Delaware & Hudson Canal Compant v. Dubois

15 Wend. 87
CourtCourt for the Trial of Impeachments and Correction of Errors
DecidedDecember 15, 1835
StatusPublished
Cited by6 cases

This text of 15 Wend. 87 (Delaware & Hudson Canal Compant v. Dubois) is published on Counsel Stack Legal Research, covering Court for the Trial of Impeachments and Correction of Errors primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware & Hudson Canal Compant v. Dubois, 15 Wend. 87 (N.Y. Super. Ct. 1835).

Opinion

The following opinions were delivered :

By the Chancellor.

This ease comes before us upon a writ of error to the supremecourt, to review its decision upon a report of referees, incorporated in the record in the form of a ease or special report. It appears from this record of the judgment of the supreme court, that the parties went down to trial at the circuit, where a stipulation was entered into by them to submit certain preliminary questions as to the right of the plaintiff to recover on the common

counts, &c. to the decision of the supreme court; and they agreed that the cause should be submitted to referees,'appointed .by rule of court, to take the account; between the parties in respect to certain labor done by the plaintiff on the Delaware and Hudson canal, in conformity to the decision of the court upon such preliminary questions. The supreme court having decided those questions before the reference was proceeded in, and neither of the parties having availed themselves of the right, reserved by the stipulation, of placing the questions on the record in the form of a bill of exceptions or special verdict, for the purpose of having them reviewed by this court, the decision of the supreme court upon those preliminary questions must now be considered, by the agreement and understanding of the parties, as the law of this case.

The substance of that decision, so far as I can understand it from the reported decision of Mr. Justice Marey, 4 Wend. 288, is that the special agreement under which Dubois commenced his work upon the canal, was rescinded by the acts, or rather by the omission of the agents of the canal company, so as to authorize the plaintiff to recover compensation for his services under the common counts, upon a quantum meruit; but that in ascertaining the amount which the plaintiff was justly entitled to for his services, the prices fixed upon by the parties themselves in the rescinded contract, ought to be resorted to, and should conclude the parties, so far as the work had been.done in the manner and within the time specified in the contract, and as contemplated by the parties at the time of entering into such special agreement. And where the work was' different from that originally contemplated by the parties, or was done at a later period and under circúmstan6es more unfavorable to the plaintiff than was thus contemplated, he was entitled to recover an extra allowance therefor; in other words, that the terms of the contract were not binding upon the plaintiff, except so far that the prices fixed upon the labor by the parties themselves, were to be considered as the real value of those parts of the work which were done at the time and in the manner originally contemplated by the parties.

Under this decision of the supreme court, which must now be considered the settled law for the regulation of the proceedings before the referees, if I could be fully satisfied that the parties, at the time of their original agreement, contemplated the existence of hard-pan excavation on this section of the canal, and the plaintiff understood that he was to excavate the hard-pan at the rate of nine cents, as fixed upon for common excavation, without receiving any allowance beyond that as extra work, I should think myself bound to vote for a reversal of the judgment of the supreme court, on the ground that the referees had allowed too much. But if the existence of hard-pan excavation was not contemplated by the parties at the time of making their contract, then the price fixed upon by that agreement for common -excavation is no evidence of what the plaintiff is justly entitled to recover for that part of his services or labor ; although the terms of the agreement were broad enough to embrace that kind of excavation, and no provision was made for the payment of any thing beyond the nine cents. The contract being rescinded by the agents of the company, the plaintiff is not bound by the strict letter thereof; and the price fixed by him as the value of common excavation is no evidence of the value of a different kind of work, which [55]*55he never supposed he was to perform at that price. In fact, both parties appear to have treated the hard-pan excavation as extra work from the beginning ; and the engineer allowed an extra compensation therefor. This extra compensation the plaintiff has always insisted was not enough ; and the referees, upon the evidence before them, have decided that such extra allowance-was not sufficient to compensate the plaintiff for his services in this re'spect.

It is insisted, however, by the counsel for the canal company, that by the written contract between the parties, the engineer was to determine the value of all extra work, and that his decision therefore,- as to the'value of the'hard-pan excavation, was conclusive upon the plaintiff. The terms of the contract, as to the powers of the engineer not only to estimate the number of yards of excavation and of embankment, and the value of extra work caused by an alteration of the line of the canal, but also to determine every other question necessary, for the adjustment and final settlement of the contract, are certainly very broad; and as the hard-pan excavation-was probably "a part of the work which the plaintiff was bound to perform under his contract, although -no price was fixed upon by the parties for that kind of labor, I-am inclined to think the decision of the engineer would have been conclusive upon the plaintiff, under this clause of the agreement, had the contract nbt been rescinded^ by the-company, and he had been compelled to bring his suit upon the special agreement. The value of the hard-pan excavation would, in that case; have been one of the questions necessary to be determined before the contract could be finally adjusted- and settled. If so, the decision of the engineer upon that question would-be final and conclusive, by the express stipulation of the parties, unless it could be shown that he had acted in bad faith. The agreement, however, has been rescinded, and is no longer binding upon the palintiff, except so far as the prices he himself has fixed upon as the value of his labor, is evidence against him upon a quantum meruit, and conclusive under the decision of the supreme court upon the preliminary questions. It is very, evident that Dubois never intended to agree that an engineer, to be selected by the canal company, should have the exclusive power of determining what any particular part of his labor was worth, if the company should think proper to rescind their contract without any fault on his parti ' The decision of the engineer, as to the value of the hard-pan excavation, was therefore' no evidence of its real ‘ value upon a quantum meruit; especially when it is taken into consideration that the plaintiff protested against the reasonableness of the'allowance at the time when that decision was made. The question being an open one before the referees, to ' be determined by them as a matter of fact upon the evidence adduced by the respective parties, this court has no authority, upon a writ of error, to inquire into .the correctness of their decision; -although the supreme court had a right to set aside the report, if it was clearly against the weight of evidence, the application to that court being in the nature of a motion for a new trial on the facts of the case, as well as to review the decisions of the referees upon questions of law.

It only remains for me to consider whether the plaititiff -was precluded, by his bill of particulars, from obtaining the full value of his labor, as proved by the testimony, of his witnesses before the referees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spaulding v. Coeur D'Alene Railway & Navigation Co.
51 P. 408 (Idaho Supreme Court, 1897)
Wilkin v. Ellensburgh Water Co.
24 P. 460 (Washington Supreme Court, 1890)
County of Cook v. Sexton
16 Ill. App. 93 (Appellate Court of Illinois, 1885)
Mitchell & Sexton v. Kavanagh
38 Iowa 286 (Supreme Court of Iowa, 1874)
Clark v. Mayor of New-York
3 Barb. 288 (New York Supreme Court, 1848)

Cite This Page — Counsel Stack

Bluebook (online)
15 Wend. 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-hudson-canal-compant-v-dubois-nycterr-1835.