Orton v. Artesian Stone & Lime Works Co.

183 Ill. App. 370, 1913 Ill. App. LEXIS 1585
CourtAppellate Court of Illinois
DecidedNovember 24, 1913
DocketGen. No. 17,916
StatusPublished
Cited by1 cases

This text of 183 Ill. App. 370 (Orton v. Artesian Stone & Lime Works Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orton v. Artesian Stone & Lime Works Co., 183 Ill. App. 370, 1913 Ill. App. LEXIS 1585 (Ill. Ct. App. 1913).

Opinion

Mb. Justice Smith

delivered the opinion of the court.

This was a case of the first class in the Municipal Court of Chicago brought by the appellants to recover from the appellee the sum of $14,000, with interest thereon, the purchase price of two electric cranes, and also certain extras for materials and services amounting to about $1,000, duly itemized in appellants’ statement of claim. The appellee claimed that the two cranes failed to fulfil appellants’ guaranties and were thereupon rejected; and by reason of certain charges, expenses, etc., thereby caused it, amounting to about $1,100, the appellee filed a set-off to recover therefor. On a hearing- by the court, without a jury, the court found the issues for the appellee and entered a judgment on the findings against appellant for $710.54.

On December 20, 1909, the appellants wrote the following proposal to the appellee:

“In reply to your request, we are pleased to quote you upon 2 electric broad gauge revolving cranes, in accordance with attached specifications and blue print, erected complete upon your bins, with all wiring upon crane done and including the services of an Expert Superintendent to instruct your operators in the handling of the machines, the sum of Fourteen Thousand Dollars ($14,000). We can make delivery of complete equipment in 70 days from receipt of order. Terms to be 50% upon presentation of bill of lading and the remaining 50% 60 days thereafter. Trusting that we may be favored with your valued order, we are,
Tours very truly.”

With this proposal were a blue print and ‘‘ Specifications for Electric Revolving Cranes for Artesian Stone & Lime Works Co.,” the specifications covering nearly four closely printed pages of the abstract. The concluding paragraph thereof was as follows:

“We will guarantee that under reasonably favorable conditions and with a good operator and current of proper voltage supplied at the motor 75 trips of the bucket from the barge to the bins can be obtained per hour. We will also guarantee that under similar conditions, 150 to 200 tons of stone can be unloaded from the barge to the bins per hour. We will also guarantee material and workmanship and will agree to replace F. O. B. cars our shops any parts proving defective within six months from date of installation. ’ ’

The said proposition was accepted by the appellee in writing January 13, 1910. Work was not begun by the appellants on the said cranes until about April 1,1910, and they were not delivered to the appellee until June, 1910, beyond the time limit of seventy days for the delivery thereof.

The appellee was engaged in the business of quarrying and selling crushed stone, with a quarry and place of business at Summit, Illinois, near the Chicago drainage channel. It proposed to erect bins at its yards on the north branch of the Chicago river near the intersection of Barry and Campbell avenues, and hereinafter referred to as the North Side yard, and at its yards on the south branch of the Chicago river near the intersection of 37th and Iron streets, and hereinafter referred to as the South Side yard. By means of three boats or barges, owned by the appellee, stone was brought up the canal into the river to the yards in question and the said cranes were to be used to unload said boats and place the stone into the bins, from which it would be loaded into wagons by gravity.

The two cranes in question were made by a company with shops at Harvey, Illinois, of which the appellant Steinbrenner was superintendent, and both appellants were stockholders. One of the cranes was shipped from Harvey May 31st, June 2nd and 4th, to the North Side yard and there erected and started in operation about July 5th. The other crane was shipped June 9th and 14th to the South Side yard and there erected and started in operation about July 18th. It naturally took, time to adjust and get the said cranes in working order. There was some difficulty in operating the cranes because of certain parts of the machinery breaking. accidents, and other causes not clear, being the subjects of much testimony more or less conflicting. On September 21st the appellee wrote the appellants declining to accept either of the cranes on the ground that they “fail to and are incapable of doing the work for which they were made and purchased,” and requested appellants to take them away. The appellants failing to so do, the appellee took them down and cared for them at the respective yards.

The record is a voluminous one. The abstract consists of nearly four hundred pages. Both counsel have filed long and exhaustive briefs, in all more than five hundred pages. The testimony on many points is conflicting, and a great many legal propositions are advanced and argued in the briefs. To analyze the evidence and comment, even briefly, upon the legal points raised would require an opinion of unpardonable length. Suffice it to state that we have given the abstracts and briefs careful and patient study and shall only attempt to indicate the controlling features of the case and our opinion thereon.

That the time limit for delivery of the cranes within seventy days after the receipt of the order was waived, is, from all the evidence and circumstances in the case, too obvious to require any serious comment.

The principal and controlling question in the case is, were the cranes in question accepted by the appellee? If so, then the appellee was bound to pay the purchase price thereof, less, of course, the damages it might be able to establish by way of recoupment. Wolf Co. v. Monarch Refrigerating Co., 252 Ill. 491-508.

Mechera on Sales, in discussing an executory contract with a warranty, says, section 818: ‘ ‘ The buyer in these cases is not obliged to rescind; he may do so, or he may retain the chattel and have his action for the damages. If he would exercise his option, he must do so with promptness after his discovery of the breach of warranty. He has a reasonable time, considering all of the circumstances, within which to test the chattel to ascertain whether it conforms to the warranty; but if it does not, he must promptly return or offer to return the article to the seller in rescission of the contract.

Also section 1380: “The acceptance need not be express. It may be, and, in the cases coming before the courts, ordinarily is, implied or denied in reliance upon the circumstances of the case.

The fact most frequently relied upon as the ground of an implied acceptance is that the buyer, after receiving the goods, has retained them without objection for an unreasonable period. As has been seen, the buyer has the right to inspect the goods and is then bound to accept them if they conform to the contract, or to reject them if they do not. He is bound, however to do one thing or the other, and that within a reasonable time; and if he simply remains inactive, neither accepting or rejecting within a reasonable period, the law will deem his inaction to be acquiescence, and he will not afterwards be permitted to reject," and cites many authorities in support thereof. In Dorrance v. Dearborn Power Co., 233 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pennsylvania Rubber Co. v. Detroit Shipbuilding Co.
152 N.W. 1071 (Michigan Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
183 Ill. App. 370, 1913 Ill. App. LEXIS 1585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orton-v-artesian-stone-lime-works-co-illappct-1913.