Underwood v. Wolf

23 N.E. 598, 131 Ill. 425
CourtIllinois Supreme Court
DecidedJanuary 21, 1890
StatusPublished
Cited by62 cases

This text of 23 N.E. 598 (Underwood v. Wolf) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Underwood v. Wolf, 23 N.E. 598, 131 Ill. 425 (Ill. 1890).

Opinion

Mr. Justice Magruder

delivered the opinion of the Court:

The contract bears date February 8, 1886. By its terms the appellee was to furnish and erect the refrigerating machinery with engine, pump, pipes, etc., in the packing house of the appellants, and have the same in complete working order by the 8th day of May, 1886. .The evidence tends to show that the whole plant was not ready for use until the first day of July, 1886.

The evidence further tends to show that the appellants were carrying on their packing business while the appellee was putting in the machinery. The appellee claims that the conduct of the business under such circumstances necessarily interfered with his work and delayed its progress. He also claims that delay was caused by the failure of the appellants to prepare in proper time the room, in which the machinery was to be erected.

. Whether the delay in the completion of the plant was due to the fault of the appellee or to that of the appellants was a question of fact to be determined by the jury under proper instructions from the court. We see no objection to the tenth instruction given for the defendants below, as modified by the court. It told the jury that “under the contract in evidence the plaintiff was bound to complete the whole plant in complete working order and condition within ninety days from the 8th day of February, A. D. 1886, unless prevented by the acts or fault of the defendants; and if the evidence shows that he did not do it, then he is liable in this action to the defendants for any damages the evidence may show they have sustained by reason of such delay.” This instruction was given as asked by the defendants except that the words in italics were added by the court. It was proper to add the words in question because the contract required the defendants to furnish a room, foundations, masonry, carpenter work, and all ■steam and feed and discharge water connections, and to properly insulate the rooms according to plans, etc., and, if delay resulted from their failure to meet these requirements, the plaintiff certainly could not be held responsible. The jury found in his favor upon this question, and the judgment of the Appellate Court forbids us to disturb the finding.

But the main controversy between the parties arises upon the following provision in the contract: “And it is further agreed * * * that if the machines have fulfilled the guaranties made for them in this agreement by 1st of September, 1886, then said party of the second part (appellants) shall accept the same; and all payments to be made after the payment to be made on July 1, 1886, shall be promissory notes, dated on the day of acceptance of the plant with interest after maturity.” The defendants refused to give and have never given the notes thus provided for.

What are the guaranties which were to be fulfilled ? The plaintiff, Wolf, agreed and guaranteed, that the machine would maintain certain degrees of cooling temperature in certain rooms in the packing-house, and would cool the rooms within a certain specified time; that it would cool a certain number of hogs of a specified weight within a specified time; that the power required to drive the machinery should not exceed a certain limit; that the fuel required to produce the steam to do the work of the engines should not exceed a certain amount; that the loss of ammonia in doing the work should not exceed a certain number of pounds; that the refrigerating machines should be of the best material and workmanship; that the engine should be capable of running the packing house machinery in addition to the compressors; that the iron piping to be furnished should be such as would be necessary to carry and convey the brine required for the proper cooling of the rooms.

In considering the nature of these guaranties, it is unnecessary to discuss any nice distinctions between warranties on the one side, and conditions precedent or descriptions of the /'property on the other. It is sufficient that the guaranties are-treated as warranties, and their non-fulfillment, if they were .not fulfilled, will be regarded as a breach of warranty.

Inasmuch as the plant was to be completed by May 8,1886, and was to be accepted if the guaranties were fulfilled by September 1, 1886, it is manifest that the period between these two dates was to be made use of'for the purpose of testing the machines, in order to ascertain whether or not they were such as they were guaranteed to be. It is also sufficiently manifest that, if the machines failed in any of the particulars named in the guaranties, the defects which would thus be shown to-exist must be regarded as patent defects as contradistinguished from latent defects.

