Helix Electric, Inc. v. United States

13 A.L.R. Fed. 2d 753, 68 Fed. Cl. 571, 2005 U.S. Claims LEXIS 342, 2005 WL 3046514
CourtUnited States Court of Federal Claims
DecidedNovember 10, 2005
DocketNo. 02-478C
StatusPublished
Cited by7 cases

This text of 13 A.L.R. Fed. 2d 753 (Helix Electric, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Helix Electric, Inc. v. United States, 13 A.L.R. Fed. 2d 753, 68 Fed. Cl. 571, 2005 U.S. Claims LEXIS 342, 2005 WL 3046514 (uscfc 2005).

Opinion

OPINION AND ORDER GRANTING SUMMARY JUDGMENT FOR DEFENDANT

WILLIAMS, Judge.

This dispute arises under a contract for the replacement of the electrical distribution system at Keesler Air Force Base (AFB) in Biloxi, Mississippi (the Contract). Plaintiff claims that the Contract gave it the right to become a cable television operator on base and that the Navy breached its implied duty to cooperate and not to hinder this aspect of Plaintiffs performance.

At issue is Section 6.2 of the Contract, which states, “[t]he Contractor must pay Cable One to relocate their [sic] [CATV] system or acquire service from another source.” Def.’s App. at 35-36.1 Plaintiff interprets the phrase “acquire service from another source” to mean that it could acquire CATV service for the base from itself. Plaintiff alleges that the Navy breached the implied covenants to cooperate and not hinder performance by requiring it to obtain a franchise and failing to respond to its requests for dispute resolution, issuing conflicting and erroneous directions on the CATV franchise application process, reversing its position on whether Helix could become a CATV provider, and delaying and ultimately preventing Plaintiff from obtaining a CATV contract on Keesler AFB. Plaintiff seeks $7,722,000 in damages, its estimation of the current market value of the CATV franchise.

This matter comes before the Court ón Plaintiffs motion for partial summary judgment on liability and Defendant’s cross-motion for summary judgment. Plaintiff cannot recover because the Contract cannot be interpreted in the manner Plaintiff suggests. The portion of Section 6.2 which authorized a contractor to acquire CATV services from another source was patently ambiguous in that it radically altered and exceeded the scope of work in the Contract, which was limited to relocation of the electrical distribution system from above ground to underground.2 Plaintiffs interpretation would expand the Contract into a wholly different agreement for provision of CATV services, a function which is governed by a separate statutory and regulatory scheme. Further, Plaintiffs interpretation of the Contract as giving it the right to acquire CATV services from itself should have raised issues about the legality of this provision and caused Helix to inquire prior to bidding.3 Because it [573]*573did not inquire, the Contract must be construed against Plaintiff, precluding its recovery.

Because the Contract did not include the provision of CATV services by Helix, the Contract does not give rise to an implied duty on the part of the Navy to cooperate with Helix in this would-be facet of its performance or impose on the Navy an obligation not to hinder Helix’s performance in this regard.4

Accordingly, Plaintiffs motion for partial summary judgment on liability is denied, and Defendant’s cross-motion for summary judgment is granted.

Factual Background5

The Request for Proposals

On February 2, 1999, the United States Navy issued solicitation number N62467-99R-0883 (the Solicitation), entitled “Design Build Two-Phase Changes to the Electrical Distribution System, Keesler Air Force Base, Biloxi, MS.” Def.’s App. at 5. The Solicitation was issued pursuant to a Comprehensive Master Plan for Keesler Air Force Base (AFB), which detailed construction and engineering projects that were necessary to modernize the base. The project included the replacement of nearly the entire electrical system on the base including labor, equipment, and materials needed to construct substations, transformers, and distribution lines to more than 1200 buildings.6 The Solicitation was comprised of six Parts, consisting of “Proposal Requirements” (Part 1), “Contract Forms and Conditions” (Part 2), “General Requirements” (Part 3), “Prescriptive Technical Specifications” (Part 4), “Performance Technical Specifications” (Part 5), and “Attachments” (Part 6). Funding for this procurement was provided by the FY Omnibus Appropriations Bill, Public Law 105-277.

Part 1, Section 00202, Paragraph 1.3, entitled “Specialized Project Requirement,” described the project as follows:

This RFP is for the design and construction to change the base and family housing electrical overhead systems to underground systems for a cost ranging from $34,000,000 to $37,500,000.00.... The overhead system distributes several communications systems that are a combination of station owned7 and non-station owned systems and a street/area lighting system. This project is to provide a new base main switehing/sub station, new underground power circuits including transformers and secondary conductors, and a replacement of the station owned communication systems. The contractor will be responsible for coordinating and providing facilities to allow for the relocation of communication systems that are not station owned. This will require extensive coordination with communication utility companies. Also, a new base-wide street/ area lighting system is to be provided. The contractor will be responsible for coordinating the entire project. Once the underground system is operational the overhead system is to be removed in its entirety. The project will require medium [574]*574voltage live-line work, substation design/construction, medium voltage distribution design/construction, significant construction/outage phasing, outdoor lighting design/construction, communications systems design/construction, etc. This base must stay in operation for the entire duration of this project.

Def.’s App. at 9. Accordingly, the project contemplated by the Solicitation was in essence, the transfer of Keesler AFB’s utility systems from overhead electrical poles to an underground system. Collins Deck ¶ 6, Def.’s App. at 396.

Paragraph 2 of Section 00202, entitled “Technical Evaluation Factors for Phase II,” listed the factors the Navy would consider in awarding the contract as follows: (i) past performance; (ii) small business subcontracting effort; (iii) technical solutions; and (iv) technical qualifications of all lead design and construction personnel. Def.’s App. at 10-13. There were no evaluation factors addressing provision of CATV services.

Section 00202, Factor C, of the Solicitation set forth the content requirements for the technical proposals that were to accompany bids. Factor C states in relevant part:

Provide a narrative of the technical solution that describes in detail the following:
1. Major equipment and materials to be incorporated into this project. Provide manufacturer catalogue data with appropriate features marked for a minimum of the following:
a. Medium voltage cable
b. Pad mounted switches
c. Sectionalizing cabinets
d. Main switchgears
e. Regulators
f. Load tap changing transformers
2. Discuss commitment and capabilities of the company to be used for locating underground facilities. Describe specialized equipment and methods to be utilized. Discuss commitment to repair any accidental interruptions in a timely manner.
3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Mission Essential Group, L.L.C.
2023 Ohio 3077 (Ohio Court of Appeals, 2023)
Stromness Mpo, LLC v. United States
134 Fed. Cl. 219 (Federal Claims, 2017)
Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
13 A.L.R. Fed. 2d 753, 68 Fed. Cl. 571, 2005 U.S. Claims LEXIS 342, 2005 WL 3046514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helix-electric-inc-v-united-states-uscfc-2005.