Gardner Displays Company v. The United States

346 F.2d 585, 171 Ct. Cl. 497, 1965 U.S. Ct. Cl. LEXIS 129
CourtUnited States Court of Claims
DecidedJune 11, 1965
Docket336-56
StatusPublished
Cited by28 cases

This text of 346 F.2d 585 (Gardner Displays Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gardner Displays Company v. The United States, 346 F.2d 585, 171 Ct. Cl. 497, 1965 U.S. Ct. Cl. LEXIS 129 (cc 1965).

Opinion

PER CURIAM.

This case was referred pursuant to former Rule 45(a), now Rule 57(a), to Trial Commissioner C. Murray Bernhardt with directions to make findings of fact and recommendation for a conclusion of law. The commissioner has done so in an opinion and report filed on March 3, 1964. Exceptions were filed by the defendant, briefs were filed by the parties and the case was submitted to the court on oral argument of counsel. Since the court agrees with the commissioner’s findings, his opinion, and his recommended conclusion of law, as hereinafter set

forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore entitled to recover and judgment is entered for the plaintiff in the amount of thirty-nine thousand, seven hundred fifty-four dollars and two cents ($39,754.02) *

OPINION OF COMMISSIONER

The central question here is whether a manufacturer of rubber terrain maps under contract with the Army may recover the increased costs of latex, the principal raw material ingredient, brought about as an economic byproduct of the Korean war during a period of Government-caused delay in inspection and approval of a preproduction model, where despite the delay the contractor still managed to perform within the contract time limits. United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039 (1944) says (to the defendant) he cannot, while Metropolitan Paving Co. v. United States, 325 F.2d 241, 163 Ct.Cl. 420 (1963), says that he can, but as we shall see the conflict is more apparent than real and rests upon a difference in operating facts.

Antecedent to this is whether the plaintiff prime contractor may maintain this action on behalf of its subcontractor Toyad, for the uncompensated loss was Toyad’s. The subcontract contains no provision resembling the exculpatory type of clause which freed both the prime contractors and the Government from liability in such cases as Severin v. United States, 99 Ct.Cl. 435 (1943), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1943); Continental Illinois National Bank & Trust Co. v. United States, 81 F.Supp. 596, 112 Ct.Cl. 563 (1949); Continental Illinois National Bank & Trust Co. v. United States, 115 F.Supp. 892, 126 Ct.Cl. 631 (1953). Quite logically where the subcontract absolves the prime contractor from liability to his subcontractor there *587 can be no derivative liability of the Government to the subcontractor even where the Government would otherwise be culpable, for actual damage to the prime is a prerequisite to recovery either for himself or for those subordinate to him. Where the subcontract does not negate liability of the prime to his sub (J. W. Bateson Co. v. United States, 163 F.Supp. 871, 143 Ct.Cl. 228 (1958)), or where it is silent as to such liability (J. L. Simmons Co. v. United States, 304 F.2d 886, 158 Ct.Cl. 393 (1962)), recovery against the Government by one on behalf of another is generally permitted. Thus the present action may be maintained by the plaintiff for Toyad.

The Government misled and then delayed the plaintiff unreasonably. While desiring the production of latex terrain maps with a smooth surface, the Government inadvertently led the plaintiff astray at the outset by advising it to bid on the basis of a prototype produced by the Army Map Service which had a rough and pebbly surface! The plaintiff predicated its low bid 6n a fixed-price subcontract with Toyad for latex, which Toyad in turn based on the prevailing market price with a reasonable margin for normal increases. All of this was in 1950 on the eve of the Korean war which started June 25, 1950, although the contract itself was entered into in July and backdated to June 26, 1950. The price of latex advanced rapidly from then to the end of the year when price controls were instituted. Toyad could not adequately protect itself against price advances by purchasing and storing all of its contract requirements for latex, for although it had sufficient storage facilities it is not considered feasible to store latex for longer than four months because of its perishable nature, even under controlled conditions. • Toyad actually ordered its total latex requirements prior to the Korean war and so insured its availability when needed, but the price at the time of delivery governed, and naturally Toyad was reluctant to run the risk of spoilage should circumstances prevent use of the latex during its storable life. The plaintiff submitted for inspection a preproduction sample map on August 30, 1950, which was eventually rejected because of the discovery.....by_ Army afterthought that the surface was too rough to permit marking of roads, etc., yvith an ink roller, even though it was faithful to the surface texture of the prebid Army prototype. The contract nowhere described the desired surface • texture, nor did it affirmatively require the texture to be such as to take markings from an ink roller. The inference that the contractor should have divined this requirement from the fact that it was to provide ink rollers as part of the map kit is more than countervailed by the direction to copy the prebid prototype, the only tangible clue the Government had provided as to the surface texture it wanted.

