Northeast Illinois Regional Commuter Railroad Corp v. Judlau Contracting, Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 20, 2024
Docket1:20-cv-02901
StatusUnknown

This text of Northeast Illinois Regional Commuter Railroad Corp v. Judlau Contracting, Inc. (Northeast Illinois Regional Commuter Railroad Corp v. Judlau Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeast Illinois Regional Commuter Railroad Corp v. Judlau Contracting, Inc., (N.D. Ill. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

NORTHEAST ILLINOIS REGIONAL COMMUTER RAILROAD CORP.,

Plaintiff, Case No. 20-cv-02901

v. Judge Mary M. Rowland

JUDLAU CONTRACTING, INC.,

Defendant.

MEMORANDUM OPINION AND ORDER

Plaintiff Northeast Illinois Regional Commuter Railroad Corp. (“Metra”) awarded a construction project bid to Defendant Judlau. Judlau completed the project more than two years after the contractual completion date, leading to Metra’s suit against Judlau for breach of contract. [49]. Judlau filed a six-count counterclaim alleging breach of contract and violation of the Local Government Prompt Pay Act. [62]. Before the Court now are the parties’ cross-motions for partial summary judgment on issues related solely to damages. [135] [139]. For the reasons stated below, Judlau’s motion for partial summary judgment [135] is granted in part and denied in part. Metra’s motion for partial summary judgment [139] is granted in part and denied in part. SUMMARY JUDGMENT STANDARD Summary judgment is proper where “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). A genuine dispute as to any material fact exists if “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The substantive law controls which facts are

material. Id. After a “properly supported motion for summary judgment is made, the adverse party ‘must set forth specific facts showing that there is a genuine issue for trial.’” Id. at 250 (quoting Fed. R. Civ. P. 56(e)). The Court “consider[s] all of the evidence in the record in the light most favorable to the non-moving party, and [ ] draw[s] all reasonable inferences from that evidence in favor of the party opposing summary judgment.” Logan v. City of Chicago, 4 F.4th

529, 536 (7th Cir. 2021) (quotation omitted). The Court “must refrain from making credibility determinations or weighing evidence.” Viamedia, Inc. v. Comcast Corp., 951 F.3d 429, 467 (7th Cir. 2020) (citing Anderson, 477 U.S. at 255). In ruling on summary judgment, the Court gives the non-moving party “the benefit of reasonable inferences from the evidence, but not speculative inferences in [its] favor.” White v. City of Chicago, 829 F.3d 837, 841 (7th Cir. 2016) (internal citations omitted). “The controlling question is whether a reasonable trier of fact could find in favor of the

non-moving party on the evidence submitted in support of and opposition to the motion for summary judgment.” Id. When cross-motions for summary judgment are filed, the Court construes all facts and draws all reasonable inferences in favor of the party against whom the motion was filed. Indianapolis Airport Auth. v. Travelers Prop. Cas. Co. of Am., 849 F.3d 355, 361 (7th Cir. 2017). The Court treats the motions “separately in determining whether judgment should be entered in accordance with Rule 56.” Marcatante v. City of Chi., 657 F.3d 433, 439 (7th Cir. 2011). See also Kreg Therapeutics, Inc. v. VitalGo, Inc., 919 F.3d 405, 416 (7th Cir. 2019) (“Each cross movant for summary judgment bears

a respective burden to show no issue of material fact with respect to the claim.”). BACKGROUND1 Metra is an Illinois public corporation, overseen by the state Regional Transit Authority, that owns and operates commuter rail service in northeastern Illinois. PRSOF ¶ 2. Judlau is a New York-based contractor in the business of construction projects for private and municipal entities. Id. ¶ 1. On September 28, 2017, Metra

awarded Judlau a contract to demolish, repair, and replace rail line tracks and 11 bridges on the Metra Union Pacific North Line between Addison Street and Balmoral Avenue in the City of Chicago. Id. ¶¶ 3, 5, 6. The formal Notice of Award contained a contract drafted and fully executed by Metra as contract No. K72374 in the amount of $17,235,000.00 for the construction of 11 bridges and related work. Id. The contract required Judlau to complete the project within 30 months of the Notice of Award, on March 28, 2020. Id. ¶10. Metra claims the Project was completed on September 10,

