of cross-error in the consolidated cases, we narrow the dispute to five primary issues: (1) whether AMEC gave timely notice of its claims to VDOT; (2) whether sustained elevated lake water levels constitute a differing site condition under the contract; (3) whether AMEC established its entitlement to home office overhead damages; (4) whether the "Rental Rate Blue Book" was properly used to calculate AMEC's actual costs as a basis for its award of damages; and (5) whether AMEC is entitled to pre-judgment interest as an element of its damages. We do not address those issues rendered moot by our holdings in this opinion. We affirm the judgment of the Court of Appeals in part, reverse in part, and remand for the circuit court to recalculate damages awarded to AMEC.

BACKGROUND

In May 2000, VDOT awarded AMEC a $72,479,999.49 contract for the construction of the Route 58 Clarksville Bypass in Mecklenburg County.[2] The central element of the construction project was a bridge (Bridge 616) spanning the John H. Kerr Reservoir (Kerr Lake), which required work to be performed by equipment floating on the water. The project also included ten smaller bridges and several miles of roadway. The time allotted to the project was 41 months, with a projected completion date of November 1, 2003. However, the project was not substantially completed until June 2005. Delays arose primarily from difficulties in the construction of concrete-filled drilled shafts that form the foundation of Bridge 616, and sustained elevated water levels in Kerr Lake.

In May 2006, AMEC submitted an administrative claim to VDOT pursuant to Specification § 105.16, seeking $24,792,823.43 in additional compensation.[3] AMEC's claim submission outlined what it deemed major impacts, consisting of the 2003-04 winter period, and differing site conditions, including unanticipated, sustained high water levels, and other alleged impacts delaying its performance of the contract. By letter, VDOT denied AMEC's claim.

AMEC then filed its breach of contract action against VDOT in the circuit court, under Code § 33.1-387. Code § 33.1-387 provides in part that "[t]he submission of the claim to the Department of Transportation within the time and as set out in § 33.1-386 shall be a condition precedent to bringing an action under this chapter."[4] The trial was *504 conducted by the circuit court without a jury. During litigation of the case, the circuit court issued two letter opinions.

The first letter opinion was issued before trial commenced, and addressed VDOT's argument that AMEC failed to satisfy the mandatory requirement for timely written notice, at the time of the occurrence or beginning of the work, of an intent to file claims under Code § 33.1-386 and Specification § 105.16. The circuit court held that "any writing that memorializes the fact the VDOT had actual notice of a claim could be sufficient" to satisfy the notice requirement of Specification § 105.16.

The circuit court also held that "strict compliance with legal form," through the requirement in Code § 33.1-386 that AMEC provide VDOT with written notice of its intention to bring claims when such claims first arise, "must yield to achievement of the law's primary purpose" of giving VDOT the opportunity to investigate such claims. The court determined that "AMEC's claim should not be dismissed since the public policy function of the written notice provision was achieved through actual notice" and, furthermore, that VDOT suffered no prejudice from AMEC's failure to abide by the statute's written notice provision.

After the trial concluded, the circuit court issued its second letter opinion. The circuit court rendered a "general verdict" and awarded AMEC $21,181,941.00, without interest or attorney's fees. The circuit court revisited the issue of notice, finding that VDOT had written notice through minutes of meetings and memoranda addressing the issues, exchanged between the parties, and concluded that every factual assumption made in its first letter opinion was established by the evidence at trial. VDOT and AMEC each appealed the circuit court's judgment to the Court of Appeals, which reversed in part, affirmed in part, and remanded the case for further proceedings. Commonwealth v. AMEC Civil, LLC, 54 Va. App. 240, 246, 677 S.E.2d 633, 636 (2009). We awarded these appeals.

ANALYSIS

Although AMEC's amended complaint segregated its claim into 12 separate allegations of damages, the Court of Appeals grouped the dispute into four principal issues, which we analyze as we address the issues presented in this appeal.

I. Notice

The Court of Appeals determined that the following claims were barred due to AMEC's failure to fulfill the notice requirement of Code § 33.1-386(A): drilled shaft work; defects in the drilled shaft concrete specification; concrete formwork for foundation caps, piers, and columns; pier 17 foundation cap repair; and work authorized by work orders 4, 6, 7, and 16. AMEC Civil, LLC, 54 Va. App. at 257-60, 677 S.E.2d at 642-43. The Court of Appeals held that, with respect to these claims, the circuit court erred as a matter of law by concluding that AMEC gave timely written notice of its intention to file a claim, because the court dispensed with the statutory requirement of written notice. Id. at 262-63, 677 S.E.2d at 644. The Court of Appeals also held that the circuit court's alternate ruling that written notice had been given from minutes of meetings and memoranda exchanged between the parties is unsupported by the evidence. Id.

AMEC also made a claim for acceleration damages because on some aspects of the contract, AMEC accelerated its efforts to keep on track with expected timelines and claimed damages for its acceleration efforts. The Court of Appeals held that the notice given to VDOT was untimely as to AMEC's claim for acceleration damages incurred before April 2004, but was timely as to acceleration damages incurred after April 2004. Id. at 260-62, 677 S.E.2d at 643-44.

Included in AMEC's complaint was a claim for damages due to a delay over two winter periods.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
699 S.E.2d 499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/com-v-amec-civil-llc-va-2010.