Lovell v. United States

59 Ct. Cl. 494, 1924 U.S. Ct. Cl. LEXIS 482, 1924 WL 2318
United States Court of Claims·Decided March 31, 1924·No. No. 34084·Published·Cited by 4 cases

Opinion

Booth, Judge,

delivered the opinion of the court:

The plaintiff responded to certain advertisements and proposal put forth by the Commissioner of Indian Affairs, representing the Government, for certain construction work on Indian reservations. He procured six contracts, as follows: Three dated May 26, 1914, for the erection of three hospitals, one of brick at Rosebud Agency, South Dakota, another of similar construction at Cheyenne Diver Agency, South Dakota, and one of frame construction at Standing Dock Reservation, North Dakota. Of the remaining three, one dated December 26, 1913, provided for the rebuilding of a brick school house, No. 9, Rosebud Indian School, South Dakota; another dated March 23, 1915, provided for a frame hospital and gas house at Turtle Mountain Agency, North Dakota, a hospital at Mescalero, New Mexico, and one other hospital at Carson, Nevada; the last dated June 22, 1915, provided for a hospital at Fond du Lac, Minnesota.

Each of these contracts contained the usual Government stipulations, plans and specifications were furnished, and the undertakings were considered as embraced within them. The contracts and specifications are made a part of the findings by reference.

The first item for which judgment is sought has to do with the specifications as to flooring to be placed in the hospitals at Standing Rock, Cheyenne River, and Rosebud Agencies. [510] The specifications (see Finding V) covering this subject are carelessly drawn and abstruse. It is difficult to define their extent and exactions. Manifestly the plaintiff was to lay wood flooring except in the rooms, etc., specified for reception of composition flooring. The defendant, in soliciting proposals for bids, either by mistaking the requirements of the specifications, or in good faith intending to extend an option to lay one or the other sort of flooring, induced the plaintiff to present alternate proposals, binding him to a certain amount in addition to his lump sum bid if composition flooring was to be laid, and the lump sum bid if it was to be omitted and wood flooring laid. The record in this respect is indisputable. The bid of the plaintiff was accepted, and the alternate proposal for $100 additional for laying composition flooring was rejected. This is the inevitable result from the bid and acceptance. It follows logically from the fact that the $100 additional asked for laying composition flooring was not added to the lump sum bid. If subsequent to the making of the written contract it was discovered that the specifications, according to the construction put thereon by the defendant, exacted composition flooring — a construction open to doubt — it is quite evident that the mistake was mutual, and in the absence of any evidence tending to establish any other than perfect good faith, it seems to us the contract to this extent should be reformed to meet the actual and intended agreement of the parties. The plaintiff, with respect to this.item, was misled to his financial injury by the juoposals submitted by the defendant. The express wording of the specifications, out of which the mistake grew, were susceptible to the commission of just such an error, and where there is a mutual mistake in the-written contract, an unintentional variance between the proposals and the written instrument, the right to resort to the proposals and acceptance thereof, to ascertain what the parties did really agree upon, has been approved by the Supreme Court in a number of decisions. Harvey v. United States, 105 U. S., 671; Garfielde v. United States, 93 U. S., 242; Ackerlind v. United States, 240 U. S., 531. That the written contract does not reflect in this case the true understanding of the parties, we think, is apparent. The plaintiff, [511] as shown by the findings, is entitled to a judgment for $1,700.12 upon this item.

The location for the hospital at Eosebud Agency was distinctly shown on the block plan and specifications, part of the plans and specifications for this particular work. This was in exact conformity with the specifications examined by the plaintiff before submitting his bid, and as so exhibited the plaintiff had a positive right to rely thereon. The plaintiff was admonished to visit the site of the work. The duty of clearing and making it ready for the structure was imposed upon him, and he was held responsible for laying out his work correctly and for exactment of measurements. The site shown on the plans was immediately adjoining the agency village. A sufficient supply of water was available, as well as business houses and places where his laborers might secure board and lodging. When the plaintiff’s superintendent reported at the agency to commence work he was informed by the agency supervisor that he — the supervisor — would not approve the building site shown on the plans, and the plaintiff was compelled, despite his protest, to erect the building on a new site, a half mile away by wagon road, at a point devoid of any conveniences, poor water supply, and more difficult and expensive to reach in the transportation of materials. By what authority the agency supervisor so arbitrarily set aside the positive provisions of the contract and the Indian Office afterwards approved the same, is a little difficult to understand. An effort is made to justify the procedure under paragraphs 2 and 14 of the “ General conditions,” as shown in Finding IV, and article 3 of the written contract. We need not indulge in a lengthy discussion to demonstrate their utter inapplicability. The right to make changes, so confidently relied upon, from the very language of the clauses according this right, has obviously no reference whatever to the location of the building. The superintendent of the school was positively forbidden to intervene in the matter of site, if the same was designated on the topographic map. It is almost inconceivable that the parties ever intended that the contractor should be left in the dark as to where he must perform the work, and be subjected to shifting opinions as [512] to the availability of the site selected. This matter was very properly put at rest by the specifications and thereafter it required the mutual consent of the parties to change it. Findings IX and X disclose the situation in detail. Judgment will be awarded on this item for $359.65.

The plaintiff was subjected to a deduction of $146, the expense occasioned the defendant in making good some defects found on final inspection of the work, in the flooring of certain rooms in the hospital building at the Standing Rock Agency. This deduction is expressly authorized by the terms of the contract. See paragraphs 2 and 16 of “General conditions” and article 6 of the contract. The defendant observed the terms, of the contract and specifications in making this deduction. The amount withheld was the exact cost of repairing the defects.

Free access — add to your briefcase to read the full text and ask questions with AI

Lovell v. United States, 59 Ct. Cl. 494, 1924 U.S. Ct. Cl. LEXIS 482, 1924 WL 2318 (cc 1924).

59 Ct. Cl. 494 (Lovell v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)
Heid Bros. v. United States
63 Ct. Cl. 392 (Court of Claims, 1927)
M. Samuel & Sons v. United States
61 Ct. Cl. 373 (Court of Claims, 1925)