2021. Id. ¶11.The parties agree that substantial completion of the project was delayed by over 500 days. PSRAF ¶ 3.

1 These facts are taken from Defendant Judlau’s Rule 56.1 statements of fact [137] (DSOF) and Plaintiff Metra’s response to Judlau’s statement of facts, [145] (PSROF); Metra’s statements of facts [140] (PSOF) and Judlau’s response to Metra’s statement of facts (DSROF) [148]; Judlau’s statement of additional material facts (DSAF) [148] and Metra’s response to Judlau’s statement of additional facts (PSRAF) [150]. The facts are undisputed unless otherwise noted. Both parties also agree that the delays were caused in part by problems with permits and review processes overseen by the City of Chicago. PSRAF ¶ 3. Judlau sought a 562-day extension on the project that Metra denied. Id. ¶ 16. The parties

dispute who bears overall responsibility for the delayed completion. Id. ¶3. Metra claims every day of delay is attributable to Judlau and that the delays caused Metra to incur damages. DSOF ¶¶ 12-14. Metra now seeks actual damages for costs it incurred while Judlau completed the project. [1]. It is undisputed that due to delay, Metra withheld $692,955.00 as liquidated damages from its payments to Judlau. DSOF ¶¶ 13, 30-31. Judlau,

meanwhile, countersued Metra for delay damages it incurred. [62]. One such delay was Metra’s failure to initiate geotechnical design review with the City’s Office of Underground Construction. Id.; DSAF ¶ 11. In addition to delayed completion damages, Judlau also seeks damages in the form of interest on late payments. Judlau submitted certified payment applications monthly to Metra. PSOF ¶12. Over the course of the project, Judlau made 24 payment applications. PSRAF ¶ 32. Pursuant to the contract, Metra paid Judlau funds

awarded by the Illinois Department of Transportation (IDOT) and the Federal Transit Administration (FTA). PSOF ¶¶ 14-15. The parties dispute whether Metra made timely payments under the contract and/or the Local Government Prompt Payment Act, 50 ILCS § 505. DSROF ¶ 14. ANALYSIS I. Judlau’s Motion for Partial Summary Judgment on Liquidated Damages Judlau moves for partial summary judgment regarding the amount of damages that Metra can recover. Judlau disputes liability, but in the event it is found in breach, it asserts that the liquidated damages provision in the contract caps Metra’s

recovery of damages for delay at a per diem rate. a. Liquidated Damages Clauses are Enforceable Section 4.9 of the contract states: LIQUIDATED DAMAGES. Time is of the essence of this Contract. Should the Contractor neglect, refuse, or fail to complete the work under this Contract within the time agreed upon, and in view of the difficulty of estimating with exactness damages caused by such delay, Metra shall have the right to charge the Contractor the sum of $1,305.00 per day for each and every calendar day that such work under this contract is delayed in its completion beyond the specified time, as liquidated damages and not a penalty.

[62-1] at 11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Unicon Management Corp. v. City of Chicago
404 F.2d 627 (Seventh Circuit, 1968)
Marcatante v. City of Chicago
657 F.3d 433 (Seventh Circuit, 2011)
Northern Illinois Gas Co. v. Energy Cooperative, Inc.
461 N.E.2d 1049 (Appellate Court of Illinois, 1984)
Siegel v. Levy Organization Development Co.
538 N.E.2d 715 (Appellate Court of Illinois, 1989)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)
J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
642 N.E.2d 1215 (Illinois Supreme Court, 1994)
Contracting & Material Co. v. City of Chicago
314 N.E.2d 598 (Appellate Court of Illinois, 1974)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
Calumet Construction Corp. v. Metropolitan Sanitary District
533 N.E.2d 453 (Appellate Court of Illinois, 1988)
Air Safety, Inc. v. Teachers Realty Corp.
706 N.E.2d 882 (Illinois Supreme Court, 1999)
Wright v. Chicago Title Insurance Co.
554 N.E.2d 511 (Appellate Court of Illinois, 1990)
Eichengreen v. Rollins, Inc.
757 N.E.2d 952 (Appellate Court of Illinois, 2001)
Gust K. Newberg, Inc. v. Illinois State Toll Highway Authority
506 N.E.2d 658 (Appellate Court of Illinois, 1987)
Bates & Rogers Construction Corp. v. Greeley & Hansen
486 N.E.2d 902 (Illinois Supreme Court, 1985)
Morris v. Flores
528 N.E.2d 1013 (Appellate Court of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Northeast Illinois Regional Commuter Railroad Corp v. Judlau Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeast-illinois-regional-commuter-railroad-corp-v-judlau-contracting-ilnd-2024.