Manuel Bros. v. United States

55 Fed. Cl. 8, 2002 U.S. Claims LEXIS 369, 2002 WL 31958797
CourtUnited States Court of Federal Claims
DecidedDecember 23, 2002
DocketNo. 97-4C
StatusPublished
Cited by8 cases

This text of 55 Fed. Cl. 8 (Manuel Bros. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manuel Bros. v. United States, 55 Fed. Cl. 8, 2002 U.S. Claims LEXIS 369, 2002 WL 31958797 (uscfc 2002).

Opinion

OPINION

HORN, Judge.

The plaintiff, Manuel Brothers, Inc. (MBI), filed its complaint requesting this court to award damages arising out of a lump sum price construction contract with the Federal Aviation Administration (FAA). MBI was awarded Contract Number DTFA07-94-C-03079 (contract), in the amount of $5,235,455.00, on March 9, 1994. The scope of the contract was for the construction, including excavation, of concrete encased ductbanks with associated manholes for the installation of fiber optic cable at the Dallas/Fort Worth Airport, Texas (DFWA). MBI has claimed damages in the amount of $2,211,744.79. Although encompassed in one very general breach of contract count, following trial, it appears that the breach claim [12]*12is based largely on the defendant’s alleged breaches and other obligations as follows: 1) the defendant’s failure to disclose its superior knowledge as to the true soil conditions at the contract site; 2) fading to clarify the misimpression created by the defendant’s representation that the soil conditions at the contract site were normal; 3) the government’s breach of the implied duty to cooperate by failing to provide sufficient escorts onto the aircraft operations area (AOA) so as not to unduly restrict MBI’s access to work areas and the denial of permanently extended work shifts; 4) the government’s interference with the plaintiffs right and plan to complete the majority of its work by mid-November 1994; 5) the defendant’s submission of defective and incomplete design drawings which inaccurately depicted underground utilities or which failed to show existing utilities; 6) the government’s failure to respond in a timely manner to requests for information and clarification necessitated by the defective design drawings; and 7) the government’s failure to fully compensate MBI for the costs of the defective drawings and differing site conditions.

FINDINGS OF FACT

I. MANUEL BROTHERS, INC.

MBI was formed by Richard, John and Al Manuel in 1977 as a general contractor for the construction of telecommunications duet-banks, the installation of copper, now fiber optic cable, and other similar underground communication installations. At the time of the contract at issue, the company had $15 million in annual revenue, John and Al had retired, Richard Manuel was president of MBI, and Richard’s son, Paul Manuel, was the controller. As controller, Mr. Paul Manuel assisted the project manager of a given contract in the organization of the necessary manpower, contract equipment, including rental agreements and purchasing, payroll and equipment expenses, as well as other accounting responsibilities.

During contract solicitation and through performance, Gary Smith was MBI’s general manager, later becoming president of MBI. At the time of the contract, Mr. Smith’s duties included estimating projects on which the company bid, overseeing projects as they were performed, purchasing materials for the various jobs, job costing, and quality control of projects through the supervision of the on-site project managers. From the start of construction until January 1995, the on-site project manager for the contract was Robert Fureby. Duane Fureby, Mr. Robert Fure-by’s brother, subsequently became the on-site project manager until the contract was completed. Mr. Robert Fureby’s duties began before construction, however, when he estimated and prepared the contract bid that MBI submitted to the FAA. Specifically, Mr. Robert Fureby prepared the estimates for excavation, materials required for the project, and prepared the production estimates. In addition, Mr. Robert Fureby, on behalf of MBI, attended the site visit and the pre-bid conference held by the FAA at the DFWA.

II. CONTRACT SOLICITATION

On December 6, 1993, the Acquisition Section (ASW-55A) of the FAA issued solicitation number DTFA07-93-B-00030 for the performance of the following: “Construction to include excavation, concrete encased duct-banks with associated manholes, installation of fiber optics cable to include but not limited to crossing beneath airport roads, taxi ways, runways, etc. at the Dallas/Fort Worth International Airport, Texas, in accordance with the attached specifications and drawings” (DFWA south ductbank loop project). The procurement was unrestricted regarding business size and had an estimated bid range of $5 million to $10 million. MBI learned of the solicitation through the Commerce Business Daily (CBD)1 and ordered the plans and specifications for the project shortly thereafter. The plans and specifications received by MBI included the description of the project, plans and specifications for con[13]*13struction of the project, and all other terms and conditions that would form the basis of the contract once a bid was accepted and the contract was executed by the potential offer- or and the defendant.

The solicitation required the offeror to begin performance within five calendar days after receiving the Notice to Proceed and complete the contract within 365 calendar days. The offeror was required to supply performance and payment bonds within fifteen days after contract award.

The solicitation included Part I, Section G, “Contract Administration Data.” Under subsection G-l, “Order of Precedence—Construction,” of Part 1, Section G, the contract provided that:

Any inconsistency in this solicitation shall be resolved by giving precedence in the following order: (a) the Schedule (excluding the specifications); (b) representations and other instructions; (c) contract clauses; (d) project specifications; (e) project drawings; and (f) other documents, exhibits, and attachments.

The solicitation also incorporated by reference, under Federal Acquisition Regulation (FAR) 52.252-2, numerous clauses that would govern the contract. See 48 C.F.R. Chapter 1 (1994). In particular, the solicitation incorporated FAR 52.236-2 “Differing Site Conditions,” 52.236-3 “Site Investigation and Conditions Affecting the Work,” 52.248-3 “Value Engineering-Construction,” 52.232-5 “Payments under Fixed-Price Construction Contracts,” 52.212-12 “Suspension of Work,” 52.214-6 “Explanation to Prospective Bidders,” and 52.243-4 “Changes.”

The specifications of the solicitation detailed the restrictions the potential contractor would encounter working on the AOA of the DFWA. The specifications required by the FAA identified restrictions on the work shifts available to the contractor, runway closures during construction, various work site requirements and restrictions, the escorting of construction vehicles, safety and security precautions, height restrictions and requirements, barricading and marking of work areas, procedures for working around underground cable and utilities, and other AOA restrictions. In addition, the DFWA provided its own requirements which were integrated into the solicitation. The DFWA work limitations included work restrictions in and around the AOA, varied airport access requirements, and other restrictions, including enforcement provisions for these DFWA procedures.

III. PRE-BID CONFERENCE

The solicitation provided interested offer-ors with notice of a pre-bid conference in early January 1994, for the purpose of providing a question and answer session on the DFWA south ductbank loop project. The pre-bid conference notification also encouraged the potential offerors to make a site visiVinspeetion of the project the day of the pre-bid conference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
L.W. Matteson, Inc. v. United States
61 Fed. Cl. 296 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 8, 2002 U.S. Claims LEXIS 369, 2002 WL 31958797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manuel-bros-v-united-states-uscfc-2002.