County of Cook v. Sexton

16 Ill. App. 93, 1884 Ill. App. LEXIS 197
CourtAppellate Court of Illinois
DecidedFebruary 5, 1885
StatusPublished
Cited by3 cases

This text of 16 Ill. App. 93 (County of Cook v. Sexton) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Cook v. Sexton, 16 Ill. App. 93, 1884 Ill. App. LEXIS 197 (Ill. Ct. App. 1885).

Opinion

Lacey, J.

The defense set up to the right of recovery of the appellee is that the causes of delay was in great part due to the fault of the other contractors and not by appellant, and that as to damages arising from such causes he had, in all his contracts with it, stipulated that he would not claim them.

It is claimed that upon this point the court improperly instructed the jury on the part of the appellee, and erroneously refused to properly instruct on the part of appellant. It is further claimed that the verdict is against the weight of the evidence, in that the jury gave to appellee, by their verdict^ all the damages accruing to him according to his claim on account of delays occasioned by whatever cause, while it was clear that appellant was not responsible for a large part of the delay if any; that the court below also by instruction given to the jury on its own motion, left it to them to construe the meaning of the contracts which the court should have done itself. In order to arrive at a proper understanding of the questions and points involved it will be necessary to examine the amount of damages claimed by appellee in each of the contracts and the cause thereof and the evidence bearing thereon somewhat in detail. And first we will consider the question involved under the contract for the masonry, iron and brick work, dated Nov. 28, 1876. The appellee claims damages thereunder for delays caused as he alleges by the appellant, for each of the years 1877, 1878, 1879, 1880, 1881. But before proceeding to consider the question we will state what we hold the law to be bearing upon the question of damages as well as on the liability of the appellant for the several delays.

The questions here raised are whether appellee, under all the circumstances, is entitled to retain the contract, so far as it can be traced, and recover the damages for increased expense in doing the work after the time for the completion of the contract had expired, in addition to the contract price, or whether he can abandon the contract entirely and recover for the reasonable value of all the labor and materials expended in the completion of the work, the county having received the benefit thereof, or whether having finished the work after the alleged breaches he could claim more compensation than the contract price.

After a careful investigation of the law and the facts in the case we have concluded to hold that the jnst and proper rule would be to allow the appellee to retain the contract, so far as it can be traced, and to recover the contract price, and in addition such damages or increased compensation, after the time for the completion of the contract had expired, as he can show was the proximate result of any breach of the contract express or implied, by the county, and that in favor of the latter all the provisions of the several contracts should remain in force until their final completion by appellee, except as to the time of fulfillment and the compensation, where affected by breaches by the county.

The law bearing on the question is not free from doubt, but we think the rule, as announced, is sustained by the authorities cited by appellee’s counsel, and it commends itself to us as being just and equitable. Alleman v. The Mayor, etc., of Albany, 48 Barb. 34; Dubois v. Delaware and Hudson Canal Co., 4 Wend. 285; Koon v. Graham, 7 Wend. 123; The Delaware and Hudson Canal Co. v. Dubois, 15 Wend. 87; Dermott v. Jones, 2 Wall. 1; Lincoln v. Schwartz et. al., 70 Ill. 134. In support of the negative of the last proposition, the appellant’s counsel in his brief makes the point, but it is not argued or referred to afterward, that the appellee having completed the contracts after the time had expired, affirmed it and could not disaffirm it and bring his action for alleged breach, and cites W. U. R. R. Co. v. Smith, 75 Ill. 496, as authority. In that case the railroad company had agreed to furnish iron, and Smith had agreed to lay the railroad track, before the ground froze in the winter. The railroad company failed to do this, but furnished it after the ground froze, and Smith, without making any complaint of the failure to furnish it before, went on and laid the track at a greatly increased cost, which he sought to recover; but the court in passing on the claim said, that as he had finished the work without any further agreement or understanding, the reasonable presumption would be that he was intending to perform the labor under the agreement.

But in this ease it will be observed that the appellee frequently notified appellant that he would not do the work, when delay was caused by it, for the same price stipulated under the contract, but would claim all the “ damages” caused by the several delays. He did not notify it that he would abandon the contract and sue for the reasonable value of the work and labor, but would claim “ damages” for the delays. If he had abandoned the contract entirely they could have paid him for what he had done up to that time and discharged him, but from his notices they could not so understand it, but that he claimed the benefit of the contracts. Mor do we understand from the appellant’s briefs that it seriously contests the right of appellee to recover damages arising after the breach of the contracts, if any, caused by delay for which it was responsible. Its main argument and contention is that the delays were caused by other contractors, damages for which appellee had agreed to make no claim against it.

We do not think, under the circumstances, that appellee would have the right to recover entirely for the reasonable value of the work without reference to the contracts, if this would be more than the contracts called for. The contract can not be regarded as wholly abrogated.

To return again to appellee’s claim for damages under the contract of date Movember 23, 1876.

The appellee testifies that the damages accruing to him by reason of all delays on the contract mentioned, spread over the entire time, was three dollars per thousand on 17,000,000 brick laid, amounting to the sum of §52,500, and his damages on the iron was §30,000, and his damages for interest and discount was §30,000, making in the total §112,500. The jury, of this account, allowed him §81,060.10, rejecting the §30,(h 0 for discount on county orders and interest, being nearly the entire claim. What were the specific causes of these damages and for what portion was the appellant responsible % It will not be necessary to recite the substance of all the evidence, but enough of it only to show what the evidence tended to prove as to who was responsible for the various delays caused to appellee and how they affected him. -We will mostly recite from appellee’s testimony, supposing he understands his own case best. His specifications of the causes of delays and damages are these: In the year 1877 he was ordered to begin laying the brick, March 1, 1877, but actually begau about the middle of April. The first cause of delay was changes in the cut-stone contract between the appellants and McMeil & Son, or Walker, requiring thick stone to be laid in the outer wall instead of thin, as the contract first required. The stoppage on this account was not very great — less than thirty days, but after that the stones came very slowly — they began to come about June, 1877. The next cause was the granite contract made with the Hinsdale Granite Company, which delayed tlie work at the four entrances of the court house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
16 Ill. App. 93, 1884 Ill. App. LEXIS 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-cook-v-sexton-illappct-1885.