Caci, Inc. v. Michael P.W. Stone, Secretary of the Army, and Vse Corporation, Intervenor

990 F.2d 1233, 38 Cont. Cas. Fed. 76,501, 1993 U.S. App. LEXIS 7471, 1993 WL 103707
CourtCourt of Appeals for the Federal Circuit
DecidedApril 9, 1993
Docket92-1163
StatusPublished
Cited by30 cases

This text of 990 F.2d 1233 (Caci, Inc. v. Michael P.W. Stone, Secretary of the Army, and Vse Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caci, Inc. v. Michael P.W. Stone, Secretary of the Army, and Vse Corporation, Intervenor, 990 F.2d 1233, 38 Cont. Cas. Fed. 76,501, 1993 U.S. App. LEXIS 7471, 1993 WL 103707 (Fed. Cir. 1993).

Opinion

PLAGER, Circuit Judge.

The General Services Administration Board of Contract Appeals (Board) declined to suspend defendant Secretary of the Army’s (Army) contract with intervenor VSE Corporation (VSE), even though the Board found that the contract violated regulations because the Army had failed to obtain a prior delegation of procurement authority (DPA). Protest of CACI, Inc., No. 11523-P, 1991 WL 286232 (GSBCA Dec. 19, 1991). Appellant CACI, Inc. (CACI) appeals that decision. Because we find that the contract is void for lack of procurement authority, we reverse the Board’s decision.

BACKGROUND AND PROCEDURAL HISTORY

The Department of the Army, U.S. Army Troop Support Command, solicited bids on April 1, 1991 for providing engineering services and data processing support services to Belvoir Research, Development and Engineering Center. Appellant CACI and in-tervenor VSE were among the companies that submitted bids in response. The con *1234 tract was awarded to VSE on September 30, 1991, and CACI filed a protest with the Board on October 15, 1991. The protest had four counts: Count I alleged that the Army had violated Federal Information Resources Management Regulations, 41 C.F.R. subpart 201-23.1 (1990), by failing to obtain a DPA from the Administrator of General Services Administration (GSA)'before proceeding with the acquisition; Count II attacked the adequacy of the Army’s discussions with bidders; Count III alleged that agency actions may have given VSE. an improper advantage; and Count IV alleged that the Army’s evaluation of the proposals was improper.

CACI moved for summary relief on Count I, requesting an order suspending the procurement until the Army obtained a DPA. On November 15, 1991, the Board denied the relief sought. The Board found no factual dispute concerning the lack of the required DPA: “The Army candidly acknowledges that it did not obtain one, although it was required to do so ...” The Board declined, however, to suspend contract performance (by suspending GSA’s procurement authority) until the Army obtained a DPA, because a suspension of VSE’s on-going services would be disruptive and detrimental to the Army’s mission. In a separate opinion on the same date, the Board denied the Army’s motion to dismiss Counts II and III (as failing to state a valid basis of protest) and Count IV (as untimely because CACI should have known the basis for the count earlier).

In its December 19,1991 final decision on the merits, the Board again refused to suspend the contract, because the Army needed thé services on an on-going basis and had taken necessary steps to obtain a DPA with dispatch. CACI appealed to this court.

DISCUSSION

The Board’s decision on a question of law is not final or conclusive, although its decision on a question of fact is final unless fraudulent, arbitrary, capricious, so grossly erroneous as to necessarily imply bad faith, or unsupported by substantial evidence. 41 U.S.C. § 609(b).

The two issues before us are purely legal in nature and thus freely reviewable: (1) for purposes of decision, may we disregard the Army’s concession to the Board that a DPA was required for the contract, and (2) does the Army’s failure to obtain a DPA before contracting for VSE’s services render the contract void?

A.

The Army asks us to disregard its earlier concession that a DPA was required, because the Army’s former position resulted from a misinterpretation of the applicable regulations. The 1991 regulations required acquisition-specific DPAs for all automatic data processing (ADP) services (now called federal information processing (FIP) services), both support-type and non-support-type, with value exceeding $2.5 million. 41 C.F.R. § 201-20.305-1 (1991). This regulation was effective April 29, 1991. 55 Fed.Reg. 53,386 (199.0); 56 Fed.Reg. 4,948 (1991). Under these regulations the Army would have been required to obtain a DPA for the contract in question because the expected cost of the services was $3 million (according to Solicitation Sec. H.15). Under the 1990 regulations, specific DPAs were required for ADP nonswpport services contracts with value exceeding $2 million. 41 C.F.R. § 201-23.-104-5 (1990). A 1990 regulation, however, gave agencies blanket procurement authority to contract for ADP support services, regardless of cost, without prior approval. 41 C.F.R. § 201-23.104-6 (1990). This regulation was effective October 1, 1990. 55 Fed.Reg. 30,702 (1990); 55 Fed.Reg. 34,719 (1990).

