Ittner v. United States

43 Ct. Cl. 336, 1908 U.S. Ct. Cl. LEXIS 44, 1907 WL 857
CourtUnited States Court of Claims
DecidedApril 13, 1908
DocketNo. 29642
StatusPublished
Cited by16 cases

This text of 43 Ct. Cl. 336 (Ittner v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ittner v. United States, 43 Ct. Cl. 336, 1908 U.S. Ct. Cl. LEXIS 44, 1907 WL 857 (cc 1908).

Opinion

Atkinson, J.,

delivered the opinion of the court.

April 4, 1903, a contract was executed between the United States and plaintiff for the construction of a hospital building at Chickamauga Park, Ga., in accordance with plans and specifications attached, wherein it was stipulated that plaintiff should be paid the sum of $59,472 for said work. The contract contained a provision that work on the building should begin April 6, 1903, and be completed on or [349]*349before January 1, 1904. The contract, however, was not approved by the Quartermaster-General until April 28, 1903, twenty-two days subsequent to the time specified for the beginning of the work under the contract.

Articles 2 and 3 of the contract, which are material in the issue before us, are in the language following:

“Article 2. The time of the completion of the work being an essential element and consideration of this contract, it is further agreed that in case of the failure of the party of the second part to complete in all respects the work called for under this contract on or before the date stipulated for such completion, the loss resulting to the United States from such failure, as liquidated, ascertained and fixed damages is hereby fixed at twenty (20) dollars for each and every day that the work on the building remains uncompleted after such date, and it is hereby stipulated that the party of the first part may withhold such amount as liquidated damages from any money due the party of the second part from the United States, and should the amount due the said party of the second part be insufficient to cover the loss at the above rate, then the party of the second part shall pay the excess of such damages over the amount due; provided, that delays caused by quarantine restrictions, storms, floods, or other violence of the elements may, upon the recommendation of the proper officer and approval by the Quartermaster-General, be excluded in determining the amount of said damages.
“Article 3. That work on this contract shall commence on or before the sixth day of April, nineteen hundred and three, shall be carried forward with reasonable dispatch, and be completed on or before the first day of January, nineteen hundred and four.”

After considerable work had been done it became manifest to plaintiff, as shown by the findings, that he could not complete the work within the time required by the contract, and on December 9, 1903, he requested an extension of time, and in this request he obligated himself in case his request was granted to complete the work within a reasonable time, naming ninety days thereafter, and agreeing to become liable for any damages which might arise should he fail to carry out his obligation under such waiver, and agreeing further that all other provisions of the original contract should remain in full force and effect.

[350]*350The surety company on plaintiff’s bond agreed to the waiver of the time limit, but said nothing about any other limitation for completion, simply requesting that the contractor be “ permitted to proceed with his work with reasonable dispatch and finish the same within reasonable time; what constitutes reasonable dispatch and reasonable time to be decided by the officer in charge.”

The officer- in charge of the construction of the building favorably recommended plaintiff’s application for an extension of time in which to complete his contract. The Quartermaster-General, after due consideration, decided that The time limit of said [this] contract is hereby waived in accordance with office circulars of November 8, 1902, and August 6, 1903, the conditions of which you will communicate to the contractor,” which was accordingly done by the officer in charge of the work.

The circular letters to Avhich reference was made by the Quartermaster-General authorized the agents of the United States in his department to waive the time limits of contracts, provided applications therefor are made in writing, and the consent of their sureties are appended to their requests for waivers, instead of annulling the original contracts, and stating also that reasonable time may be allowed for the completion of the work under their contracts.

The defendants contend, however, that the Quartermaster-General did not possess the power to waive the provisions of a contract which stipulated liquidated damages for breach thereof, and they, therefore, insist that the terms of section 2 of the contract, supra, should be literally carried out. The findings show that the defendants’ agent who was superintending the construction of the building and the Quartermaster-General both treated plaintiff as free from fault, and not only waived the time limit, but advised that no damages should be assessed against him.

We do not deem it necessary to consider the waiver respecting the damages assessed against the plaintiff, since he was prevented by the defendants from executing his contract in accordance with its terms (Finding I). It stated that time is an essential feature of the contract, but it also provides that it must be approved by the Quartermaster-General [351]*351before it becomes binding. It was not so approved until twenty-two days after the time fixed for beginning the work by plaintiff. It is well settled that where one of the parties to a contract demands strict performance as to time by the other party, he must comply with all of the conditions requisite to enable the other party to perform his part, and a failure on the part of the one demanding performance to do all the preliminary work required by him to enable the other party to complete the work within the time limit, operates as a waiver of the time provision in the contract.

It appears that the plaintiff completed the construction of the building in this case, within a reasonable time, and that the defendants incurred no expense and suffered no loss in consequence of such delay.

In the case of Dannat et al. v Fuller (120 N. Y. R., 550), in passing upon a contract very similar to the one at bar, the court decided: “ It consequently appears to us that the failure of the plaintiffs to perform on their part operated as a waiver of the performance of the contract as to time, and the defendant consequently had the right to perform his part of the contract within a reasonable time after the plaintiffs had completed their part. The allowing of the defendant thirty days additional time in which to complete the contract, as was done in this case by the referee, does not restore the provisions of the contract which had been waived. It was, in effect, the making of a new contract for the parties by the referee. The defendant having contracted to do this work within a specified time, was bound to have his servants and employees on hand ready to perform within that time. He had the right to assume that the plaintiffs would perform on their part, and therefore could properly contract with other parties for the time of himself and employees for any future time not covered by his contract with the plaintiffs. They could not prevent his performance by delays on their part for even a greater period than that specified in the contract in which he was to perform, and then require him to proceed immediately, for this would require him to do the work at another time than that named in the contract, and when he might be under obligations to other- parties.”

[352]*352The same doctrine is laid down in the case of Standard Gas Light Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hirsch v. United States
94 Ct. Cl. 602 (Court of Claims, 1941)
Graybar Electric Co. v. United States
90 Ct. Cl. 232 (Court of Claims, 1940)
MacDonald Engineering Co. v. United States
88 Ct. Cl. 473 (Court of Claims, 1939)
Levering & Garrigues Co. v. United States
73 Ct. Cl. 566 (Court of Claims, 1932)
Christensen Construction Co. v. United States
72 Ct. Cl. 500 (Court of Claims, 1931)
S. R. H. Robinson & Son Contracting Co. v. United States
53 Ct. Cl. 536 (Court of Claims, 1918)
American Dredging Co. v. United States
49 Ct. Cl. 350 (Court of Claims, 1914)
Hinkley v. United States
49 Ct. Cl. 148 (Court of Claims, 1913)
Laidlaw-Dunn-Gordon Co. v. United States
47 Ct. Cl. 271 (Court of Claims, 1912)
United Engineering & Contracting Co. v. United States
47 Ct. Cl. 489 (Court of Claims, 1912)
Callahan Construction Co. v. United States
47 Ct. Cl. 229 (Court of Claims, 1912)
Cathell v. United States
46 Ct. Cl. 368 (Court of Claims, 1911)
Wyant v. United States
46 Ct. Cl. 205 (Court of Claims, 1911)
Moore v. United States
46 Ct. Cl. 139 (Court of Claims, 1910)
New Jersey Foundry & Machine Co. v. United States
44 Ct. Cl. 178 (Court of Claims, 1909)
Little Falls Knitting Mill Co. v. United States
44 Ct. Cl. 1 (Court of Claims, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
43 Ct. Cl. 336, 1908 U.S. Ct. Cl. LEXIS 44, 1907 WL 857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ittner-v-united-states-cc-1908.