Where there is a sale and delivery of personal property in presentí with express warranty, and" the property turns out to be defective, the vendee may receive and use the property and sue for damages on a breach of the warranty, or, when sued for the purchase price, he may recoup such damages under the general issue, or set them up in a special plea of set off. This is a well settled rule. In the present ease, the contract is executory; the title to the property did not vest in the purchaser until the period for making the test had passed. It has been held in some States that, where the contract is thus executory and a time is fixed for making a test, the acceptance and use of the property, after such time has passed, amount to a waiver of the right to claim damages for a breach of the warranty. But such is not the law in this State. In the, present case, the evidence tends to show that the defendants took possession about July 1,1886, of the machines, placed in their packing house by the plaintiff, and had been using the same up to the time of the trial of the cause in the court below. The chief complaint of the appellants is that, under the instructions given by the trial court, the jury were led to regard the acceptance and use of the machinery by the defendants as an abandonment of all right to damages for breach of the warranties. We are unable to regard this complaint as well founded.

We agree with the counsel for appellants, in the main, in their view of the law. We think that, even where the contract is executory, the claim for damages on account of a breach of the warranty will survive the acceptance of the property. Chitty on Contracts (11th ed.) at page 652 says: “Where, therefore, the vendor of a warranted article, whether it be a specific chattel or not, sues for the price or value, it is competent to the purchaser, in all cases, to prove the breach of the warranty in reduction of damages, and the sum to be recovered for the price of the article will be reduced by so much as the article was diminished in value by non-compliance with the warranty.” The previous discussion of the authorities by the author, before arriving at the conclusion thus announced, shows his meaning to be, that the breach of the warranty may be proven in reduction of damages, not only in the case of the sale of a specific chattel, but also in the case of an executory contract, as, for example, “where an article is ordered from a manufacturer who contracts that it shall be of a certain quality, or fit for a certain purpose.” (Idem, pages 641 to 652).

In Benjamin on Sales, Vol. 2, sec. 1356 (4th Am.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard Oil Co. of Indiana v. Daniel Burkhartsmeier Cooperage Co.
77 N.E.2d 526 (Appellate Court of Illinois, 1948)
Fuller v. Fried
224 N.W. 668 (North Dakota Supreme Court, 1928)
Spiro v. Cable
248 Ill. App. 343 (Appellate Court of Illinois, 1928)
United Boiler Heating & Foundry Co. v. Ackermann-Quigley Printing Co.
236 Ill. App. 111 (Appellate Court of Illinois, 1925)
Santa Rosa-Vallejo Tanning Co. v. Charles Kronauer & Co.
228 Ill. App. 236 (Appellate Court of Illinois, 1923)
Kennett, Sparks & Co. v. Knecht
221 Ill. App. 601 (Appellate Court of Illinois, 1921)
Conner v. Borland-Grannis Co.
128 N.E. 317 (Illinois Supreme Court, 1920)
Whitney, Inc. v. Mandel
218 Ill. App. 316 (Appellate Court of Illinois, 1920)
Rice v. Friend Bros.
179 Iowa 355 (Supreme Court of Iowa, 1917)
Leonard v. Home Builders
161 P. 1151 (California Supreme Court, 1916)
T. H. Rogers Lumber Co. v. M. W. Judd Lumber Co.
1915 OK 923 (Supreme Court of Oklahoma, 1915)
Photo Cines Co. v. American Film Manufacturing Co.
190 Ill. App. 124 (Appellate Court of Illinois, 1914)
Staver Carriage Co. v. American & British Manufacturing Co.
188 Ill. App. 634 (Appellate Court of Illinois, 1914)
American Dredging Co. v. United States
49 Ct. Cl. 350 (Court of Claims, 1914)
Orton v. Artesian Stone & Lime Works Co.
183 Ill. App. 370 (Appellate Court of Illinois, 1913)
Hakes v. B. Aaron & Sons
182 Ill. App. 100 (Appellate Court of Illinois, 1913)
Connersville Co-operative Creamery Ass'n. v. Baltz
180 Ill. App. 376 (Appellate Court of Illinois, 1913)
Woodford Distilling Co. v. Remington Typewriter Co.
174 Ill. App. 244 (Appellate Court of Illinois, 1912)
Fred W. Wolf Co. v. Monarch Refrigerating Co.
96 N.E. 1063 (Illinois Supreme Court, 1911)
Kelley-Springfield Road Roller Co. v. Coffman
72 S.E. 749 (West Virginia Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
23 N.E. 598, 131 Ill. 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/underwood-v-wolf-ill-1890.