American Dredging Co. v. United States

49 Ct. Cl. 350, 1914 U.S. Ct. Cl. LEXIS 235, 1914 WL 1384
CourtUnited States Court of Claims
DecidedFebruary 16, 1914
DocketNos. 30538 and 30539
StatusPublished
Cited by1 cases

This text of 49 Ct. Cl. 350 (American Dredging Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Dredging Co. v. United States, 49 Ct. Cl. 350, 1914 U.S. Ct. Cl. LEXIS 235, 1914 WL 1384 (cc 1914).

Opinions

BarNey, Judge,

delivered the opinion of the court:

This suit was originally brought in two separate actions to recover, respectively, the sums of $1,207.82 and $2,100.01, which were deducted by the defendants in its final settlement with the claimant on two separate contracts, as well as for meals and lodgings furnished the defendants’ employees during the delay period hereinafter mentioned. These deductions were made for the cost of superintendence and inspection during the period of delay on one of the contracts for 50 days and on the other for 60 days.

Both of the contracts were for dredging work on the Delaware River on sections adjoining each other, one called “ subsection 5A” and the other “ subsection 5B.” The contracts were identical in every particular except as to the location of the work to be performed. Copies of these contracts were attached to the petition in these suits and made a part of the same. They both provide that the work was to be completed by June 30, 1908. These two suits have been consolidated by order of the court and, except as to the date of final completion of each of them, are treated in this opinion as one contract.

The bids for this work .were submitted by the claimant pursuant to advertisement theretofore published on the 16th day of November, 1907; on the 6th of December following the claimant received notice from Maj. Sanford, the Government engineer, and who is located in the city of Philadelphia, Pa., in charge of the work, that its bid had been accepted. January 2, 1908, the claimant received from Maj. Sanford the contracts for the performance of this work [357]*357signed by him for the defendants and dated December 31, 1907; the claimant executed them on its part and returned them to Maj. Sanford on January 6, together with the bonds required. They were approved by the Chief of Engineers at Washington on January 23, and on January 27 the claimant received notice of such approval.

June 23, 1908, the claimant addressed a letter to Maj. Deakyne, the Government officer then in charge of the work, stating in substance that it would not be able to complete the contracts within the time limit and requested an extension of time for such completion till August 31, 1908. On June 27 Maj. Deakyne addressed letters to the claimant waiving the time limit for a reasonable period, but stating that the claimant must bear such expenses due to such waiver as were properly chargeable under the contracts. The work under the contract for subsection 5A was completed August 19, 1908, and on subsection 5B August 31, 1908, and accepted by the defendants. Upon final settlement with the claimant the defendants deducted all of their expenses for superintendence and inspection during the whole of such delay period under one contract for 50 and the other for 60 days.

It is contended by the claimant that no such deductions should have been made, as it claims that the extension of time above noted was required to complete the work under the contracts because of delays on the part of the defendants which retarded the work more than the period of extension.

The court has found as an ultimate fact that the defendants took 30 days more time than was reasonably necessary in getting the contracts to the claimant with notice of approval.

The statement of the case hereinbefore made gives the history of this whole question from the submission of the bids till the final approval of the contracts, and the decision upon the point in question is doubtless one of law rather than of fact. It seems, however, proper to call attention to some of the admitted facts in the case, which have led the court to make the ultimate finding of fact mentioned. The bids were opened November 15, 1907, but the contract, duly [358]*358approved, never reached the claimant before January 27, 1908, or 73 days thereafter. None of this delay was chargeable to the claimant. On the contrary, the findings show that it was unusually diligent in doing its part in expediting matters, as it received the contracts executed on the part of the Government January 2, 1908, and within four days executed them on its part and forwarded them to the proper officer of the Government, together with the bonds required. Time was of the essence of the contract, and there is nothing in the record showing any lack of diligence on the part of the claimant in executing the contracts after it was permitted under their terms to begin the work, which shows that it needed every day allowed to complete the work within the time limit. Taking these facts into consideration, we think that the finding that the defendants took 30 days more time than was reasonably necessary to get the contracts to the claimant, with notice of approval, is justified.

The findings show that dredging work in the Delaware River can not usually be done in the month of January, and the Government contends that this fact excused it for its delay, though the findings show that in the winter of 1907-8, when this work should have been in progress, dredging work on the Delaware River could have been done during the whole month of January. We do not think this contention is sound. If Providence favored the claimant by bestowing an open winter, during a part of which this work could have been carried on, we do not think the Government could by its negligence deprive it of this advantage. The claimant had the time limit named in the contracts, which was some time between November 15, 1907, and June 30, 1908, within which it was to do this work, and not of some other year or the average of years. How would the case stand if the opposite contention was made? Suppose the findings showed that in normal years dredging work could be done on the Delaware River during the whole winter, but that the winter in question was an abnormal one and the river was frozen so solid that no work of this kind could be done during the months of January and February. In such a case would the .Government not rightfully contend [359]*359that the unnecessary time taken in approving the contracts did not delay or injure the claimant ?

Some evidence was introduced by the Government tending to show that the claimant was not so situated as to begin work under these contracts before it actually did, because of the fact that it had its dredges employed elsewhere. While such evidence was so obscure as to hardly justify a finding upon that subject, we do not think such evidence was material under the circumstances of this case. A similar question was involved in Pickney v. United States, 46 C. Cls., 77, 90, and this court said: “ What right have we to assume that if the notice had been given in time to require completion within the terms of the contract the claimant would not have employed a sufficient force for that purpose? ”

A similar question arose in the case of Morse Dry Dock & Refair Co. v. Seaboard, &., Co., 161 Fed. Rep., 99, and the court said: “ The respondents’ contention is based upon an assumption which it had no right to make * * *. It can not assume that its failure to perform its obligations made no difference. It is imposible to say what might have happened had the conditions been different.” In the case at bar what right have we to assume that the claimant would not have purchased or hired other dredges even if all it then owned were employed elsewhere®

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graybar Electric Co. v. United States
90 Ct. Cl. 232 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
49 Ct. Cl. 350, 1914 U.S. Ct. Cl. LEXIS 235, 1914 WL 1384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-dredging-co-v-united-states-cc-1914.