The Army and VSE now argue that the Army had blanket procurement authority for its contract with VSE because first, the 1990 regulations were still in effect when the bid solicitation was published on April 1, 1991, and second, the contract was for ADP support services. The Army thus asserts that it should not be bound by its earlier mistaken interpretation of the law.

*1235 CACI argues that, since the existence of a blanket procurement authority depends on whether the contract was for ADP support services or non-support services, and since this is an issue that the Army did not raise below, the Army has waived the issue. Thus, says CACI, the Army must be bound by its concession that a DPA was required.

The Army admitted to the Board that a DPA was required but had not been obtained. It is too late now for the Army to change its position and thereby assert for the first time on appeal a point which it did not raise before the Board. Because of the Army’s admission, the Board made no factual findings or conclusions on the issue of a blanket procurement authority. The proper time for the Army to have raised this issue, which turns on underlying factual questions, was before the Board; it would be unfair to appellant and would disrupt the orderly conduct of litigation if we allowed the Army to change its position at this stage. See Jamesbury Corp. v. Litton Indus. Prods., Inc., 839 F.2d 1544, 1549, 5 USPQ2d 1779, 1783 (Fed.Cir.1988) (on appeal, Jamesbury cannot dispute its factual admissions after failing to raise the question in district court), cert. denied, 488 U.S. 828, 109 S.Ct. 80, 102 L.Ed.2d 57 (1988), and overruled on other grounds by A.C. Aukerman Co. v. R.L. Chaides Constr. Co., 960 F.2d 1020, 22 USPQ2d 1321 (Fed.Cir.1992) (en banc); cf. CPG Prods. Corp. v. Pegasus Luggage, Inc. 776 F.2d 1007, 1010, 227 USPQ 497, 498 (Fed.Cir.1985) (appellant cannot argue issue that it failed to raise before at trial); cf. Lizut v. Department of Army, 717 F.2d 1391, 1396 (Fed.Cir.1983) (“Allowing a party to withhold important issues from the [Merit Systems Protection] board and later present them to this court would undermine the board’s authority”).

B.

40 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Veterans Contracting Group, Inc. v. United States
920 F.3d 801 (Federal Circuit, 2019)
Liberty Ammunition, Inc. v. United States
835 F.3d 1388 (Federal Circuit, 2016)
Sigma Construction, Inc. v. United States
113 Fed. Cl. 13 (Federal Claims, 2013)
Sperient Corporation, Inc. v. United States
113 Fed. Cl. 13 (Federal Claims, 2013)
Helix Electric, Inc. v. United States
13 A.L.R. Fed. 2d 753 (Federal Claims, 2005)
Strickland v. United States
382 F. Supp. 2d 1334 (M.D. Florida, 2005)
Ruttenburg v. United States
65 Fed. Cl. 43 (Federal Claims, 2005)
Fluor Enterprises, Inc. v. United States
64 Fed. Cl. 461 (Federal Claims, 2005)
McNabb v. United States
54 Fed. Cl. 759 (Federal Claims, 2002)
William O. Schism and Robert Reinlie v. United States
316 F.3d 1259 (Federal Circuit, 2002)
Hawkins & Powers Aviation, Inc. v. United States
46 Fed. Cl. 238 (Federal Claims, 2000)
Melrose Associates, L.P. v. United States
43 Fed. Cl. 124 (Federal Claims, 1999)
Cubic Applications, Inc. v. United States
41 Cont. Cas. Fed. 77,075 (Federal Claims, 1997)
Foley Co. v. United States
41 Cont. Cas. Fed. 77,014 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
990 F.2d 1233, 38 Cont. Cas. Fed. 76,501, 1993 U.S. App. LEXIS 7471, 1993 WL 103707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caci-inc-v-michael-pw-stone-secretary-of-the-army-and-vse-cafc-1993.