City of Chicago v. McKechney

205 Ill. 372
CourtIllinois Supreme Court
DecidedOctober 26, 1903
StatusPublished
Cited by24 cases

This text of 205 Ill. 372 (City of Chicago v. McKechney) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chicago v. McKechney, 205 Ill. 372 (Ill. 1903).

Opinions

Mr. Justice Magruder

delivered the following opinion:

The contractors, Weir, McKechney & Co., began work under the contract of October 19, 1895, in December of that year. They first sank a shaft at Keith street, northwest of the south-east end of section 3. Their next work was to sink a shaft at Potomac avenue north-west from the Keith street shaft. After sinking these shafts they began to excavate for the tunnel both ways from the two shafts. They continued the work until August 1, 1896, and then stopped work. From the time they began their work in December, 1895, until they ceased working in July, 1896, the city paid them $39,574.81. These payments were made in various sums, all the payments except the first two being made at the rate of two per month upon certified estimates, signed by the proper city officials. Upon these estimates are endorsed written receipts for the amounts so paid to them, signed by Weir, McKechney & Co., amounting altogether to the total sum above named.

When the contractors, Weir, McKechney & Co., ceased work on August 1, 1896, they at once began a suit against the city. This suit grew out of differences of opinion between the city and the contractors as to the proper construction of certain provisions of the contract of October 19, 1895. This suit was begun in the circuit court of Cook county, and resulted in a judgment in favor of the plaintiffs therein on September 14, 1896. An appeal was taken from such judgment to the Appellate Court, and on December 31,1896, the Appellate Court entered a judgment. (Weir v. City of Chicago, 67 Ill. App. 247). An appeal was taken from the judgment of the Appellate Court to this court, and the decision of this court, embodied in an opinion'filed on March 12, 1897, is reported as City of Chicago v. Weir, 165 Ill. 582. During the pendency of this litigation from August, 1896, to the final termination thereof on March 12, 1897, very little work was done by the contractors in the construction of the tunnel; but they resumed work on November 14, 1896, in view of a threat by the commissioner of public works to cancel the contract,, and, during this period, six payments were made to them, two in December, 1896, three in February, 1897, and one on March 1, 1897, amounting altogether to $12,591.40. Substantially all of the payments thus made to the contractors during the period between August, 1896, and March, 1897, were receipted for under protest.

Work was resumed in March, 1897, and between March 20,1897, and December 1, 1897, and including those dates, the city paid to the contractors, Weir, McKechney & Co., the sum of §283,094.86 upon certified estimates. The said sum of §283,094.86 was paid out to Weir, McKechney & Co. in various amounts, the payments being made twice in each month during that period; and sometimes three payments were made in one month. Upon the certified estimates are endorsed written receipts, signed by Weir, McKechney & Co., for the amounts of such payments.

At this point, and on December 8,1897, the contractors began this present suit against the city. Before proceeding to state the substance of the pleadings in the present action, it may be remarked that the contractors proceeded with the work of construction, and the city continued to make payments to the contractors, such payments being for the most part semi-monthly payments, until about the 21st of April, 1898, when the contractors again abandoned their work upon the tunnel. They did not resume work until about July 11,1898, at the time of the proceedings by the common council of Chicago, set forth in the statement preceding this opinion. About July 11, 1898, work was again resumed and continued with more or less regularity until November 11, 1898, when the contractors abandoned the work altogether, and never have since resumed it. The work of constructing" the tunnel was unfinished on November 11, 1898, when the contractors finally abandoned it. Between the time when this suit was begun, and November 11, 1898, when the work was finally abandoned, the city paid to the contractors various sums of money, amounting altogether to the sum of §283,455.59. The payments, constituting this total amount, were made between December 16, 1897, and November 1, 1898, including those dates, upon certified estimates, and for the most part at the rate of two payments in each month. These payments were duly receipted for without protest by the contractors, in writing, endorsed upon the estimates. The total amount paid to the contractors by the city between December 31,1895, about the time when the construction of the tunnel began, and November 11, 1898, ,when the same was abandoned, was the sum of $618,-716.66. This sum, and the judgment rendered in this case for $555,560.22, amount to $1,174,276.88.

