Barker & Stewart Lumber Co. v. Edward Hines Lumber Co.

137 F. 300, 1905 U.S. App. LEXIS 5224
CourtU.S. Circuit Court for the District of Western Wisconsin
DecidedMarch 13, 1905
DocketNo. 102
StatusPublished
Cited by1 cases

This text of 137 F. 300 (Barker & Stewart Lumber Co. v. Edward Hines Lumber Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Western Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barker & Stewart Lumber Co. v. Edward Hines Lumber Co., 137 F. 300, 1905 U.S. App. LEXIS 5224 (circtwdwi 1905).

Opinion

SANBORN, District Judge.

The defendant at the close of the. plaintiff’s testimony moves to strike out all evidence relating to profits claimed by plaintiff, and further to exclude all evidence given on behalf of the plaintiff, and to direct a verdict in favor of the defendant, as to the first cause of action.

The most important question relates to the construction of the contracts made between the defendant and the assignors of the plaintiff, a copartnership known as Barker & Stewart. The claim of the plaintiff is for damages based upon the act of the defendant in withdrawing from the contract between the parties certain timber known as the Bigelow timber, and some 7,000,000 additional known as the Hines Lumber Company timber, and sawing it at the defendant’s mill. It is claimed by the plaintiff that this timber was brought within the contract by the last written agreement made between them, while the defendant claims that it had the option under that agreement to so withdraw such timber.

On June 14, 1898, a contract was made between Weyerhaeuser & Rutledge and the defendant, providing that Weyerhaeuser & Rutledge would, from lands owned by them in townships 48 and 49, ranges 7 and 8 west, cut into saw logs all the merchantable pine on such lands, estimated at 187,000,000 feet, and would deliver said logs to the Hines Company at certain booms on Chequamegon Bay. Such logs were to be delivered in quantities of not less than 20,000,000 feet or more than 40,000,000 feet annually until all such timber was delivered.. The defendant company was to give notice in writing to Weyerhaeuser & Rutledge prior to November 1st each year óf the amount it desired to have delivered during the ensuing year. Such notices requiring the delivery of the full amount of 40,000,000 feet' have been given for each year, including the year 1905. Deliveries of logs under this contract were to begin after January 1/1899, so as to permit the manufacture of the logs by March 1, 1899, and Weyerhaeuser & Rutledge agreed to make annual deliveries thereafter until all the logs were cut. The defendant company was to accept all such logs, and pay for the same within 90 days after the end of the month of delivery. On the 19th day of June, 1900, and in each year thereafter during the existence of the contract, defendant was to pay Weyerhaeuser & Rutledge interest from June 14, 1899, on the stumpage value of the logs delivered during the preceding year, but on June 14th in each year there was to be credited to the defendant company interest on all cash payments made by it for logs received during the preceding year. After further provision in respect to a contract made by Weyerhaeuser & Rutledge with the Standard Construction Company for the cutting of the logs, the lands are described upon which the logs are situated, and certain other agreements were made, not material to this controversy.

On October 6, 1898, the first contract between Barker & Stewart and the defendant company was made. It recites that the defendant has made the-Weyerhaeuser & Rutledge contract, and in general its provisions, and that the Hines Company was desirous [302]*302of having said logs manufactured into lumber at or near the point of delivery, and Barker & Stewart desired to secure a contract to manufacture a portion of said logs into lumber, and were familiar with- the terms of the Weyerhaeuser & Rutledge contract. It was therefore agreed that Barker & Stewart should prior to March 1, 1899, build, erect, and fully equip a sawmill capable of sawing at least 35,000,000 feet of lumber during each sawing season, working both night and day, and that they would build the mill and have it ready to commence manufacture on or before March 1, 1899. It was further agreed by Barker & Stewart that between March 1st and December 1st of each year thereafter, until all the said logs were mánufactured into lumber, they would at their sawmill manufacture into merchantable lumber, in a proper manner, not less than 25,000,000 or more than 35,000,000 feet of the Weyerhaeuser & Rutledge logs. The quantity to be manufactured each year, within the limits so specified, was to be fixed by the defendant company giving notice in writing to Barker & Stewart on or before November 1st each year of the quantity which it desired to have manufactured into lumber during the next sawing season. Such notices have been given for each year at the full amount of 35,000,-000. Barker & Stewart further agreed to continue the manufacture at the full capacity of the mill until the close of the sawing season each year, and manufacture all logs delivered to them by defendant within the specified limits, and would not manufacture for others at any time when there were sufficient of defendant’s logs available to keep the mill running to its full capacity for a week unless the defendant should, in writing, consent thereto. It was further provided' that the lumber should be sorted and piled into 35 sorts or piles. They further agreed to manufacture lath which would grade No. 1. Various other provisions are contained for the manufacture, sorting, and piling of the lumber. Barker & Stewart further agreed to accept all the logs so to be manufactured as delivered by Weyerhaeuser & Rutledge, and such delivery should be considered a complete delivery under the contract of October 6, 1898. Defendant, on its part, agreed to deliver such logs up to the amount to be manufactured in each year. Then comes the following provision:

“But it Is understood that if under the said contract of June 14, 1898, or by other agreement with the said Weyerhaeuser and Rutledge the said second party [Hines Lumber Company! shall have more than 35,000,000 feet, board measure, of logs covered by said contract of June 14, 1898, cut and delivered as aforesaid in any one or more years, then the second party shall have the right to have such excess manufactured at mill selected by it other than the one owned by the first party [Barker & Stewart].”

Defendant should only be required to deliver to Barker & Stewart such logs as were delivered by Weyerhaeuser & Rutledge under their said contract, and no damage was to accrue to or be recovered by Barker & Stewart on account of nondelivery of logs for any reason specifically mentioned in the Weyerhaeuser & Rutledge contract, or because of the nonperformance of that contract for any other reason not the fault of the defendant. Barker'& Stewart were to [303]*303receive for sawing $1.85 per thousand for lumber, and 85 cents for lath. It is further provided that, if the mill should be accidentally destroyed by fire or otherwise, Barker & Stewart will rebuild_ within 90 days after such destruction, and will then proceed with the performance of the contract. No damage was to accrue to defendant for the suspension of operations during the 90 days, provided it should have the right, if it so desired, to have logs delivered under the Weyerhaeuser & Rutledge contract manufactured during said period at some other convenient mill in the vicinity; Barker & Stewart to pay any excess over the contract price for such manufacture. If Barker & Stewart should default in the performance of the contract, defendant might stop further manufacture, and cause the Weyerhaeuser & Rutledge logs to be manufactured _ at other mills, and Barker & Stewart were to pay any damages which defendant might thereby suffer. Provision was made for the assignment of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Bankers Life Co.
283 Ill. App. 77 (Appellate Court of Illinois, 1935)