The plaintiff’s preproduetion sample rejected by the Government following the inspection on August 30,1950, represented the end product of an elaborate sequence of models, plaster molds, and cast aluminum production molds. Rejection on grounds of surface texture meant the scrapping of the aluminum molds and the repreparation of a new surface for the plaster mold, followed by recasting the aluminum molds. These were expensive and time-consuming operations. Their difficulty was enhanced by the inexplicable failure of the Government to advise the plaintiff of the surface it wanted or how it was to be achieved. By December 1950 the plaintiff prepared additional preproduction samples having a smoother surface texture, but through further procrastination on the Government’s part the final approval for production was withheld and not issued until February 19, 1951, while under conditions of reasonable cooperation approval should have been forthcoming about November 1, 1950. On the one hand the Government expressed to the contractor its urgent need for the maps for military training purposes, on the other by its failure to act it delayed the contractor’s performance, and all the while the cost of latex was zooming until it was stabilized by a *588 pnce freeze on January 1, 1951. By issuing a change order in June 1952 offidaily defining for the first time desired surface texture and providing for the payment to plaintiff of $5,505.51 as an equitable adjustment for the cost of changing molds the defendant by1 strong implication admitted not only that it had changed its original surface texture requirements, but also that it was capable of reducing the description of the desired surface texture to writing. It did not, of course, admit to unreasonable delay in the circumstances surrounding the change, but this is abundantly clear in the report of facts accompanying this opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
System Fuels, Inc. v. United States
79 Fed. Cl. 37 (Federal Claims, 2007)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Precision Pine & Timber, Inc. v. United States
63 Fed. Cl. 122 (Federal Claims, 2004)
Gentex Corp. v. United States
61 Fed. Cl. 49 (Federal Claims, 2004)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Croman Corp. v. United States
49 Fed. Cl. 776 (Federal Claims, 2001)
Coast Federal Bank, FSB v. United States
48 Fed. Cl. 402 (Federal Claims, 2000)
R.C. Construction Co. v. United States
42 Cont. Cas. Fed. 77,389 (Federal Claims, 1998)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Castle Construction Co. v. Owens & Woods Partnership
590 So. 2d 186 (Supreme Court of Alabama, 1991)
Stevens v. United States
21 Cl. Ct. 195 (Court of Claims, 1990)
CCM Corp. v. United States
35 Cont. Cas. Fed. 75,590 (Court of Claims, 1988)
Albermarle Bank & Trust Co. v. United States
12 Cl. Ct. 704 (Court of Claims, 1987)
Town of North Bonneville v. United States
11 Cl. Ct. 694 (Court of Claims, 1987)
H.H.O., Inc. v. United States
32 Cont. Cas. Fed. 73,393 (Court of Claims, 1985)
Interstate Coatings, Inc. v. United States
32 Cont. Cas. Fed. 73,208 (Court of Claims, 1985)
DeBarros v. United States
32 Cont. Cas. Fed. 72,614 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
346 F.2d 585, 171 Ct. Cl. 497, 1965 U.S. Ct. Cl. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gardner-displays-company-v-the-united-states-cc-1965.