Sexton v. City of Chicago

107 Ill. 323, 1883 Ill. LEXIS 266
CourtIllinois Supreme Court
DecidedJune 16, 1883
StatusPublished
Cited by22 cases

This text of 107 Ill. 323 (Sexton v. City of Chicago) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sexton v. City of Chicago, 107 Ill. 323, 1883 Ill. LEXIS 266 (Ill. 1883).

Opinion

Mr. Justice Mueket

delivered the opinion of the Court:

This was an action of indebitatus assumpsit, brought by Patrick J. Sexton, the appellant, in the Superior Court of Cook county, against the city of Chicago, the appellee, to recover a balance claimed to be due for work done and materials furnished by him, and used and appropriated by the city in the construction of the iron work for the new city hall. To the declaration the city filed the plea of non assumpsit, and the cause, by agreement of parties, was submitted to the court without the intervention of a jury, resulting in a finding and judgment for the defendant. On appeal to the Appellate Court for the First District the judgment of the Superior Court was affirmed, and Sexton thereupon appealed to this court.

Notwithstanding the voluminous record before us, the real controversy in the case is confined to very narrow limits. As claimed by appellee, we have nothing to do with the controverted questions of fact raised by the pleadings or evidence in the case. They have all been settled adversely to the appellant, and we have no power or disposition to review them. While this is so, it is nevertheless the duty of this court to examine the evidence bearing upon the issues of fact thus determined, to see what principles of law were involved in the controversy, and whether they were properly applied by the trial court.

On the trial of this cause the court refused to hold certain propositions of law, which we think were appropriate to the facts in the case, and that in doing so there was error, for which the Appellate Court should have reversed the judgment. The refused propositions are as follows:

“6. If, in consequence of differences between the several sets of plans furnished by the city as a guide for estimates of the work then proposed to be let, and in consequence of the use by Sexton of one set of such plans so furnished to him for making his estimates, differences naturally arose between Sexton and the city as to the amount of work then to be let, and Sexton’s bid, made upon the plans submitted to him, was accepted by the city, and was made the foundation of the contract between the city and Sexton, which has been offered in evidence, then the words ‘plans,’ ‘diagrams’ and ‘drawings,’ mentioned in the contract,' should, as between Sexton and the city, be held to refer to the plans, etc., furnished by the city, upon which Sexton based his estimates and his bid, the differences in the sets of plans were the fault of the city or its officials, and the city can not take advantage of its own wrong, to the prejudice of Sexton.

“7. If the differences of understanding as to the amount of work to be done resulted from the cause and in’ the manner suggested in the last preceding proposition, then either the contract must be construed in accordance with the plans, etc., furnished to Sexton, and upon which he based his bid, or there was, as a matter of law, no contract between Sexton and the city, notwithstanding the signing of the paper purporting to be such contract; and in the latter case Sexton is entitled, in the present action, to recover the fair value of the work done and materials furnished by him, and which have been accepted by the city, upon the basis of a quantum meruit. ”

In order to fully understand these propositions and their legal relation to the ease in hand, it will be necessary to examine to some extent the evidence, bearing in mind the chief object in adverting to the testimony at all is to ascertain whether there is evidence in the record tending to establish the hypothetical case made by the propositions. We say “tending to establish,” for, as is well understood, it is not necessary there should be a preponderance of evidence to warrant the giving of such propositions, if otherwise unobjectionable. Our consideration of the evidence then being for the purposes stated, it will only be necessary to refer to such parts of it as, in our judgment, tend to establish the hypothesis in question.

