William Cramp & Sons Ship & Engine Building Co. v. United States

239 U.S. 221, 36 S. Ct. 70, 60 L. Ed. 238, 1915 U.S. LEXIS 1483, 51 Ct. Cl. 478
CourtSupreme Court of the United States
DecidedNovember 29, 1915
Docket63
StatusPublished
Cited by30 cases

This text of 239 U.S. 221 (William Cramp & Sons Ship & Engine Building Co. v. United States) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William Cramp & Sons Ship & Engine Building Co. v. United States, 239 U.S. 221, 36 S. Ct. 70, 60 L. Ed. 238, 1915 U.S. LEXIS 1483, 51 Ct. Cl. 478 (1915).

Opinions

[227]*227After making the foregoing statement,

Mr. Justice Day

delivered the opinion of the court.

The contract in this case and the release above set forth are in the form shown in United States v. Cramp, 206 U. S. 118,. and except for the considérations to be later dealt with, the present case is ruled by that unless relief in equity can be had, for it was there held that a release executed in the matter of the contract for the •battleship Indiana included, all claims which grew out of the performance of the contract, although not arising from the actual construction of the vessel. In the subsequent case of Cramp and Sons v. United States, 216 U. S. 494, the case in 206 U. S. was distinguished because of the different form of release executed in that case, which contained a proviso that it should not include claims arising under the contract other than those which the Secretary of the Navy had jurisdiction to entertain.

As the recital of facts definitely shows, the Court of Claims found, after consideration of the evidence adduced upon behalf of the claimant and the defendant, that there was no mutual mistake between the parties in the execution of the contract and release, and that the contract and release expressed the intention and purpose of the United States, as previously agreed upon, though the contracting party on behalf of the claimant company had mistaken its legal rights. As ultimate facts, the court found, so far as the same were questions of fact, that there was no mutual, mistake between the parties in the execution of the contract or the final release; that the same expressed the true intent and purpose of the United States, and that the failure of the officers of the claimant company to apprehend the legal effect thereof was not the fault of the United States or its officers, and was not the subject of reformation.'.' If we are governed by the findings of fact in this, as in other cases [228]*228coming from the Court of Claims, these findings conclude the question of fact as to whether the testimony warranted a reformation of the contract upon equitable principles.

The record contains a stipulation, signed by the As-' sistant Attorney General and counsel for the claimant, in which it is recited that whereas one of the questions raised and decided by the judgment of the Court of Claims is the right of the claimant to equitable relief through the reformation of the contract in suit, and the" reformation of certain releases, and that evidence was introduced in behalf of both parties touching the facts upon which the claimant founded its claim for equitable relief, subject to the defendant’s objection, and because the record was very voluminous and contained the report of many proceedings not relevant to the right to equitable relief, certain evidence bearing upon that point was stipulated into the record. The stipulation concluded: “Providing, however, that on appeal recourse shall be had to the record of the proceedings and evidence next hereinbefore mentioned, for no purpose whatsoever, except for the consideration and determination of the question with respect to the claimant’s right to the equitable relief aforesaid; it being understood and agreed that the Findings of Fact filed by the court May 29, 1911, shall not be affected in any other manner or for any other purpose by the said proceedings and evidence.”

In. view of this state of the record, we are met with the question, whether, in cases coming from the Court of Claims, of the character of the one now under consideration, the findings of fact are conclusive, as in other cases, or whether it is the duty of this court to determine for itself from the evidence sent up whether the claimant is entitled to equitable relief necessary to the establishment of his claim. The cases relied upon which it is contended make it the duty of this court to independently [229]*229consider the evidence are Harvey v. United States, 105 U. S. 671, and United States v. Old Settlers, 148 U. S. 427, which we shall notice later on.

