Fred W. Wolf Co. v. Monarch Refrigerating Co.

96 N.E. 1063, 252 Ill. 491
CourtIllinois Supreme Court
DecidedDecember 21, 1911
StatusPublished
Cited by30 cases

This text of 96 N.E. 1063 (Fred W. Wolf Co. v. Monarch Refrigerating Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fred W. Wolf Co. v. Monarch Refrigerating Co., 96 N.E. 1063, 252 Ill. 491 (Ill. 1911).

Opinion

Mr. Justice Dunn

delivered the opinion of the court:

Appellee recoverd a judgment for $13,844.57 against appellant in an action of assumpsit. The Appellate Court affirmed the judgment and granted a certificate of importance and appeal to this court.

The trial court directed the verdict. The action was for the unpaid balance of the consideration of $21,300 agreed to be paid for the construction and installation of a refrigerating plant upon the premises of the appellant. The defense claimed was that the steam engine, which formed an essential part of the refrigerating plant to be furnished, did not conform to the specifications of the contract, and was not of the best material and workmanship as required by such specifications, but was materially defective and was worth $5000 less than the engine specified in the contract, and that it would cost $5000 to make the engine actually installed conform to the specifications. The appellee’s contention was that the appellant had accepted the plant in full discharge of appellee’s agreements, and could therefore neither defeat the action nor recoup its damages.

The contract consisted of a written proposal signed by appellee and accepted in writing by appellant. There was a subsequent agreement whereby certain direct expansion piping was to be furnished at an increased price instead of thirty sections of air cooler required by the original contract, but the original contract was not otherwise changed by the subsequent agreement and the rights of the parties in this suit are not affected by it. The appellee’s original proposal, which was accepted by the appellant, contained the following:

“We propose to furnish and erect in your building at Chicago, Illinois, in complete working order and condition and of the best material and workmanship, one refrigerating plant of 225 tons refrigerating capacity daily, consisting of the following machinery and material, all as hereinafter specified. * * * It is understood that the plant as above described is to be in complete working order and condition during the month of April, 1903, unless delayed by causes over which we have no control, such as fire, providential interferences, riots, strikes, or civil commotions of any kinds. We agree that the power required to drive the compressor while doing the above work shall not exceed 282 effective horse power at fifty revolutions per minute, providing you furnish condenser water at 60 deg. Fahrenheit, in ample quantity, and that the consumption of fuel necessary to furnish steam to do the work of the engine shall not exceed two and one-quarter pounds of coal per indicated horse power per hour, providing you carry one hundred and fifty pounds boiler pressure and furnish coal which will evaporate eight pounds of water per pound of coal burned. And we agree that this machine, when prop-operated, and when provided with the proper amount of expansion surface, ammonia, etc., and when operated in connection with a power plant of ample capacity, shall be of capacity to perform a refrigerating duty equivalent to the melting of 225 tons of ice during the twenty-four hours of continuous operation. After the plant is started we will furnish an engineer to have charge of the operation of the machine for ten days, during which time we will do the work and produce the temperatures herein specified. While we are in charge you are to furnish all necessary help, together with fuel, light, water, steam, oil, waste, and all other necessary supplies for the successful operation of this plant. At the end of the above mentioned ten days you shall accept or reject the plant, it being understood, however, that if it shall meet the requirements of this proposition it shall be accepted. If rejected you shall notify us in writing thereof, and hereby permit us to enter the premises and remove the same without charge to you and upon refunding to you whatever money has been paid us. An acceptance after the above mentioned period shall be in full discharge of the agreements hereinbefore contained.”

The plant was not in complete working order and condition during the month of April, 1903. It was operated for a few days in August, 1903, was then shut down and was again started in April, 1904. It was not claimed that this delay occurred through any fault of the appellee or that the rights of the parties are affected by it. The plant was started in operation April 26, 1904, in charge of an engineer of appellee, and was operated until May 26, 1904. The appellee’s engineer was then withdrawn. There was evidence tending to show that the engine was not of the best material and workmanship, but was substantially defective and was worth $5000 less than if it had been in accordance with the specifications; that it could not be made to operate satisfactorily and could not do the work required of it.

