Levering & Garrigues Co. v. United States

73 Ct. Cl. 566, 1932 U.S. Ct. Cl. LEXIS 519, 1932 WL 2094
CourtUnited States Court of Claims
DecidedJanuary 18, 1932
DocketNo. D-418
StatusPublished
Cited by16 cases

This text of 73 Ct. Cl. 566 (Levering & Garrigues Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levering & Garrigues Co. v. United States, 73 Ct. Cl. 566, 1932 U.S. Ct. Cl. LEXIS 519, 1932 WL 2094 (cc 1932).

Opinion

Williams, Judge,

delivered the opinion:

The plaintiff, on October 17, 1919, entered into a contract with the Navy Department, through the Bureau of Yards and Docks, whereby the plaintiff agreed to construct and complete, at the Naval Academy, Annapolis, Maryland, an addition to the existing power house, including roof drainage and electric lighting systems, and to construct timber pile and concrete foundations for an ash bunker, and make certain alterations to the existing building.

The plaintiff was to receive the sum of $81,877 for the completed work. The contract further provided that for each timber pile in place, based on the length of 55 linear feet, measured from point to cut-off, in excess of or less than the number called for on the drawings, there was to be added to or deducted from the sum of $81,877 the sum of $41.25 or $27.50, respectively; and for each linear foot of timber pile in place in excess of or less than 55 linear feet measured from point to cut-off there was to be added to or deducted from the amount the sum of $0.75 or $0.10, respectively.

The work was to be completed within 110 calendar days and was to be performed in accordance with certain specifications prepared by the Bureau of Yards and Docks and made a part of the contract. The plaintiff completed the contract 210 days after the time specified and was paid the full contract price, together with certain additional amounts allowed for extras under change orders, less the sum of $2,025, [573]*573deducted as liquidated damages, and $434.22, withheld by the Government on the execution of the qualified release.

The plaintiff in this suit seeks to recover a sum aggregating $22,145.25, based on the following items:

(1) For excessive cost of the piling work resulting from insufficient and misleading information furnished by the defendant as to the subsurface conditions at the site of the building_$10,135.58

(2) Extra cost of face brick on account of the arbitrary and unreasonable delay of defendant in making approval of the brick to be used_ 797. 65

(3) Damage and loss occasioned by reason of 210 days’ delay in completing the work caused by the action of the defendant_ 8, 615. 86

(4) Liquidated damages assessed and retained by defendant from amount due under the contract for 27 days’ delay_ 2, 025.00

(5) Difference between the amount claimed by plaintiff and the amount allowed by the defendant on account of extra cost incurred in redriving and retesting 28 rejected piles_._ 136. 94

(6) Amount retained by the defendant (2%) on the execution of the qualified release_ 434. 22

These claims will be considered in the order of their statement.

(1) Claim for $10,135.58 based on loss and damage sustained on account of extra costs of doing the 'piling work.— The building was to be erected of heavy reinforced concrete, constructed on a pile and concrete foundation. In estimating what the cost of the piling work required under the contract would be the plaintiff relied on the provision of paragraph 19 of the specifications, that “ For purposes of estimating, proposals shall be based on the length of pile in place between point and cut-off of fifty-five feet,” and on the plans shown to its representative by the public-works officer, as correctly showing the subsurface condition at the site where piles were to be driven.

Paragraph 187 of the specifications provides that “ such information as the Government possesses regarding sewers, pipes, and other construction beneath the surface of the ground on the site of the work may be obtained from the [574]*574public-works officer at the Naval Academy.” The plaintiff had a right to rely upon this representation and to assume that the plans submitted to its representative, purporting-to show the subsurface conditions at the site, contained all the information in the possession of the Government relating-to that matter, and that they revealed the true subsurface conditions at the site.

The existence of a sunken sea wall running diagonally across the site, which seriously impeded the work of driving the piles and greatly increased its cost to plaintiff, was not shown on„ the plans exhibited by the public-works officer to plaintiff’s representative, although such plans had been prepared by the Navy Department before that time, and were-then in the possession of the Government. The failure of the defendant to disclose this information to the plaintiff amounted to a deceptive representation of the subsurface conditions at the site. The fact that the public-works officer did not have the plans showing the sunken sea wall in his-possession, and did not know of their existence at the time-he talked with plaintiff’s representative, and that he acted in good faith, believing he was furnishing plaintiff with all the information in the possession of the Government, is immaterial. The plaintiff was entitled to have such information, as to the subsurface conditions, as was in possession of the Government, and not as the defendant contends, only such as happened to be in the possession of the public-works-officer.

The defendant having misled the plaintiff as to the existence of buried construction beneath the surface of the ground where the piles were to be driven, is liable to the plaintiff' for extra cost incurred in doing the piling work which such obstruction occasioned. GKristie v. United States, 237 U. S. 234; Hollerbach v. United States, 233 U. S. 165; United States v. Spearin, 248 U. S. 132.

The fact that the specifications provide that “ The Government does not guarantee the information given to be-correct or that other buried construction will not be encountered, and does not assume any risk or responsibility in-connection therewith,” and that “ intending bidders will have the privilege of examining the site, and they should [575]*575satisfy themselves as to existing conditions,” does not relieve the defendant from damages arising out of the misrepresentations as to subsurface conditions at the site. United States v. Atlantic Dredging Company, 253 U. S. 1.

The plaintiff has failed, however, to establish by competent proof the extra costs it incurred, if any, in doing the piling work because of the sea wall. The plaintiff made no separate "bid for the piling work. Compensation for this work was included in the lump sum contract price of $81,877, except as that sum might be increased or decreased in accordance with the provisions of paragraph six of the contract, set out in Finding II, and heretofore referred to. Plaintiff has been paid $1,987.45 in accordance with that provision of the contract. 'It is not claimed the amount paid was not properly computed, or that the plaintiff is entitled to a larger .amount under that provision of the contract. The plaintiff, therefore, can recover in respect to the work of driving the piles only such amount as it cost the plaintiff to do the work, in excess of what it would have cost had the sea-wall obstruction not been present.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Nelse Mortensen & Co. v. United States
301 F. Supp. 635 (E.D. Washington, 1969)
Gardner Displays Co. v. United States
171 Ct. Cl. 497 (Court of Claims, 1965)
Gardner Displays Company v. The United States
346 F.2d 585 (Court of Claims, 1965)
Morrison-Knudsen Company, Inc. v. The United States
345 F.2d 535 (Court of Claims, 1965)
Morrison-Knudsen Co. v. United States
170 Ct. Cl. 712 (Court of Claims, 1965)
Flippin Materials Co. v. United States
312 F.2d 408 (Court of Claims, 1963)
George A. Fuller Co. v. United States
69 F. Supp. 409 (Court of Claims, 1947)
General Contracting Corp. v. United States
96 Ct. Cl. 255 (Court of Claims, 1942)
Schmoll v. United States
91 Ct. Cl. 1 (Court of Claims, 1940)
C. W. Blakeslee & Sons, Inc. v. United States
89 Ct. Cl. 226 (Court of Claims, 1939)
MacDonald Engineering Co. v. United States
88 Ct. Cl. 473 (Court of Claims, 1939)
Sobel v. United States
88 Ct. Cl. 149 (Court of Claims, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ct. Cl. 566, 1932 U.S. Ct. Cl. LEXIS 519, 1932 WL 2094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levering-garrigues-co-v-united-states-cc-1932.