It appears from the record that prior to the 30th of March, 1878, the city of Chicago, with the view of building a new city hall, had, by its architect and the draughtsmen under him, prepared a general plan of the building, which -consisted of numerous drawings and specifications, showing, in distinct views or subordinate plans, the different parts of the building, and the different kinds of work and material required in its construction, and the manner in which the same was to be done. These distinct views or sub-plans were also divided into sections, which were numbered in numerical order. The city had, also, prior to the date last above mentioned, with the view of facilitating bidding bn the different parts of the work, and, as we understand it, for the purpose of furnishing each contractor after the work was let' •with a distinct plan relating mainly to his own work, caused a number of partial copies or duplicates of these subordinate plans of the work to be prepared, some of them showing the. stone work, others the iron work, and so on, and also so much 'of the general plan as was necessary to show the relation of. the specific work to it, and that they, together with the general or original plan, were on file in the office of the department of public works belonging to the city, prior to and at the time the city advertised for the, letting of the work in controversy. On the day last mentioned, to-wit, on the 30th of March, 1878, the city advertised for bids on the stone, brick' and iron work of the building. The appellant, being a contractor by profession, and desirous of bidding on the iron work, applied at the proper office of the city and was furnished by the party then in charge of the office with one of the above mentioned duplicate plans of the iron work, for the express purpose of enabling him to make his estimates with a view of bidding on the work. Having made his estimates from the plan thus furnished' him by the city, on the 8th of the following month he made a formal bid, by which he offered to furnish the materials and do the iron work, according to plans and specifications, for the sum of $105,302.69, which was accepted by the city, and, on the 17th of the same month, a formal contract to that effect was drawn up and mutually executed by the parties, in which the city reserved the right to forfeit the contract, or any part of it, for any breach or default on the part of appellant in its performance. On thus letting the iron work to appellant, the city, in conformity with the general custom to that effect, furnished him with the same plan and specifications of the work which had been previously given to him to make his estimates by, to be used by him in doing the work under the contract. Under these circumstances he commenced and proceeded with the work to the entire satisfaction of the city, so far as the record shows, until he came to construct the roof, when the city, on the 22d of December, 1880, declared his contract forfeited, on two grounds: First, because appellant refused to furnish “T” iron rafters for the roof weighing from ten and one-fourth to thirteen and one-half pounds per lineal foot; and second, because he declined to furnish the materials and construct the superstructure of the sky-lights. The appellant then and now insists that a proper construction of his contract with the city did not and does not require him to comply with either of these demands, which were made the occasion of declaring a forfeiture of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowser, Inc. v. Hamilton Glass Co.
207 F.2d 341 (Seventh Circuit, 1953)
Hancock v. Village of Hazel Crest
47 N.E.2d 557 (Appellate Court of Illinois, 1943)
Ambursen Dam Co. v. United States
86 Ct. Cl. 478 (Court of Claims, 1938)
Espenschied v. Yeager
278 Ill. App. 508 (Appellate Court of Illinois, 1935)
Totten v. Houghton
2 S.W.2d 530 (Court of Appeals of Texas, 1927)
Drainage Dist. No. 1 v. Rude
21 F.2d 257 (Eighth Circuit, 1927)
State ex rel. Ottesen v. Clausen
223 P. 591 (Washington Supreme Court, 1924)
Holmes v. City of Chicago
203 Ill. App. 445 (Appellate Court of Illinois, 1917)
Griffiths v. Sanitary District
174 Ill. App. 100 (Appellate Court of Illinois, 1912)
Atlantic Terra Cotta Co. v. Masons' Supply Co.
180 F. 332 (Sixth Circuit, 1910)
Moore v. United States
46 Ct. Cl. 139 (Court of Claims, 1910)
McLean County Coal Co. v. City of Bloomington
84 N.E. 624 (Illinois Supreme Court, 1908)
City of Chicago v. Duffy
117 Ill. App. 261 (Appellate Court of Illinois, 1904)
Northwestern Elevated Railroad v. City of Chicago
1 Ill. Cir. Ct. 480 (Illinois Circuit Court, 1904)
City of Chicago v. A. R. Beck Lumber Co.
93 Ill. App. 70 (Appellate Court of Illinois, 1901)
Salt Lake City v. Smith
104 F. 457 (Eighth Circuit, 1900)
Mantonya v. Reilly
56 N.E. 425 (Illinois Supreme Court, 1900)
Mantonya v. Reilly
83 Ill. App. 275 (Appellate Court of Illinois, 1899)
McKey v. Nelson
43 Ill. App. 456 (Appellate Court of Illinois, 1891)
City of Elgin v. Joslyn
26 N.E. 1090 (Illinois Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
107 Ill. 323, 1883 Ill. LEXIS 266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sexton-v-city-of-chicago-ill-1883.