On May 18 the appellee, through Mr. Knuth, its agent, presented to the appellant the following letter addressed to the appellant and requested that it be signed:

“Chicago, III.,................ 1904.
“The Fred Wolf Co., Chicago, Illinois.
“Gentlemen—The refrigerating plant, per our contract dated November 28, 1902, also the expansion pipe covered by our contract dated December 22, 1903, has been installed, except the pipe in one small room in the basement of new building. The fact that the pipe in this room has not been erected is due to no fault of yours, as the room is not yet in condition to have the pipe put in. Your engineer has been in charge of the operation of the plant for the required period and machinery and apparatus is working satisfactorily, and you may treat this as a formal acceptance under such contract. It is understood that the pipe will be installed in the room referred to as soon as we are ready to have the work done.
“Yours very truly.”

The appellant’s officers refused to sign the letter and handed it back to Knuth, saying they did not propose to accept the plant but must reject it and would so write his firm. Frederick Espert, the secretary and treasurer of the appellant, then told Knuth the trouble with the engine and what was wrong with it, and Knuth said it would be unfair to shut the engine down,—to go ahead and run it and give it a chance to show itself; whereupon Espert said: “Well, if that is your idea,—if that is your request,—we can let the boys run it further, try it out.” The next day the appellant wrote the following letter to appellee:

"May 19, 1904.
“Gentlemen—Referring to your letter of the acceptance left here by your representative yesterday, which relates to the contract dated Nov. 28, 1902, we have this to say: we decline to accept the steam engine, the same is not in accordance with contract and is unsatisfactory to us.”

On May 25 the appellee’s manager wrote the following letter to the appellant:

“Gentlemen—We have furnished all the apparatus and performed all work required of us under the provisions of our contract of November 28, 1902, and of the supplementary contract modifying such original contract, and our man has been in charge of the operation of the apparatus for a considerably longer period than is provided in such contract. The apparatus is working perfectly and is performing the full duty guaranteed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midwest Builders v. Lord and Essex
Appellate Court of Illinois, 2007
Midwest Builder Distributing, Inc. v. Lord and Essex, Inc.
891 N.E.2d 1 (Appellate Court of Illinois, 2007)
Spirit of Excellence, Ltd. v. Intercargo Insurance
777 N.E.2d 660 (Appellate Court of Illinois, 2002)
Alden Press, Inc. v. Block & Co.
527 N.E.2d 489 (Appellate Court of Illinois, 1988)
Brule C. E. & E., Inc. v. Pronto Foods Corp.
278 N.E.2d 477 (Appellate Court of Illinois, 1971)
Pirie v. Carroll
171 N.E.2d 99 (Appellate Court of Illinois, 1960)
Davidson v. Wisconsin Chair Co.
77 N.E.2d 820 (Appellate Court of Illinois, 1948)
Hall v. Hodgdon
39 A.2d 195 (Supreme Court of Vermont, 1944)
United States v. Lux Laundry Co.
118 F.2d 848 (Seventh Circuit, 1941)
Frick Co. v. Rubel Corporation
62 F.2d 765 (Second Circuit, 1933)
Foley & Co. v. Excelsior Stove & Manufacturing Co.
265 Ill. App. 78 (Appellate Court of Illinois, 1932)
Hall v. Bergschneider
265 Ill. App. 118 (Appellate Court of Illinois, 1932)
Butler Manufacturing Co. v. Elliott & Cox
233 N.W. 669 (Supreme Court of Iowa, 1930)
Wright & Co. v. Shackleford
148 S.E. 807 (Supreme Court of Virginia, 1929)
State Board of Administration v. Roquemore
117 So. 757 (Supreme Court of Alabama, 1928)
Hoobler v. Voelpel
246 Ill. App. 69 (Appellate Court of Illinois, 1927)
J. C. Boss Engineering Co. v. Gunderson Brick & Tile Co.
209 N.W. 876 (Supreme Court of Minnesota, 1926)
Scriven v. Hecht
287 F. 853 (Second Circuit, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
96 N.E. 1063, 252 Ill. 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fred-w-wolf-co-v-monarch-refrigerating-co-ill-1911.