Ambursen Dam Co. v. United States

86 Ct. Cl. 478, 1938 U.S. Ct. Cl. LEXIS 221, 1938 WL 4058
CourtUnited States Court of Claims
DecidedMarch 7, 1938
DocketNo. 42235
StatusPublished

This text of 86 Ct. Cl. 478 (Ambursen Dam Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ambursen Dam Co. v. United States, 86 Ct. Cl. 478, 1938 U.S. Ct. Cl. LEXIS 221, 1938 WL 4058 (cc 1938).

Opinion

Williams, Judge,

delivered the opinion of the court:

In response to an invitation of the defendant, the plaintiff, on August 18, 1926, submitted its bid for the construe[507]*507tion of a dam, known as the Stony Gorge Dam, across Stony Creek for the Orland irrigation project about 8 miles west of Fruto, California. It was stated in the invitation for bids that the principal items involved are about 19,000 cubic yards of excavation; about 37,200 cubic yards of concrete; drilling and grouting about 7,000 linear feet of grout holes; bending and placing of about 1,500,000 pounds of reinforcing steel; and installing about 892,000 pounds of valves,, gates, and other metal work. Forty-two separate items of work were enumerated in the invitation, and unit prices were invited for the various classes of work involved.

Prior to advertising for bids the defendant made an investigation of the site for the proposed dam to determine, its suitability therefor, and to decide on the type of dam to be constructed. In making this investigation core-drill test-holes were drilled in the bottom of the creek and test pits.were made in the locations for the dam abutments where solid rock was not exposed. The results of these investigations were made available to bidders through the invitation, for bids, although it was stated that “the accuracy of the interpretation of the facts disclosed by borings or other preliminary investigations is not guaranteed.” Prior to the. invitation for bids the defendant had also prepared detailed, drawings and specifications covering the work to be done-These specifications, together with a circular advertisement inviting bids on the proposed work, were furnished plaintiff. Prior to the submission of its bid plaintiff made a personal investigation at the site of the proposed dam. The plaintiff’s bid was accepted, and on October 2, 1926, the plaintiff and the defendant entered into a formal contract for the construction of the dam. The plaintiff’s bid and the specifications of the work were incorporated in and made a part of the contract.

The contract in general provided that materials entering into the construction of the dam, including cement and structural steel and reinforcing steel, would be furnished by the defendant and that the labor thereon would be performed by the plaintiff. It provided for the performance of 42' separate items of work, which with a single exception would be paid for at unit prices. The concrete to be placed. [508]*508in the dam appeared under 14 different classifications. The unit prices with respect to the pouring of the concrete varied from $6.00 per cubic yard for upstream and downstream cutoffs and buttress footings to $20.00 for 24-inch circular conduit from 10-inch outlet valve, and the estimated quantities ■.shown varied from 70 cubic yards for “trash rack structure ■floors” and 100 cubic yards for “24-inch circular conduit” to 23,500 cubic yards for “buttresses including tongues and •corbels.”

The plaintiff began operations by the removal of the earth •from the top of the rock and when rock was reached it was ascertained that the rock was of such a character as not to he suitable for the construction of the dam as originally planned. Plaintiff called this fact to the attention of the •engineer, and a board of experts appointed by the defendant visited the site, examined the conditions, and rendered a report in which certain definite and material changes in respect to the construction of the dam were recommended. .’Subsequently, the chief engineer of the Bureau of Keclamation visited the site, made a personal investigation of the ■conditions, and approved the recommendations of the board. The Denver office of the defendant later prepared drawings for the performance of the work in accordance with the modified plans agreed upon by the defendant’s officers, and the work under the contract thereafter was carried on and •completed by plaintiff in accordance therewith. In carrying forward such work differences arose between the plaintiff and the defendant in respect to payment of various items involved. Many of these differences were satisfactorily adjusted. Certain differences, however, were impossible of adjustment and plaintiff upon settlement for the work performed by it under the contract reserved the right to maintain suit on the following items:

1. Out-off wall, $%3ftl(O.Of. — The cut-off wall as contemplated by the original specifications and drawings was to be a vertical keystone-shaped wall of concrete extending across the upstream toe of the dam and which was to form a •connection between the upstream portion of the dam and amderlying rock. Under the original plans this was to be [509]*509poured into a trench excavated into the solid rock. The sides and bottom of the rock would be irregular and jagged in shape and contour and the concrete being poured into this sort of a trench would become keyed and bonded into the solid rock. The top of the cut-off wall was to have a plane or flat surface about level with the surface of the rock and there was to be a construction joint at the top of this cut-off wall. The face-slab was to fit into this construction joint on top of the cut-off wall and was then to slope upward in a downstream direction at an angle of 45 degrees. Under such plans there would be absolutely no reason for any form work in the construction of the cut-off wall because the concrete was to be poured into the rock trench and the sides and bottom of the trench would form the retaining surfaces for the concrete. The cut-off wall was to be poured as one operation separate from the face slabs and the buttresses. Under the new plan the original cut-off wall was not constructed as a continuous wall but as a separate mass of blocks. The •engineers issued separate plans for the blocks between each pair of buttresses. The cut-off blocks were entirely different in every respect from the cut-off wall originally designed, some of the major differences being as follows: the original cut-off wall was to be poured into a trench in the rock while the new cut-off blocks were not poured into a trench; the original cut-off required no forms while the new cut-off blocks required forms on all sides except the bottom; the reinforcing steel in the new cut-off blocks was different from that in the old cut-off wall; the shape of the cut-off blocks was different from that of the old cut-off wall; the size of the new cut-off blocks was entirely different from that of the old cut-off wall; there was no construction joint on the top of the cut-off blocks, whereas such a joint existed on the top of the cut-off wall; the old cut-off wall was to be poured as a separate operation from the buttresses and face slab, whereas in the new cut-off block part of the face slab and buttresses was poured at the same time; the old cut-off wall was separate from the buttresses and face slab while ■ the new cut-off blocks included a part of the buttresses and .face slab; the cost of constructing the cut-off blocks was [510]*510greatly increased over what it would have cost to have constructed the cut-off wall.

As the work proceeded in the construction of the cut-off' blocks, the defendant made tentative classifications of the-concrete in these blocks for the purposes of monthly payments, and plaintiff was advised that these were only tentative and a final determination would be made at the end of' the work. Plaintiff protested the tentative payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wood v. Fort Wayne
119 U.S. 312 (Supreme Court, 1886)
Henderson Bridge Co. v. McGrath
134 U.S. 260 (Supreme Court, 1890)
Freund v. United States
260 U.S. 60 (Supreme Court, 1922)
Chicago & Great Eastern Railway Co. v. Vosburgh
45 Ill. 311 (Illinois Supreme Court, 1867)
Western Union Railroad v. Smith
75 Ill. 496 (Illinois Supreme Court, 1874)
Sexton v. City of Chicago
107 Ill. 323 (Illinois Supreme Court, 1883)
County of Cook v. Harms
108 Ill. 151 (Illinois Supreme Court, 1883)
Kirk v. L. Wolf Manufacturing Co.
8 N.E. 815 (Illinois Supreme Court, 1886)
City of Elgin v. Joslyn
26 N.E. 1090 (Illinois Supreme Court, 1891)
Six Companies, Inc. v. United States
85 Ct. Cl. 687 (Court of Claims, 1937)
Salt Lake City v. Smith
104 F. 457 (Eighth Circuit, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
86 Ct. Cl. 478, 1938 U.S. Ct. Cl. LEXIS 221, 1938 WL 4058, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ambursen-dam-co-v-united-states-cc-1938.