Moore v. United States

46 Ct. Cl. 139, 1910 U.S. Ct. Cl. LEXIS 128, 1910 WL 921
CourtUnited States Court of Claims
DecidedJanuary 16, 1910
DocketNo. 27477
StatusPublished
Cited by15 cases

This text of 46 Ct. Cl. 139 (Moore v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore v. United States, 46 Ct. Cl. 139, 1910 U.S. Ct. Cl. LEXIS 128, 1910 WL 921 (cc 1910).

Opinion

BaeNet, J.,

delivered the opinion of the court:

This suit grows out of the construction of a dry dock in Boston, Mass. On the 14th of March, 1899, the firm of O’Brien & Sheehan, composed of John J. O’Brien and John C. Sheehan, entered into a contract with the United States to construct this dry dock, the same to be completed December 1, 1901. The time for completion was afterwards extended by the Government to August 30, 1903, but the dry dock was not turned over to and accepted by the Government until August 12, 1905. The City Trust, Safe Deposit and Surety Company of Philadelphia was the surety of the contractors on a bond for the faithful performance of the [170]*170contract, and by agreement with the original contractors took charge of the work July 10, 1902, and carried it-to completion, and during such time was recognized by the Government authorities as the contractor for said work. As stated in the findings, the term “ contractors ” is hereinafter used to apply either to the original contractors or said City Trust, Safe Deposit and Surety Company, or to all of them, as the time may indicate.

By the terms of the contract the dry dock was to have been completed December 1, 1901, but the time for completion was extended by the Government to August 30, 1903, and it was actually completed and turned over to and accepted by the Government August 12, 1905. It is conceded by the Government that the work was well done; therefore that question does not enter into a discussion of the case.

The damages sought to be recovered in this suit arise out of delays in the completion of the dry dock occasioned by the Government, faulty directions as to its construction given by the Government engineer in charge of the work, changes in the plans for the work, and the construction to be given to several provisions of the contract. These damages are made up of several items which will be considered separately.

COEEERDAM.

The first item is a claim for loss on account of breaks in the cofferdam occurring during its construction, occasioned by a defective plan for the same proposed and directed to be followed by the Government engineer in charge of the work. The first article of the. contract (omitting those terms which are manifestly inapplicable to the cofferdam) provided:

“The contractors will * * * at their own risk and expense, furnish and provide * * * temporary structures of every description * * * necessary or requisite in and about the construction of said dry dock * * * subject to the approval of the civil engineer.”

The findings show that the cofferdam in question was a subject of considerable discussion between the claimants’ engineers and Mr. Maxson, the Government engineer in [171]*171charge of the work, and properly so, as it was to be one of the largest cofferdams ever constructed. Finally, a general plan was suggested by Mr. Maxson and worked out in detail by the claimants’ engineers with his advice and approval, and this was the plan which was subsequently followed in its construction. Reasonable care was taken in such construction as well as in its filling, but, not unlike many human undertakings, mistakes seem to have been made in the plan as well as in the construction, and serious breaks occurred, involving the claimants in considerable loss of time and money; and the first question to be decided is whether this loss is to be charged to the Government.

The Government was largely interested in the performance of the details of this contract from the very beginning of the work. It had agreed that monthly estimates should be made by its engineer in charge as the work advanced, and that 90 per cent of such estimates should be paid to the contractors from month to month. A mere statement of this fact shows that ordinary prudence demanded that the Government should have general supervision of the work as it progressed, and the claimants had agreed to this as above quoted. The findings show that the Government engineer in charge of the work had considerable skill as a civil engineer, but had had but little experience in the construction of cofferdams.

The findings also show that these defects which caused the breaks in the cofferdam were such as the exercise of ordinary care and skill on the part of the Government engineer would have foreseen. In other words, the first two breaks in the cofferdam were chargeable to the fault of the defendants.

The contractors objected to the plan for the cofferdam, as directed to be made by the Government engineer, and followed it only because it was required of them by him to do so. The contractors, however, took no appeal from his decision and made no formal protest against following his directions.

No case arising under a Government contract has been cited to us on either side which is a precedent for the decision of this case. Numerous cases have been cited by [172]*172the Government attorney where it has been held that the engineer in charge of the work was the appointee of the parties and that his decision was final unless influenced by malice or prejudice or was so grossly erroneous as to imply fraud or bad faith. But most if not all of these cases 'arose under contracts containing the provision that the decision of the Government officer in charge should be final, which is not true in the case before us; and in all of them the matter for decision was so essentially different as to involve a different principle.

In Kihlberg v. United States (97 U. S., 398) it was ascem taining and fixing a route for the transportation of stores; in Gleason v. Unitéd States (175 U. S., 588) it was the exercise of the judgment of the Government engineer as to the advisability of granting an extension of time to the contractors; in Barlow v. United States (184 U. S., 123) it was the decision of the Government engineer as to the quality of stone employed in the construction of a dry dock. In all of the cases so cited it was the exercise of the judgment of the Government engineer in charge as to the material being employed, the construction of the contract as to the manner of doing the work, or, in general, the way in which the work should be when completed, which was involved. In none of them was the question at issue, What is the responsibility of the Government where its engineer in charge actively directs work to be done in a certain manner which proves defective and causes great loss to the contractor and where the exercise of ordinary skill would have foreseen such defects?

In addition to the provision of the contract above quoted the specifications which were made a part of the contract also provided:

“ The works included in the contract will be carried out by the contractor under the inspection and supervision of the civil engineer detailed for the purpose, who will inspect all the materials and workmanship and will have full authority to reject any which, in his opinion, are not in full, accordance with the true spirit, intention, and meaning of the contract, plans, and specifications.”

It is true that the contractors by these provisions of the contract agreed to construct the dry dock “ under the inspec[173]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Rodriguez v. United States
69 Fed. Cl. 487 (Federal Claims, 2006)
Helix Electric, Inc. v. United States
13 A.L.R. Fed. 2d 753 (Federal Claims, 2005)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Bloedel Donovan Lumber Mills v. United States
74 F. Supp. 470 (Court of Claims, 1947)
W. E. Callahan Construction Co. v. United States
91 Ct. Cl. 538 (Court of Claims, 1940)
MacDonald Engineering Co. v. United States
88 Ct. Cl. 473 (Court of Claims, 1939)
Rubin v. Coles
142 Misc. 139 (City of New York Municipal Court, 1931)
Moran Bros. v. United States
61 Ct. Cl. 73 (Court of Claims, 1925)
Spearin v. United States
51 Ct. Cl. 155 (Court of Claims, 1916)
Normile v. United States
49 Ct. Cl. 73 (Court of Claims, 1913)
Laidlaw-Dunn-Gordon Co. v. United States
47 Ct. Cl. 271 (Court of Claims, 1912)
United Engineering & Contracting Co. v. United States
47 Ct. Cl. 489 (Court of Claims, 1912)
Richtman v. United States
47 Ct. Cl. 483 (Court of Claims, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
46 Ct. Cl. 139, 1910 U.S. Ct. Cl. LEXIS 128, 1910 WL 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-v-united-states-cc-1910.