Sexton v. County of Cook

28 N.E. 608, 114 Ill. 174
CourtIllinois Supreme Court
DecidedMay 15, 1885
StatusPublished
Cited by11 cases

This text of 28 N.E. 608 (Sexton v. County of Cook) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sexton v. County of Cook, 28 N.E. 608, 114 Ill. 174 (Ill. 1885).

Opinion

Mr. Justice Sheldon

delivered the opinion of the Court:

The errors assigned are, the refusing of an instruction asked by the plaintiff, and the giving of two asked by the defendant. The refused instruction asked by plaintiff was:

“If the jury believe, from the evidence in reference to the dome contract, that the board of county commissioners of Cook county passed a resolution authorizing and instructing P. J. Sexton to build as much of the foundation of the dome, under the supervision of the architect, as is necessary to inclose the building, subject to the architect’s valuation of the same, and the jury further believe that one of the walls of the foundation of said dome formed also a portion of the west wall of the court house, and said building could not be inclosed without running up said wall, and that thereafter the plaintiff took said order to James J. Egan, the architect of the court house, and said architect in one order fixed the prices of said work, and in another order defined the manner of construction of said dome, and the extent and limits thereof, and the said Sexton thereupon proceeded and did a portion of the work, and- was stopped by the defendant, and on his part was prepared and ready and willing to do all of said work, then Sexton is entitled to recover the value of the work done under the contract, and the value of the contract for work not done,— or, in other words, he is entitled to the value of the work which he has done, and the profits on the work which remained to he-o done and toas not done.”

So much of the instruction as is printed in italics the court-struck out, and gave the residue of the instruction to the jury.. The two instructions given for the defendant were:

“That the resolution of the county board of Cook county adopted July 30, 1877, only authorized the building by Sexton of as much of the foundation of the dome as was necessary to inclose the building, and if the jury believe, from the evidence, that the foundation of the dome did not extend above the level of the basement floor of the court house, then such resolution, when acted upon by Sexton, did not constitute a contract between him and the county of Cook for the building of such dome above such foundations, nor above the level of such basement floor, and the architect, under such resolution, had no power or authority, by virtue of such resolution, to-make a valuation of work done by Sexton above such foundation, and bind the county of Cook thereby.
“That notwithstanding the resolution of the county board adopted July 30, 1877, requesting Sexton to build as much of the foundation of the dome, under the supervision of the architect, as was necessary to inclose the building, subject to-the architect’s valuation of the same, the county board had a right to direct that work on the dome above the foundation be stopped or suspended, and by so doing incur no liability to Sexton for profits on work not done, and the jury will reject all claim in this case for profits on work not done on said dome above the foundation thereof. ”

In the language of appellant’s brief herein, “the design was to erect, upon the public square in the city of Chicago, a joint building, one-half to be erected by the county, and to be used for county purposes, and the other half by the city,' and for city purposes, and the intention was that each building should be complete in itself, and that the two buildings should be connected together by an octagonal dome, which, commencing at the ground, should run up about three hundred and sixty-six feet. This dome was so designed that a portion of the east wall of it should constitute (a portion of) the west wall of the court house, and a portion of the west wall should constitute (a portion of) the east wall of the city building. A space of about forty-four feet was left in the building, to be occupied by this dome wall, and when the dome should be erected, it (with the other work contracted to be done) would constitute the entire four walls of the county part of the building. ”

The resolution of the county board, of July 30, 1877, when accepted by Sexton, constituted a contract for the building of a portion of the foundation of the dome, and we are of opinion that was all the contract that existed between the county and Sexton upon the subject. It is the county board, only, which has authority, by law, to bind the county by a contract. There is no such power in an architect, or a committee, unless it has been bestowed by the county board. We find no such power to have been given here. “The authorized body of a municipal corporation may, * * * by a resolution or vote, clothe its officers, agents or committees with power to act for it.”' (Dillon on Mun. Corp. sec. 450.) And see Rice v. Plymouth County, 43 Iowa, 136; Bouton v. McDonough County, 84 Ill. 384. The architect had authority, under the resolution, only to supervise the work it directed to be done,—not to order the doing of any other work. The architect’s orders of October 27 and November 3 were for work which was outside of the terms of the resolution of July 30, and were not binding upon the county. That resolution, a.t the most, only authorized work which was necessary “to inclose the building. ” These orders directed work to be done on the entire county half of the 'dome,—the four sides of the octagon,—the resolution having reference to no more than work on one side of it.

So far, then, as regards prospective profits on work not done, under an alleged contract with the county, we are to look to the resolution of July 30, to see what the contract was. The direction under that resolution was, to build a portion of the foundation of the dome. Under the evidence in the case we think the court was justified in finding that the word “foundation, ” as used in the resolution, meant the part below the ground. It is objected to this that both parties, by their conduct, gave the contract a different construction. The acts of the architect, and of the joint committee on public buildings and public service, were their individual acts, and are not to be regarded as the acts of the county board. The county board appear to have begun with a contract for the foundation. Subsequently, Sexton was ordered by the joint committee to fill in the wall up to the main water-table, or level of the first story floor. This order was not binding upon the county, but the work was done and paid for. This does not necessarily imply any more than that the work having been done for the county, it was willing to pay for the same. And so of the subsequent direction to complete the work as far as the roof line of the building, .so far as payment was made for that work.

As the resolution uses the language, “as much of the foundation of the dome as is necessary to inclose the building, ” it is urged that the use of the italicized words shows an intention on the part of the county board to provide, by that resolution, for the closing up of the entire gap in the west wall of the building to the roof line. Defendant’s view and explanation of that language is this : That the dome had not been determined upon when the resolution of July 30 was passed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hope, Inc. v. County of DuPage
717 F.2d 1061 (Seventh Circuit, 1983)
Robert W. Hadley v. County of Du Page
715 F.2d 1238 (Seventh Circuit, 1983)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)
County of Stephenson v. Bradley, Inc.
275 N.E.2d 675 (Appellate Court of Illinois, 1971)
Consolidated Chemical Laboratories, Inc. v. County of Cass
53 N.E.2d 738 (Appellate Court of Illinois, 1944)
Pauly v. County of Madison
123 N.E. 281 (Illinois Supreme Court, 1919)
City of Chicago v. McKechney
205 Ill. 372 (Illinois Supreme Court, 1903)
Fullerton Lumber Co. v. Gates
89 Mo. App. 201 (Missouri Court of Appeals, 1901)
County of Crawford v. Walter
89 Ill. App. 7 (Appellate Court of Illinois, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
28 N.E. 608, 114 Ill. 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sexton-v-county-of-cook-ill-1885.