Opinion

*672 Mr. Justice Blatchfobd

delivered the opinion of the court.

On the 12th of May, 1869, General Rodman, in command of .the United States Arsenal at Rock Island, Illinois, caused to be published the following advertisement, in pursuance of law: —

“Proposals por Bridge Masonry.
“ Sealed proposals will be received at this arsenal up to 10 o’clock a. m. on the twenty-fifth day of May, 1869, for the construction of the piers and. abutments of the railroad and wagon-road-bridge to be built to connect the island of Rock Island with the city of Davenport. It is proposed to build, .say, five- common piers, one draw-pier, and two abutment's. The stone and cement required for the work will be furnished on railroad cars, on arsenal switch, near the island end of the proposed bridge, and the sand required for the cement will be furnished by the United States at or near the same point. All the masonry must be of the best quality .of bridge masonry, the stones in each' course must be well banded, and each course well secured by dowels to the course below under cut-water, and at lower end of piers, arid the foundation courses must be fairly bedded and well secured to the rock-bed of the river, the work as it progresses being subject to the inspection and, approval of the commanding officer1 of the arsenal, or such other officer or person as may be designated by proper authority. Detailed information with regard to the general form and dimensions of the piers and abutments, and a profile of be'd of river, can be obtained by personal application at the arsenal. The total amount of masonry is estimated at about 10,000 cubic yards. All the piers and abutments •’will bé required to be completed prior to the first day of December, 1869. Parties making bids will, state the price per cubic yard of solid masonry at which they are willing to complete the work, the United States furnishing the stone, -cement, arid sand, as above stipulated, and nothing more. They will also make a bid stating separately the price per cuh’c yard of solid, masonry at which they will undertake to build the piers and abutments, the United States furnishing the stone, cement, and sand, as above, and the price at which they will - agree to put in the necessary coffer-dams with their protections. Proposáis will bé indorsed ‘ Proposals for Bridge Masoriry,’ and addressed to the undersigned. The United States reserves the right to reject any bid not deemed satisfactory.
“T. J. Rodman,
Lt. Col. and Bvt. Brig. Gen. U. S. A., Commanding."

*673 The appellants put in the following proposal: —

“Rock Island, May 25th, 1869.
. “ We propose to build the masonry of piers and abutments of the Rock Island bridge, as per annexed .advertisement: —
Small-piers and abutments, per yard .... $11 00
Draw-pier, per yard ..........13 00
“ Harvey & Livesey,
“Madison, Wisconsin.”

The only other proposal put in was one by Reynolds, Saul.paugh, & Co., as follows : —-

“ Rock Island, III., May 25th, Í869.
“ Brig.-Gen’l T. J. Rodman, Corn'd?g Rock Island Arsenal.
“Sir, — Wé respectfully propose to build your piers and abutments for the rail and wagón road bridge between the island of Rock Island and thé' city of Davenport, in accordance with the ’terms of your advertisement of May 12, 1869, at prices as follows :
“Solid masonry at-$19.10 per'cubic yard in the work complete, the United States furnishing the stone, cement, and sand, as stipulated, and nothing more. This .price is based on 10,000 cubic yards of masonry in the work when completed. Or, as per your second plan, at prices as follows: —
“.Solid masonry at $12.70 per cubic yard in the work' complete, the United States furnishing the stone, cement, and sand, as above, and build the coffer-dams at prices as follows: —
For pier No. 1, dam 18 feet high . . . . , .. $7,800.
For. “ '2, “ 15 “ . . .. . . . 34,900
For 3, “ 13 « . ........ 6,000
For • “ 4,5, & 6, 12 “ ...... 15,000
$63,700
“ The above prices for dams include the protections to the same, complete. Respectfully yours,
“Reynolds, Saulpaugh, & Co.”

The bid of the appellants was accepted. A contract was then drawn by a clerk of General Rodman’s. A rough draft of it was submitted to the appellants, and, on 'their returning it as satisfactory, the engrossed copies were prepared for .signature, and the contracts were executed and-interchanged, bear *674 ing date June 1, 1869. The following are the'provisions of tlie contract which are material to this case: “ The parties of the first part do hereby contract and engage with the said United States to construct the piers and abutments for the new rail and wagon bridge, to be built to connect the island of Rock Island with the city of Davenport, in accordance. with such plans and specifications as may be fixed by proper authority acting for the United States; the United States to furnish stone, cement, sand, .and all necessary templets required for thp work, and nothing more; the stone, and cement to he delivered in cars at the government switch on the island, near the site of the work.....The character of the work to be daily inspected as it progresses by such officer or other person as the commanding officer of the Rock Island arsenal or other authority appointed by the United States, may designate; such inspector to have full authority to give any directions with regard to the character or manner of conducting the work. The ¡whole work to be completed prior to the first day of December’ jnext, provided that the stone shall be delivered at the rate of •2,000 cubic yards per month; and, in case of any failure on the part of the United States to deliver this amount of stone, then the work to be completed as soon after the first day of December next as practicable. . . . Payment in such funds as the Treasury Department may provide, at the rate of thirteen (13) dollars per cubic yard for all masonry in the draw-pier, and at the rate of eleven (11) dollars per cubic yard for all other masonry. ... It is further stipulated and agreed, that if any default shall be made by the parties of the first part in the performance of their work specified in this contract, of the qualify and a,t the times and places therein provided, that then, in that case, the United States shall have the right to take entire and exclusive charge of the work, and to complete if in accordance with the conditions prescribed, by . this contract, charging us with the entire cost of completing it, and crediting us with the amount per cubic yard héretofore stipulated to be paid us for the completing of the work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Harvey v. United States, 105 U.S. 671, 26 L. Ed. 1206, 1881 U.S. LEXIS 2176 (1882).

105 U.S. 671 (Harvey v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Five Star Airport Alliance, Inc. v. Milwaukee County
939 F. Supp. 2d 936 (E.D. Wisconsin, 2013)
Buchine v. C.I.R.
Fifth Circuit, 1994
Universal Printing Co. v. State
43 Ill. Ct. Cl. 165 (Court of Claims of Illinois, 1990)
Paragon Energy Corp. v. United States
645 F.2d 966 (Court of Claims, 1981)
City of Merrill v. Wenzel Brothers, Inc.
277 N.W.2d 799 (Wisconsin Supreme Court, 1979)
Baycon Industries, Inc. v. Lee County
46 Fla. Supp. 35 (Lee County Circuit Court, 1977)
Dana Corp. v. United States
470 F.2d 1032 (Court of Claims, 1972)
Casado v. Schooner Pilgrim, Inc.
171 F. Supp. 78 (D. Massachusetts, 1959)
North American Iron & Steel Co. v. United States
130 F. Supp. 723 (E.D. New York, 1955)
Frazier-Davis Construction Co. v. United States
100 Ct. Cl. 120 (Court of Claims, 1943)
G. Schwartz & Co. v. United States
89 Ct. Cl. 82 (Court of Claims, 1939)
Pennington v. Town of Sumner
270 N.W. 629 (Supreme Court of Iowa, 1936)
American Cyanamid Co. v. United States
4 F. Supp. 937 (Court of Claims, 1933)
Western Cartridge Co. v. United States
61 Ct. Cl. 482 (Court of Claims, 1926)
Lovell v. United States
59 Ct. Cl. 494 (Court of Claims, 1924)
Swift & Co. v. United States
59 Ct. Cl. 364 (Court of Claims, 1924)
Poole Engineering & Machine Co. v. United States
58 Ct. Cl. 9 (Court of Claims, 1923)
American Dredging Co. v. United States
49 Ct. Cl. 350 (Court of Claims, 1914)