J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority

340 N.E.2d 572, 34 Ill. App. 3d 929, 1975 Ill. App. LEXIS 3429
CourtAppellate Court of Illinois
DecidedDecember 31, 1975
Docket74-134
StatusPublished
Cited by13 cases

This text of 340 N.E.2d 572 (J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority, 340 N.E.2d 572, 34 Ill. App. 3d 929, 1975 Ill. App. LEXIS 3429 (Ill. Ct. App. 1975).

Opinions

Mr. JUSTICE BARRY

delivered the opinion of the court:

Plaintiff-contractor and defendant-project owner were parties to a written agreement, dated May 5, 1972, wherein plaintiff undertook to construct lighting improvements along defendant’s east-west tollway then under construction by other contractors. The amended complaint, with a portion of the contract attached as an exhibit, was filed in two counts. Count I sought a declaratory judgment that plaintiff is entitled to a reasonable extension of time for completion of the contract work; count II sought payment for additional costs incurred in executing the contract work. Plaintiff’s right of relief under both counts was alleged to derive from delays occasioned by defendant’s breach of an implied duty to have prepared construction sites available to plaintiff on or before the starting date of plaintiff’s contract on May 8, 1972, or within a reasonable time thereafter. Both counts alleged that defendant failed in this duty by “negligently scheduling” the necessary preliminary work of other contractors (i.e., for earthwork and grading) so that they would have “the same completion date [i.e., October 1, 1972] as that specified for the completion of the work undertaken by plaintiff.” This “negligent scheduling” was characterized in the pleading as “active interference” by defendant which made the work sites unavailable to plaintiff within the time scheduled by the contract for its performance and occasioned delays which increased plaintiffs costs, and therefore entitled plaintiff to a reasonable extension of time. Both counts were dismissed on defendant’s motion supported by affidavits furnishing contract specifications (by Judge Rink); the circuit court held that the implied duty pleaded in the amended complaint was a conclusion of the pleader negated by the express language of the agreement sued upon. Plaintiff was given leave to file an amendment by adding count III. Thereafter, a default was entered against defendant for failure to respond to count III within the time ordered. Defendant’s motion to vacate the default was denied and the cause proceeded to trial before a different judge, without a jury, under count III for the value of items of “extra work” allegedly furnished under the contract. Defendant appeals from an adverse judgment under count III in the amount of $149,661.93; plaintiff cross appeals from the order dismissing counts I and II.

We consider first, the propriety of the order dismissing counts I and II of the amended complaint. There is substantial authority to support the view that one who contracts to provide labor and materials for a construction project with the reasonable expectation that it will be done within a particular period, and who is thereafter delayed through no fault of his own, but by virtue of the act of the other contracting party, will be entitled to recover for any consequential damages. (Annot. 16 A.L.R.3d 1252 (1967).) But potential loss from delay is inherent in any construction project (McDaniel v. Ashton-Mardian Co., 357 F.2d 511, 517, 16 A.L.R.3d 1243 ( 9th Cir. 1966)), particularly one involving coordinated efforts of multiple contractors. And if from the express provisions of the particular contract, it is apparent that the delay complained of was fully anticipated and provided for, and the right of recovery is expressly limited or precluded (Herlihy Mid-Continent Co. v. Sanitary District, 390 Ill. 160, 60 N.E.2d 882 (1945); Underground Construction Co. v. Sanitary District, 367 Ill. 360, 11 N.E.2d 361 (1937); Ryan Co. v. Sanitary District, 317 Ill.App. 549, 47 N.E.2d 576, affd, 390 Ill. 173, 60 N.E.2d 889 (1945); County of Cook v. Sexton, 16 Ill.App. 93 (1884), affd, 114 Ill. 174, 28 N.E. 608 (1885); see Annot, 91 L.Ed. 48-80 (1946)), or if it is apparent from all the provisions of the agreement that it provides no reasonable basis for the expectation on the part of a complainant that the work could be done by a fixed period (H. E. Crook Co. v. United States, 270 U.S. 4, 70 L.Ed 438, 46 S.Ct. 184 (1926); United States v. Rice, 317 U.S. 61, 87 L.Ed. 53 (1942); United States v. Howard P. Foley Co., 329 U.S. 64, 91 L.Ed. 44, 67 S.Ct. 154 (1946)), then these provisions will control. At Restatement of Contracts §315 (1932), the principle is given:

“(1) Prevention or hindrance by a party to a contract of any occurrence or performance requisite under the contract for the creation or continuance of a right in favor of the other party, or the discharge of a duty by him, is a breach of contract, unless
(a) * * *
(b) the terms of the contract are such that the risk of such prevention or hindrance as occurs has been assumed by the other party.” (Emphasis added.)

In Crook plaintiff-contractor undertook with the government to install heating systems in a foundry building and in a machine shop, both of which were then under construction by different governmental contractors. The facts alleged in the case at bar are similar. In Crook, the completion date specified in plaintiff’s contract was March 19, 1918; the completion dates in the preliminary construction contracts for the foundry building and the machine shop were March 17, 1918, and February 18, 1918, respectively. In the case at bar, plaintiff’s completion date is alleged to have been October 1, 1972, and that of the preliminary work contractors about the same. In Crook, the building contractors fell behind schedule by nearly a year causing delays to plaintiff and additional costs for which suit was brought against the government. There was no suggestion in Crook that the contract had any express provision exonerating the government from losses occasioned by its own delays. There is no such provision in the contract in the case at bar. Nonetheless, in denying recovery to plaintiff in Crook, and in finding that the contract imposed no duty upon the government to have the contemplated structure ready for plaintiff’s work by any fixed time, Mr. Justice Holmes concluded from all its provisions, that the agreement made it clear that the parties contemplated from the beginning that the time fixed for plaintiffs performance was provisional. It is appropriate to observe that where there exists no duty to have the contemplated site ready by a fixed time, there exists no occasion for a clause exonerating the project owner from damages for its delays in that respect.

The agreement in Crook, like the one here, anticipated that plaintifFs progress would depend upon and be affected by the progress of the other contractor’s preliminary work. The agreement there like the one here stated that the government had the right to make changes in the plans and to interrupt the continuity of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

US EX REL. VIRG. BEACH MECH. v. SAMCO Const. Co.
39 F. Supp. 2d 661 (E.D. Virginia, 1999)
J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
642 N.E.2d 1215 (Illinois Supreme Court, 1994)
John Burns Construction Co. v. City of Chicago
601 N.E.2d 1024 (Appellate Court of Illinois, 1992)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Lowry Electric Co. v. State
43 Ill. Ct. Cl. 52 (Court of Claims of Illinois, 1991)
Lippert Brick Contracting v. State
43 Ill. Ct. Cl. 71 (Court of Claims of Illinois, 1991)
K & S Associates, Inc. v. State
43 Ill. Ct. Cl. 117 (Court of Claims of Illinois, 1991)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)
M. A. Lombard & Son Co. v. Public Building Commission
428 N.E.2d 889 (Appellate Court of Illinois, 1981)
Loughman Cabinet Co. v. C. Iber & Sons, Inc.
361 N.E.2d 379 (Appellate Court of Illinois, 1977)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
340 N.E.2d 572, 34 Ill. App. 3d 929, 1975 Ill. App. LEXIS 3429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-f-edwards-construction-co-v-illinois-state-toll-highway-authority-illappct-1975.