In this case the Secretary of the Navy, as it appears from the recital of the facts, recommended that action be brought in the Court of Claims, and it was accordingly instituted in that court. The Court of Claims was given jurisdiction under the act of March 3, 1887 (c. 359, § 1, 24 Stat. 505), of all claims “founded . . . upon any contract, expressed or implied, with the Government of the United States, or for damages liquidated or unliquidated, in cases not sounding in tort, in respect of which claims the party would-be entitled to redress against the ’United.States either in a-court of law, equity, or admiralty if the United States were suable.” By the rulés of this court, the record from the Court of Claims is required to contain a transcript of the pleadings in the case, of the final judgment or decree of the court, and of such interlocutory orders, rulings, judgments, and decrees as may be necessary to a proper review of the case, and a finding by the Court of Claims of the facts in the case established by the evidence .in the nature of a special verdict, but not the evidence establishing them. These facts are to be the ultimate facts established by the evidence, and not the evidence upon which the ultimate facts are based. Burr v. Des Moines R. R., 1 Wall. 99, 102.

In the case of District of Columbia v. Barnes, 197 U. S. 146, it was held, under an act of Congress permitting parties to submit the justice of th.eir claims against the United States for work done in the District of Columbia to the adjudication of a competent court, that equitable jurisdiction was thereby conferred upon the Court of Claims, sufficiently, at least, to order the. reformation of a written contract between the claimant and the District, and to award a money judgment on the contract so reformed. In that case it was said that the findings of fact [230]*230would not be reviewed in this court, but were regarded as conclusive here, and that this court would determine the questions of law properly brought to its attention upon such findings.

In United States v. Milliken Imprinting Co., 202 U. S. 168, which was a suit in the Court of Claims praying for the reformation of a contract and for damages for breach of the same as reformed, this court held that the Court of Claims, under the act of March 3, 1887, had jurisdiction to reform the contract as a basis of a judgment for money damages. In United States v. Sisseton and Wahpeton Bands, 208 U. S. 561, where a suit was brought under a special act of Congress, giving the Court of Claims jurisdiction to hear testimony and render final judgment, this court held that it would not go behind findings of fact made by the Court of Claims, citing McClure v. United States, 116 U. S. 145, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Verizon's Bell Atlantic Cash Balance Plan
667 F. Supp. 2d 850 (N.D. Illinois, 2009)
Bank of Guam v. United States
578 F.3d 1318 (Federal Circuit, 2009)
Alexander v. Bosch Automotive Systems, Inc.
232 F. App'x 491 (Sixth Circuit, 2007)
Bianco v. United States
171 Ct. Cl. 719 (Court of Claims, 1965)
Wiseman v. State
101 A.2d 472 (Supreme Court of New Hampshire, 1953)
Sutcliffe Storage & Warehouse Co. v. United States
112 F. Supp. 590 (Court of Claims, 1953)
Werner v. United States
10 F.R.D. 245 (S.D. California, 1950)
Iowa-Wisconsin Bridge Co. v. United States
84 F. Supp. 852 (Court of Claims, 1949)
Northern Pac. Ry. Co. v. United States
70 F. Supp. 836 (D. Minnesota, 1946)
Frazier-Davis Construction Co. v. United States
100 Ct. Cl. 120 (Court of Claims, 1943)
City of Long Beach v. United States
94 Ct. Cl. 64 (Court of Claims, 1941)
Admiral Oriental Line v. United States
86 F.2d 201 (Second Circuit, 1936)
American Cyanamid Co. v. United States
4 F. Supp. 937 (Court of Claims, 1933)
Order of United Commercial Travelers v. Shane
64 F.2d 55 (Eighth Circuit, 1933)
Clifton Mfg. Co. v. United States
3 F. Supp. 508 (W.D. South Carolina, 1933)
Wessel v. United States
49 F.2d 137 (Eighth Circuit, 1931)
Chicago & North Western Railway Co. v. United States
68 Ct. Cl. 524 (Court of Claims, 1929)
Western Cartridge Co. v. United States
61 Ct. Cl. 482 (Court of Claims, 1926)
Texas Co. v. Rosenthal-Brown Fur Co.
12 F.2d 297 (W.D. Louisiana, 1925)
Perkins—campbell Co. v. United States
264 U.S. 213 (Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
239 U.S. 221, 36 S. Ct. 70, 60 L. Ed. 238, 1915 U.S. LEXIS 1483, 51 Ct. Cl. 478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-cramp-sons-ship-engine-building-co-v-united-states-scotus-1915.