Tennesse & Coosa Railroad v. Armstrong

112 Ala. 80
CourtSupreme Court of Alabama
DecidedNovember 15, 1895
StatusPublished
Cited by19 cases

This text of 112 Ala. 80 (Tennesse & Coosa Railroad v. Armstrong) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennesse & Coosa Railroad v. Armstrong, 112 Ala. 80 (Ala. 1895).

Opinion

McCLELLAN, J.

This cause has been twice before in this court on appeals by the present appellant, the Tennessee & Coosa Railroad Co.— (93 Ala. 614 and 99 Ala. 331). We shall adhere to the opinions -delivered on these former appeals in respect of those of the questions, now again presented, which were then considered.

On the first appeal, it was held, among other things, that where, under a contract for work and labor and materials, the work and labor has been done and performed in part and materials have been in part supplied, and after this the party obligated thereto has been prevented by the other party from doing and performing the remaining work and labor and furnishing the remaining stipulated material, he may in one and the same action sue upon the contract for the compensation provided for therein for his labor and material performed and furnished under it, and also for the profits he would have realized from a full performance and discharge of his undertaking had he not been prevented from such full performance and discharge by the other party. — 93 Ala. 621. And we do not understand the correctness of this proposition to be seriously controverted as it is here reproduced from the former opinion. But it is.said for appellant that when, as was the fact here, the plaintiff claims in his original complaint under the contract, and only an amount due for work and labor and materials performed and supplied according to its [89]*89terms, the only breach of the contract imputed to the defendant being his failure to pay for these items according to its stipulations, lie cannot afterwards by amendment present another claim for profits which he would have realized for work and labor and material which the defendant wrongfully prevented him from performing and furnishing, because this would be to introduce a new cause of action by amendment which is not allowable. Now this is precisely the form this question assumed when the case was first here : the point was made in precisely this way — an objection to the addition to the original counts, for money due under the contract as performed in part, of a count for profits plaintiffs were prevented from making by not being allowed to fully perform the contract. So that, while what is said in the opinion would not necessarily cover the question, yet when regard is'had to the record in that case it is clear that the contention now made by the appellant in this connection was there presented, and fully determined in favor of the appellees.

But beyond all this, the present 'record furnishes no basis for this contention : it does not arise, the point is not made so as,to authorize us to pass upon it on the present appeal. It is a question of pleading, and for the decision of the court, not of fact for the jury. It should have been presented to the court in some appropriate way, by objection to the allowance of the amendment whereby the claim for profits was injected into the case, or, the amendment having been allowed, by a motion to strike out the new counts. This record shows no such objection or motion, nor any ruling by the court in settling the pleadings having any bearing on this matter. The defendant pleaded to all the counts, the general issue and several special pleas ; and upon the-issues thus made the case was tried and submitted to the jury. On this state of the record, if the plaintiffs proved the averments of each count of the complaint, assuming the counts to have been good in and of themselves severally, and the defendant failed to make good its special defenses, plaintiffs were entitled to a verdict upon each .count, or to a general verdict, wholly regardless of a misjoindér of counts, or of the fact that the original counts went upon the contract treating it as continuing, and the counts added by the amendment treated the contract as [90]*90having been brought to an end by the defendant, and claimed damages for not being allowed to fully perform and discharge it. So that both upon the former decision and on the case as now presented, apart from that decision, our conclusion is that the court properly refused the several charges requested by the defendant which proceeded on the idea that a recovery could not be had both on the original and added counts because the latter were inconsistent with, or. constituted a departure from, or, for any reason, were improperly j oined to the former.