Besides the suit begun in August, 1896, and the present suit begun on December 8, 1897, the contractors during the progress of the work brought at least three injunction suits against the city. The first injunction suit was brought by them against the city in March, 1898. In the beginning of that month the city engineer gave-the contractors a written direction to raise the grade in certain drifts, and, although the specifications provided that the tunnel should be built on such grades as should be determined by the city engineer, they refused to obey the order, and procured an injunction from the Superior Court of Cook county restraining the city from enforcing the order. This injunction was subsequently dissolved. The second injunction suit, brought by the contractors against the city, was commenced on April 30, 1898. At that time the city engineer wrote a letter to the contractors, ordering them to brick up certain portions of the excavation in certain drifts of the tunnel, there being danger at those points that the tunnel would cave in. This order was not complied with, but the contractors obtained an injunction against the city from interfering with the work. This injunction was in force when the Council proceedings of July 11, 1898, were had. At the time of the last suspension of the work on or about November 11,1898, the contractors filed a third bill for an injunction against the city. By this third bill they sought to prevent the city, through an injunction, from seizing the tunnel and machinery and forfeiting the contract. This last injunction was finally dissolved on June 16, 1899, one week before the beginning of the trial of this case; and on June 23, 1899, the day on which the trial began, the commissioner of public works served upon the contractors the notice of forfeiture of the contract of October 19, 1895, as the same is set forth in the statement preceding this opinion.

First—The pleadings. In order to understand the present case, and the various points involved in the record, ■it will be necessary to state somewhat in full the very extraordinary condition of the pleadings in the case.

When the suit was brought on December 8, 1897, the ad damnum was laid at $68,000.00. On January 7, 1898, a declaration was filed. On March 5, 1898, a demurrer was filed to this declaration, and, after argument, was overruled, and the plaintiffs were given leave to increase the ad damnum to $125,000.00. On November 28,1898, the plaintiffs were granted leave to amend their declaration instanter by increasing the ad damnum to the sum of $650,000.00, and to file their bill of particulars instanter, which they did. The sum total of the bill of particulars, so filed on November 28, 1898, is $620,833.18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Agents Insurance Co. of America, Inc. v. Midwest Sporting Goods Co.
812 N.E.2d 620 (Appellate Court of Illinois, 2004)
Kirkpatrick v. UNITED FED. OF PCB ASS'N
202 N.E.2d 136 (Appellate Court of Illinois, 1964)
Gillock v. Holdaway
41 N.E.2d 504 (Illinois Supreme Court, 1942)
Home Life Insurance v. Franklin
24 N.E.2d 874 (Appellate Court of Illinois, 1940)
Anderson v. Mitchell
253 Ill. App. 509 (Appellate Court of Illinois, 1929)
Koban v. Gordon Supply Co.
253 Ill. App. 569 (Appellate Court of Illinois, 1929)
Anglo-California Trust Co. v. Essanay Film Manufacturing Co.
155 N.E. 26 (Illinois Supreme Court, 1926)
Morse v. City of Boston
148 N.E. 813 (Massachusetts Supreme Judicial Court, 1925)
George J. Cooke Co. v. Miller Brewing Co.
146 N.E. 459 (Illinois Supreme Court, 1925)
Seevers v. Cleveland Coal Co.
138 N.W. 793 (Supreme Court of Iowa, 1912)
McKechney v. City of Chicago
160 Ill. App. 544 (Appellate Court of Illinois, 1911)
Lecklieder v. Chicago City Railway Co.
142 Ill. App. 139 (Appellate Court of Illinois, 1908)
Schwarzschild & Sulzberger Co. v. Pfaelzer
133 Ill. App. 346 (Appellate Court of Illinois, 1907)
Chicago City Railway Co. v. McDonough
125 Ill. App. 223 (Appellate Court of Illinois, 1905)
City of Chicago v. Duffy
117 Ill. App. 261 (Appellate Court of Illinois, 1904)
Chicago City Railway Co. v. Enroth
113 Ill. App. 285 (Appellate Court of Illinois, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
205 Ill. 372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chicago-v-mckechney-ill-1903.