Western Union Railroad v. Smith

75 Ill. 496
CourtIllinois Supreme Court
DecidedSeptember 15, 1874
StatusPublished
Cited by14 cases

This text of 75 Ill. 496 (Western Union Railroad v. Smith) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Union Railroad v. Smith, 75 Ill. 496 (Ill. 1874).

Opinion

Mr. Chief Justice Walker

delivered the opinion of the Court:

It appears that on the 29th day of March, 1865, Eandall W. Smith entered into an agreement with the Northern Illinois Eailroad Company to grade and construct the earth-worlc on the line of then* road, between Fulton and Port Byron. The contract was in writing, and signed by the parties. From time to time there were changes made in the contract, by the company agreeing to pay him for grubbing, for rock excavation, and trestle-work, at prices specified in the additional agreements. Smith proceeded with the performance of the work, until in October of that year, when, by a mutual agreement of all parties, the contract was transferred to appellee, a brother of E. W. Smith. He was to proceed to the completion of the work, on the same terms as specified in the agreement. They were to pay him the same prices, and in the same manner.

Appellee proceeded with the work, and the company paid him on monthly estimates, making them in his name and payments to him. Subsequently, appellee contracted to lay seventeen miles of track for the company. He commenced in the latter part of October, and continued at the work until he laid all of the iron the company had provided, when he suspended the work. But about the first of January, the company having procured iron, he proceeded to lay the balance of the track, which amounted to four and one-half miles. This was done when the ground was frozen, and the surface was a portion of the time covered with ice. The contract provided that the track should be laid before the ground should freeze, but that was rendered impracticable, because of the failure of the company to furnish the iron necessary for the purpose. By the contract, the company were to pay him four hundred dollars per mile for laying the track, to furnish an engine and flats properly manned, but he to load and unload materials used in laying the track and surfacing it.

Appellee also used a large quantity of stone in casing embankments, to protect them from being destroyed by the washing of water. About this item there is a total disagreement of the parties as to price, etc.- Appellee claims this was work not embraced in his brother’s contract, whilst the company' contend that it is. He claims that he is entitled to pay for ballasting, or tilling the track, between the ties, and for making a fill and grading in the streets of Port Byron. He also claims for services, in taking charge of the hands of the company, for himself and son, in protecting the road against high water for half a month, in May, 1866, and he claims interest on these various sums, at the rate of ten per cent. The company charged him with the use of an engine, $1,320, which they deducted from his estimates and retained, which he insists is wrong, as he had paid $1,000 in full for the use of the engine. The jury found a verdict in his favor for $9,538.08, being the items which he claimed, and ten per cent interest per annum. The court below rendered a judgment on the verdict, and the company appeal to this court.

It appears that on the 17th day of January, 1866, The northern Illinois Eailroad Co. and The Western Union Eailroad Co. consolidated and formed a new company, under the name of The Western Union Eailroad Co. Hence, it will be observed that a portion of the work for which appellee claims was performed before, and a portion after the consolidation. But it was agreed by the articles of consolidation that the new company should assume the debts and liabilities of the old companies, and should carry out and perform all of the unexecuted contracts. And the act of the general assembly, ratifying and confirming the consolidation, saves the rights and remedies of creditors, etc. Sor is there any question made, nor do.we see how any can be, as to the right of appellee to sue and recover, if he has a meritorious claim.

It is urged, with great apparent earnestness, that when the last discussion of their accounts occurred between appellee and Thompson, the president of the road, and appellee received a part of his claim, it should be held and treated as a final settlement. There is no rule of law declaring that such acts amount to, or operate as, an estoppel. What the parties did and intended at that interview, like any other fact, must be ascertained from the testimony of witnesses, in connection with the accompanying circumstances. And from the testimony of both Thompson and appellee, we fail to learn that either party understood it as a final settlement. The president seems to have allowed what he supposed to be right, and to wholly ignore appellee’s claim, and paid him on his own views of what was just and proper. But there can be no pretense that appellee assented to the arrangement, but, on the contrary, he, Thompson, and young Smith, all say that he protested against the disallowance of his claim. We think there is not the slightest pretense that he ever assented to, or was satisfied with, what was then done, or that he ever intended to relinquish his claim. He took the money that was offered him, but signed no release, acquittance or discharge of the company.

Whether it is necessary, and a part of the undertaking of the person contracting to lay the track of a railroad, to fill up between the ties with earth, or other proper substance, is a question of fact. It must depend upon the usage in such cases. We know that many things are indispensable to complete the road. It must be graded, bridged, furnished with culverts, embankments and fills. It must be tied, and the iron laid and secured, and then it must, to be a finished and complete road, be filled and leveled between the ties with broken stone, earth or gravel. Appellee agreed “ to make up the track in good running order, well surfaced, ties evenly and firmly bedded, and 2,600 good ties to be put in per mile, joints to be properly set between ties, fastened with clasp joint, supplied for the purpose, properly fitted and driven on so as to hold an equal portion of each rail, and no greater space to be left between' the ends of the rails than sufficient for expansion,” etc.

The difficulty seems to arise as to what is embraced in the term “ surfaced.” Does it mean that the road-bed shall be properly leveled and adjusted to receive the ties so as to render their surface even and level ? Or does it embrace that, and the filling of the space under and between the ties ?

The witnesses called by the different parties seem to disagree as to which meaning is embraced in the term. It seems to us that the meaning of the word, as used in this connection, is indefinite, and may be variously applied. Appellee and his witnesses understand it to only require that the surface of the ties shall be brought to a level, horizontal line, both lengthwise and laterally. On the other hand, the witnesses say that it is to fill the spaces between the ties. The term in this case is, no doubt, employed in the' sense applied by those engaged in the construction of such roads. We cannot determine from the evidence that it only embraced what is claimed by appellee. It may, however, be shown on another trial. There was some evidence tending to show that the engineer directed him to fill in the earth, and he should be paid, but this is flatly denied by the engineer, and it is for the jury to say on which side was the preponderance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hennecke v. Harold Warp & Flex-O-Glass, Inc.
107 N.E.2d 185 (Appellate Court of Illinois, 1952)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
Ambursen Dam Co. v. United States
86 Ct. Cl. 478 (Court of Claims, 1938)
Drainage Dist. No. 1 v. Rude
21 F.2d 257 (Eighth Circuit, 1927)
Obermeyer v. Wisconsin Dairy Farms Co.
199 Ill. App. 568 (Appellate Court of Illinois, 1916)
Lehmann v. Warren Webster & Co.
110 Ill. App. 298 (Appellate Court of Illinois, 1903)
Salt Lake City v. Smith
104 F. 457 (Eighth Circuit, 1900)
Ostrander v. Scott
60 Ill. App. 322 (Appellate Court of Illinois, 1895)
Langhorne v. Richmond City Ry. Co.
19 S.E. 122 (Supreme Court of Virginia, 1894)
City of Moundsville v. Ohio R. R.
16 S.E. 514 (West Virginia Supreme Court, 1892)
Payne v. McLean
44 Ill. App. 354 (Appellate Court of Illinois, 1892)
Louisville & Nashville Railroad v. Hollerbach
5 N.E. 28 (Indiana Supreme Court, 1886)
County of Cook v. Sexton
16 Ill. App. 93 (Appellate Court of Illinois, 1885)
Railroad Co. v. Steinfeld
42 Ohio St. (N.S.) 449 (Ohio Supreme Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
75 Ill. 496, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-union-railroad-v-smith-ill-1874.