Laidlaw-Dunn-Gordon Co. v. United States

47 Ct. Cl. 271, 1912 U.S. Ct. Cl. LEXIS 18, 1911 WL 1353
CourtUnited States Court of Claims
DecidedNovember 11, 1912
DocketNo. 30611
StatusPublished
Cited by3 cases

This text of 47 Ct. Cl. 271 (Laidlaw-Dunn-Gordon Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laidlaw-Dunn-Gordon Co. v. United States, 47 Ct. Cl. 271, 1912 U.S. Ct. Cl. LEXIS 18, 1911 WL 1353 (cc 1912).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court.

The question now arises on the claimant’s motion for a new trial on the ground substantially that the judgment rendered is contrary to law.

The claimant, a corporation existing under the laws of the State of Ohio, entered into the contract made part of the petition herein with the United States through he Isthmian Canal Commission, dated July 13, but not signed by the claimant until July 27, and by the chairman of the Isthmian Canal Commission August 29, 1906, whereby the claimant ■agreed to furnish and deliver by steamer to said commission, free of all charges, on dock at Colon, Isthmus of Panama, subject to final inspection and acceptance at that place, six •duplex steam and compound air ©ompressors, as per specifi■cations furnished, to wit, one compressor or or before October 11, 1906; one compressor on or before October 26, 1906; ■one compressor on or before November 10, 1906; one compressor on or before November 25, 1906; one compressor on or before December 10, 1906; and one compressor on or before December 25, 1906.

By the alternative proposals submitted by the claimant the first machine was to have been shipped 70 days from notice of the award and the remaining five at intervals of [275]*27515 days; but the contract signed by the parties provided for deliveries of the compressors at definite dates.

In making settlement with the claimant the 12 days’ delay caused by the Government in making inspection of the compressors, at the place of manufacture, were credited to the claimant as shown in Finding IV, but were not treated as extending deliveries of subsequent compressors a corresponding length of time. Nor was the claimant given credit for the delay of the Government in signing the contract. By this method of settlement 501 days’ delay in making delivery of the compressors were charged to the claimant, and $5 per day, or in all $2,505, was deducted from the contract price. Hence this action.

The claimant’s contention is that paragraph 4 of the contract providing that “ time shall be considered as an essential feature of this contract ” was waived by reason of the delay of the chairman of the Isthmian Canal Commission in signing the contract more than 80 days after claimant had signed same.

This paragraph provides:

“AstiCle 4. It is further expressly understood and agreed that time shall be considered as an essential feature of this contract, and that in case of failure on the part of the party of the second part to complete this contract within the time specified and agreed upon that the party of the first part will be damaged thereby, and the amount of said damages being difficult, if not impossible, of definite ascertainment and proof, it is hereby agreed that the amount of said damages shall be estimated, agreed upon, liquidated, and fixed at the sum of five dollars ($5.00) for each compressor for each and every day the party of the second part shall delay in the completion and delivery of the compressors mentioned in this contract, and the party of the second part agrees to pay to the United States as liquidated damages, and not by way of penalty, the sum of five dollars ($5.00) for each compressor for each and every day the payty of the second part shall delay in the completion and delivery of the compressors covered by this contract, such delay not being the fault of the party of the first part; and the party of the first part may deduct or retain any or all of the above-mentioned sums out of or from any money that may be due or become due the party of the second part under this agreement. * * *
[276]*276“ Provided, however, that if the party of the second part shall by strikes, epidemics, local or State quarantine restrictions, or by abnormal force or violence of the elements be actually prevented from completing the compressors, or delivering the same at the date agreed upon in this contract, and such delay is without contributory negligence on their part-, such additional time may, in the discretion of the chairman of the Isthmian Canal Commission, be allowed for such completion as in the judgment of the party of the first part, or its successor, shall be just and reasonable. Provided further, that in case of such delay the party of the second part shall give immediate notice in writing to the chairman of the Isthmian Canal Commission, who may, in his discretion, accept such delays as sufficient cause for waiving the deductions; but such allowance or extension shall in no manner affect the rights and obligations of the parties under this contract, but the same shall subsist, take effect, and be enforceable precisely as if the new date for such commencement or completion had been the date originally agreed upon.” * * *

In support of its proposition the claimant relies upon and cites the cases of Ittner v. United States (43 C. C., 336); Little Falls Knitting Mills Co. v. United States (44 C. C.,1); and Callahan Construction Co. v. United States (ante, 229). The effect of those decisions is that where time is of the essence of a contract and the Government by its delay prevents performance within the contract time such delay will operate as a waiver of the time limit and give the claimant a reasonable time in Avhich to perform. With this contention we agree; but in the present case it is nowhere shown that the delay in signing the contract prevented the claimant from performance. On the contrary, the findings show that, as required by the specifications attached to the circular asking for proposals, the claimant submitted drawings of foundation details, which were returned to it August 6, and it is not shown that any delay was caused thereby after the claimant had signed the contract; and we may fairly presume that the claimant proceeded with the work on the return to it of the plans, as it is nowhere shown it objected to the delay in signing the contract on the ground of interference with the work.

[277]*277Had the delay in signing the contract been the cause ol all the delay in the delivery of the compressors it would, as held in the case of Morse Dry Dock Co. v. Seaboard Transportation Co. (161 Fed. Rep., 99, 100), have operated as a waiver of the time provision in the contract. But, as before stated, it nowhere appears that such was the case, as the first compressor was not delivered until 'December 14, or 64 days after the time fixed in the contract; and assuming, as the claimant contends, that the act of June 2, 1862 (12 Stat. L., 411), requiring contracts to be in writing, applies to the Isthmian Canal Commission by reason of its connection with the War Department, the claimant, after the final execution of the contract, continued to proceed thereunder without objection; so while the delay in signing does not appear to have prevented performance thé same can not be construed as a waiver of the time limit, but did operate by implication to extend the time a corresponding length. That is to say, allowing the chairman of said commission a reasonable time within which to sign after the claimant had signed the contract, there was a delay of 30 days, thus extending the time of delivery of each of the compressors 30 days beyond the time fixed in the contract and thereby continuing in force as applicable to the extended time the liquidated-damage clause of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Dredging Co. v. United States
49 Ct. Cl. 350 (Court of Claims, 1914)
Hinkley v. United States
49 Ct. Cl. 148 (Court of Claims, 1913)
Smith v. United States
48 Ct. Cl. 235 (Court of Claims, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 271, 1912 U.S. Ct. Cl. LEXIS 18, 1911 WL 1353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laidlaw-dunn-gordon-co-v-united-states-cc-1912.