Atlantic Terra Cotta Co. v. Masons' Supply Co.

180 F. 332, 103 C.C.A. 462, 1910 U.S. App. LEXIS 4762
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 13, 1910
DocketNo. 2,026
StatusPublished
Cited by5 cases

This text of 180 F. 332 (Atlantic Terra Cotta Co. v. Masons' Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Terra Cotta Co. v. Masons' Supply Co., 180 F. 332, 103 C.C.A. 462, 1910 U.S. App. LEXIS 4762 (6th Cir. 1910).

Opinion

WARRINGTON; Circuit Judge

(after stating the facts as above). The main question is whether plaintiff obligated itself to deliver for the sum of $12,600 all or only a part of the terra cotta which was used in the construction of the -Hippodrome building. The solution of the question must depend upon whether the contract of July 26, 1906, was intended to include certain lintels and sills of terra cotta on' the sides of the building. It is claimed on behalf of the plaintiff that this is a question of fact, and on behalf of defendant that it is a question of law. Although no opinion was rendered either upon the motion to direct or upon the motion for a new trial, we gather from an interlocutory statement made during the progress of the trial that the learned judge was “inclined to the opinion that the contract covers all of the terra cotta work to be furnished as gathered from the plans and specifications”; or, as otherwise stated, plaintiff was “bound to furnish terra cotta work described in the specifications but which was not shown on the plans.”

The issue thus presented arose upon a dispute relative to certain papers upon which plaintiff claims to have submitted its bid and en[335]*335tered into the contract. Plaintiff claims that only two drawings were received by it, to wit, the Euclid and Prospect avenue elevations, and that no side elevations, floor plans, or specifications were received; but defendant claims the contrary. There is conflict upon the issue so made, both in the testimony and correspondence offered. It is insisted by defendant, however, that this conflict is not material, because the contract in terms requires plaintiff “to provide all the material and perform all the work for the delivery of terra cotta f. o. b. cars at destination, shown on drawings and described in specifications prepared” by the architects.

Shortly after the contract was signed (August 3, 1906), the defendant notified plaintiff by letter that it was sending to it by express “plans and specifications, together with three-quarter scale drawings for the Cleveland Hippodrome building,” and requesting plaintiff to get “full sized working drawings out and return to us for architects O. K. at once.” Plaintiff replied to this by letter of August 9th, stating:

“In looking over the drawings recently sent for this order, we find among them additional drawings showing side lintels of terra cotta. These drawings were never sent to us before, consequently were not figured by us in our estimate to you. * * * We received the specifications after we had signed the contract. We trust that there will be no misunderstanding as to our part in this matter, as everything seems to us clear. Undoubtedly the original intention was to have these lintels and sills in some other material except terra cotta.”

Plaintiff stated further that it was inclosing its estimate for side lintels and sills in terra cotta.

This resulted in much correspondence; defendant claiming and plaintiff denying that it (plaintiff) had received a copy of the specifications. Plaintiff expressed its willingness to perform the contract, but declared it would “not include material that is not included in same”; and again that it would “not make sills and lintels without extra order.” In this correspondence it appears that terra cotta companies other than plaintiff had declined to bid on certain papers submitted by defendant, and defendant claimed that it had in consequence sent additional papers not only to other terra cotta companies, but to plaintiff. While neither company seems to have receded from its original claim, their correspondence by mail and telegrams culminated in a settlement of the dispute by a proposition of plaintiff in a letter of September 11th, and accepted by defendant, as follows:

“Will proceed to fulfill our contract leaving all disputes to arbitration in accordance with article three of our agreement. * * * ”

The arbitration clause so referred to is stated in a letter of plaintiff thus:

“All disputes or disagreements of any nature whatsoever arising under this agreement shall also be referred to and settled by the arbitrators. * * * ”

Defendant’s letter of September 13th, accepting plaintiff’s proposition of September 11th, contains also this statement:

“The settlement of any question in difference, to be arbitrated as per article 3 of your contract. In reference to the color of terra cotta, you will [336]*336please disregard the sample of granite recently sent you, as the Hippodrome board have made a'change to a pinkish granite. * * * As there has been considerable delay in the progress of this work, it will be necessary to revise the time limit for the delivery of same. * * * The sills and lintels for the theater portion of the building, you will please bear in mind, will be wanted first. * * * ”

Plaintiff thereupon supplied the terra cotta in dispute and also made the replacements mentioned in the pleadings; and, while defendant admitted the reasonableness of the charge for the replacements, the parties failed to agree upon a submission either to the architects or to arbitrators of the question relating to the terra cotta used for lintels and sills upon the sides of the building. The provision for arbitration contained in the contract provided that “the decision of any. two of whom (arbitrators) shall be final and binding.” Efforts were made to formulate new articles of arbitration, but failed because of defendant’s refusal “to sign papers in said matter which provide that a decision of a majority of the arbitrators is final,” stating further that “we will treat this as a closed instance.”

It will be recalled that the first cause of action of the petition is formulated upon the theory that plaintiff had not by its contract agreed to deliver, for $12,600, terra cotta for the side lintels and sills or to make the replacements mentioned; that it was sought to recover the reasonable value of those items as extras; and that in the second cause of action recovery is sought as upon a quantum valebat. It is further to be borne in mind that in the answer the defendant admitted that there was due to the plaintiff under the contract as defendant interpreted it a balance of $304.03, and as an extra the sum of $60 for replacements, with interest on both sums from October 9, 1907. It is averred also in the answer that defendant “tenders” these sums and brings them “into court with its answer herein”; but we do not discover any evidence offered in support of this averment; nor do we understand that the matter was disposed of when the condition of the pleadings in respect to the sums mentioned in the answer was under consideration by the court and counsel during the progress of the trial.

Now, was defendant entitled to a directed verdict upon this record? Can it be rightfully maintained that plaintiff was not entitled to a recovery of any sum whatever? It might be sufficient to say that it was entitled to recover at least the sums admitted to be due. But, aside from this, we shall consider the more important question whether as matter of law plaintiff was bound to supply terra cotta for the side lintels and sills. Plainly there were two sets of different instruments submitted to some manufacturers, of terra cotta, who were prepared to make proposals.' Some of them would not bid on. one set of these papers. The defendant would seem prima facie to be responsible for the mistake if there were any in the submission of papers to bidders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
180 F. 332, 103 C.C.A. 462, 1910 U.S. App. LEXIS 4762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-terra-cotta-co-v-masons-supply-co-ca6-1910.