Walser v. United States

37 Cont. Cas. Fed. 76,154, 23 Cl. Ct. 591, 1991 U.S. Claims LEXIS 363, 1991 WL 151386
CourtUnited States Court of Claims
DecidedAugust 2, 1991
DocketNo. 90-96C
StatusPublished
Cited by2 cases

This text of 37 Cont. Cas. Fed. 76,154 (Walser v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walser v. United States, 37 Cont. Cas. Fed. 76,154, 23 Cl. Ct. 591, 1991 U.S. Claims LEXIS 363, 1991 WL 151386 (cc 1991).

Opinion

MARGOLIS, Judge.

This government contracts case is before the court on the defendant’s motion for summary judgment. The plaintiff contracted with the government to clear debris from a stretch of land alongside a river in West Virginia. During the course of performance, the plaintiff claims that it encountered differing site conditions, including varying water levels in the river, a state ban on burning tires, and beavers and people cutting down trees. The plaintiff alleges that these differing site conditions caused it to perform extra work and incur additional costs, and seeks an equitable adjustment in the contract price. The defendant argues that none of the conditions justify an equitable adjustment for differing site conditions. After careful consideration, and after hearing oral argument, this court grants the defendant’s motion for summary judgment.

FACTS

On September 30, 1986, the plaintiff, Jack Walser d/b/a Jack Walser Construction Company (“Walser”), entered into a contract with the Soil Conservation Service (“SCS”) of the United States Department of Agriculture to remove debris on a section of the Cheat River in West Virginia. The contract price was $120,432, and the contract was to be completed within 64 days after the notice to proceed. Walser began work on the contract site on October 15, 1986, and completed the work in 65 days. The work was timely after a one-day [593]*593extension. The results were accepted by the SCS on December 18, 1986.

Walser filed a claim with the contracting officer on January 5, 1987, seeking an equitable adjustment to the contract price. The claim was denied by the contracting officer on January 15, 1987. Walser then filed suit in the United States Claims Court, but that suit was dismissed without prejudice for failure to submit a properly certified claim to the contracting officer. On September 5, 1989, Walser resubmitted a certified claim to the contracting officer, which was denied on September 19, 1989.

In this court, Walser claims that it is entitled to an equitable adjustment of the contract price under paragraph H-4 of the contract due to differing site conditions. Walser asserts five differing site conditions as grounds for its equitable adjustment claim: (1) the water level of the river fell between the day the site was shown for purposes of bidding and the first day of work on the site, leaving considerably more debris to be cleared than was visible at the job showing; (2) a state ban on the practice of using tires to keep the debris pile burning was enforced, making it more difficult to eliminate some of the waste; (3) excessive rainfall in November and December 1986, washing additional debris into the construction area which Walser removed; (4) beavers cut down trees, leaving additional debris which Walser cleaned up; and (5) unauthorized people entered the job site and cut down trees for firewood, leaving additional debris which Walser cleared.

As a result of these conditions, Walser claims that the contract was completed in 65 days, rather than the projected time of 20 days. Walser seeks an equitable adjustment of $124,853.13, plus interest, which it contends represents the amount of extra work that was required due to the differing site conditions.

DISCUSSION

The contract provides that there are two types of differing site conditions which could lead to equitable adjustments:

(1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or
(2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the contractor provided for in the contract.

Contract 11 H-4 (FAR 52.236-2) Differing Site Conditions. In a Type I case, the issue concerns whether the site condition differs from a representation made about the site in the contract itself. See, e.g., Seroidone Construction Corp. v. United States, 19 Cl.Ct. 346, 360 (1990), aff'd, 931 F.2d 860 (Fed.Cir.1991); Dawco Construction, Inc. v. United States, 18 Cl.Ct. 682, 687 (1989), aff'd in part and rev’d in part on other grounds, 930 F.2d 872 (Fed.Cir. 1991). In our case, the contract contained no representations concerning the conditions at issue.1 Therefore, our case is a Type II case.

Walser must prove that the physical conditions on the site were unknown and unusual. See Charles T. Parker Construction Co. v. United States, 193 Ct.Cl. 320, 333, 433 F.2d 771, 778 (1970). In a differing site condition case, “a Government construction contractor seeking to establish a ‘category two’ changed condition is confronted with a relatively heavy burden of proof.” Id. In proving its case, Walser must show that it did not know about the physical condition, that it could not have anticipated the condition from inspection or general experience, and that the condition varied from the norm in similar contracting work. Lathan Company, Inc. v. United States, 20 Cl.Ct. 122, 128 (1990) (citing cases). This court will analyze the five alleged differing site condi[594]*594tions to determine whether an equitable adjustment to the contract is warranted.

Water Level

Walser argues that the water level of the river fell between the day the site was shown for purposes of bidding and the first day of work on the site, leaving considerably more debris to be cleared than was visible at the job showing. Walser contends that this situation represents a different site condition warranting an equitable adjustment. Walser also asserts that the level of the Cheat River at the time of the job showing in comparison to the water level at the time when contract work began is a genuine issue of material fact in dispute precluding summary judgment. In this connection, Walser contends that it is not reasonable to expect that Walser should have anticipated a reduction in the water level and should have anticipated the nature and extent of the additional debris to be removed.

The contract mandates that it is the responsibility of the contractor to take actions to ascertain “the uncertainties of weather, river stages, tides, or similar physical conditions at the site,” and also that the “failure of the Contractor to take the[se] actions ... will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.” Contract U H-l (FAR 52.236-3) Site Investigation and Conditions Affecting the Work. To prove its case, Walser must show that it encountered a situation materially different from the “known” or the “usual.” See Charles T. Parker, 193 Ct.Cl. at 333, 433 F.2d at 778. Even assuming that the water level changed from the time of the job showing to the initiation of work, the government presents unrefuted evidence 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. AMEC CIVIL, LLC
699 S.E.2d 499 (Supreme Court of Virginia, 2010)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,154, 23 Cl. Ct. 591, 1991 U.S. Claims LEXIS 363, 1991 WL 151386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walser-v-united-states-cc-1991.