The testimony of 0’Hearn and Ludwig to which defendant objected went to show the cost of doing certain classes of the work contracted for at one point on this line of-road, which was about sixty-six miles in length. These classes of work, the excavation and removal of earth, loose or broken rock and solid rock, were common to the whole line ; and the elements which went to make up the cost of the excavations were, in the main, the same along the whole line, leaving out of consideration in this connection the solid rock excavations contemplated to be done at Fort Deposit Bluff. There was some difference in the character of soil to be excavated at different places, being of a sandy and gravelly kind where 0’Hearn had worked, red clay on another part of the road, and “white sticky” earth on another. It is contended in the briefs of appellant’s counsel (and said arguendo in the abstract) that the cost of excavating sandy soil is something less than that of excavating red and white clay; but we do not find this borne out by the evidence. To the contrary all of the witnesses for the defendant, except one, puts the cost of earth excavation on division A of the road, where O’Hearn worked in sandy soil, the same as on division B, where there was red and white clay; and the one witness who makes a difference — McDonald, the engineer of the railway company which appears to have succeeded to the defendant’s rights and liabilities in the premises— testifies that the cost of earth excavation is slightly greater on division A than on division B. And it is not contended that the cost of rock excavations, leaving out said bluff, was greater on other sections than it was where O’TIearn worked. It would seem to be clear, therefore, that all this testimony of O’Hearn and Ludwig as to the cost of the excavations made by the former [91]*91was relevant and pertinent to the inquiry as to tlie cost of tliis work per cubic yard all along the road, and afforded, fairly and justly, bases for inferences to be drawn by the jury as to the cost of the work which plaintiffs had contracted to perform. And the cost of doing the work was a necessary factor in estimating the profits which plaintiffs would have made had they been allowed to carry out the contract. If we assume plaintiffs were to perform the contract themselves directly and not-through sub-contractors, such cost and the contract price to be paid plaintiffs were the two main factors in the estimate to be made by the jury. This we no not understand to be controverted; but appellant’s counsel insist that inasmuch as it is made to appear in the ease that plaintiffs had no intention of doing the work except through sub-contractors and had made arrangements only to that end, their profits would bear no necessaiy relation to the difference between the cost and the contract price of.the work, but would be entirely represented by the difference between the prices fixed in the sub-contracts and those fixed in the contract in chief, and hence, it is insisted, evidence of cost is not pertinent. We may grant this proposition in the main without concurring in the conclusion just stated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whiting v. Dodd
94 So. 2d 411 (Alabama Court of Appeals, 1957)
Selman v. Bryant
72 So. 2d 704 (Supreme Court of Alabama, 1954)
Malone v. Reynolds
105 So. 891 (Supreme Court of Alabama, 1925)
Obear-Nester Glass Co. v. Mobile Drug Co.
95 So. 13 (Supreme Court of Alabama, 1922)
Ballenger v. Ballenger
88 So. 826 (Supreme Court of Alabama, 1921)
Pappenburg v. State
65 So. 418 (Alabama Court of Appeals, 1914)
Alabama City G. & A. Ry. Co. v. Appleton
54 So. 638 (Supreme Court of Alabama, 1911)
Byrd v. Hickman
52 So. 426 (Supreme Court of Alabama, 1910)
Atlas Coal Co. v. O'Rear
50 So. 63 (Supreme Court of Alabama, 1909)
Tutwiler v. Burns
49 So. 455 (Supreme Court of Alabama, 1909)
Fitzpatrick Square Bale Ginning Co. v. McLaney
44 So. 1023 (Supreme Court of Alabama, 1907)
Andrews v. Frierson
39 So. 512 (Supreme Court of Alabama, 1905)
Barker & Stewart Lumber Co. v. Edward Hines Lumber Co.
137 F. 300 (U.S. Circuit Court for the District of Western Wisconsin, 1905)
Chase v. Smith
77 P. 1069 (Washington Supreme Court, 1904)
Pollard v. American Freehold Land Mortgage Co. of London
139 Ala. 183 (Supreme Court of Alabama, 1903)
City of Chicago v. McKechney
205 Ill. 372 (Illinois Supreme Court, 1903)
Lawrence v. Bell
31 So. 503 (Supreme Court of Alabama, 1902)
State v. Lake St. Clair Fishing & Shooting Club
87 N.W. 117 (Michigan Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
112 Ala. 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennesse-coosa-railroad-v-armstrong-ala-1895.