Lowry Electric Co. v. State

43 Ill. Ct. Cl. 52, 1991 Ill. Ct. Cl. LEXIS 60
CourtCourt of Claims of Illinois
DecidedMay 30, 1991
DocketNo. 83-CC-0324
StatusPublished
Cited by1 cases

This text of 43 Ill. Ct. Cl. 52 (Lowry Electric Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lowry Electric Co. v. State, 43 Ill. Ct. Cl. 52, 1991 Ill. Ct. Cl. LEXIS 60 (Ill. Super. Ct. 1991).

Opinion

OPINION

Montana, C.J.

The Claimant, Lowry Electric Company, brought this claim seeking $122,487.31 in damages due to delays and other problems Claimant encountered in the performance of a construction contract with the Respondent’s Capital Development Board (hereinafter referred to as “CDB”). The cause was consolidated for trial purposes only with claims of Guarantee Electrical Company, Lippert Brick Contracting, and K & S Associates, Inc.

The facts of the case are sufficiently set out in separate opinions of this Court relating to the claims of the joined Claimants so that only those facts necessary to decide this claim will be stated herein.

On July 18, 1978, the CDB awarded a contract for electrical work to Claimant, Lowry Electric Company, for work on the Skilled Training Center of the East St. Louis Community College project. Claimant received its notice to proceed from the CDB on August 30, 1978. Lowry had 550 days from August 30, 1978, to complete its work. Time was of the essence according to the contract documents. Claimant was to be off the project by February 4,1980.

The project did not get off the ground for over a year from August of 1978 due to the inability of the State to get the excavating work done. Initially the excavator chosen by the CDB, Fanes Excavating, was unable to obtain a bond. Later, the CDB change ordered Fanes to work for K & S, the general contractor. Fanes was unable to do the work and eventually was terminated. The successor excavator also had problems. Over a year was wasted on an excavating contractor.

The CDB had the obligation to see that the site was excavated. It failed miserably. Of course, other problems plagued the project beyond the initial excavation problems. Once the project got off schedule, the architect/engineer and the general contractor, K & S, were incapable of getting the project back in sync. The roofing delayed the project. The CDB had five different project managers which delayed the project. Co-Mac, the concrete company, delayed the project. Incredibly poor coordination delayed the project, and theft delayed the project. The evidence is clear, however, that Lowry Electric caused no delays on this project. As electricians, they were at the mercy of the other trades. The CDB at one time gave Lowry two sets of drawings that cancelled each other out. On other occasions, Claimant could not work because other trades were working in the area and at other times, it would do their work and another tirade would move it, requiring the Claimant to do the work over. All of this was because of a lack of coordination initially caused by the project losing a year due to no excavation.

Because of the delays, Lowry did not receive its final acceptance from CDB until March 3, 1982. Claimant was paid its contract price of $237,860.00 but because of these delays, Claimant testified it experienced increased labor and material costs. Additionally, because of the delays and coordination problems, Lowry had to expend additional man-hours to complete its work over and above the man-hour estimations included in its bid. Lowry claims an additional 9426 hours expended because of delays.

Lowry’s Exhibit No. 1 is the owner contractor agreement. Exhibit No. 2 is the authorization to proceed dated August 30, 1978, by the CDB. Exhibit No. 3 is a copy of the IBEW Local 309 electrician rates September 1,1978, to August 31,1979; March 15,1978, to August 31, 1978; September 1, 1979, to February 28, 1980; March 1, 1980, to August 31, 1980; September 1, 1980, to December 31,1980; and September 1,1981, to February 28, 1982. Lowry’s Exhibit No. 4 documents Lowry’s alleged material increases. Exhibit 4A is the statement of monthly electrician hours expended; Exhibit 4B is a recap of the additional costs incurred by Lowry Electric Company. Exhibit No. 5 is a letter from Claimant to CDB reserving its rights to its delay claim. Exhibit No. 6 is the CDB’s letter to Claimant stating it does not have funds to pay the delay claim. Exhibit No. 7 is the CDB’s certificate of final acceptance to Claimant dated March 3, 1982. Exhibit 3 indicates the labor cost increases to Claimant by its union electricians. The labor rate of $17.58 per hour for journeymen plus $18.25 per hour for foremen effective on September 1, 1978, at the start of the job increased to $20.99 per hour for journeymen on September, 1980, through December 3, 1980, and the rate for foremen went to $23.69 per hour for September I, 1980, through February 28, 1982. The additional increases are documented.

As to the material, the contract specifications required Lowry to purchase the material at the time the bid was accepted. Claimant did not purchase all of its material at the time of bid acceptance. Claimant indicates it did not order the material at the time of bid acceptance because lengths of conduit were not ordered until the lengths were known.

Claimant’s contract was with the CDB. The CDB has the primary responsibility for making the work site available to the contractor in time for the contractor to do the work. As owner, the CDB is legally liable for the delays and resulting damages. The fact that the CDB reportedly contracted with other entities who may be to blame for delay is of no consequence to this action. If the CDB is damaged by the actions of others, it may pursue those it believes caused the damage under the circumstances as are involved here. Where all of the parties cannot sue each other in one forum, the Court of Claims is the proper forum and this result must obtain. J. F. Inc. v. S.M. Wilson and Co. (1987), 152 Ill. App. 3d 873.

It is inevitable that all construction projects will suffer delays of one form or another, particularly projects calling for coordinated efforts by multiple contractors. In the instant case, there were thirty-six prime contractors. Normally there are five. The State broke the contracts down to try to obtain minority participation on the project.

For a delay to be tolerated, it must be reasonable under the circumstances. The delay on this project of almost two years was considerable and intolerable. Other than to try to put the blame on other contractors, the Respondent has offered little excuse for the delay in excavation from the beginning.

In the present case, Lowry was given 550 days to complete its work from the authorization to proceed. The authorization to proceed issued on August 30,1978. The entire project was to be completed in 730 days pursuant to the project specifications. While the Respondent argues that the completion date was provisional and did not impose a duty upon the owner to ensure completion by that date, citing Edwards Construction Co. v. Illinois State Toll Highway Authority (1975), 34 Ill. App. 3d 929, Respondent’s reliance is misplaced. Here the contract was awarded in July of 1978, and the authorization to proceed was issued August 30, 1978. It was reasonable for Claimant to expect that its bid and completion date would correspond to the original specifications and the lower labor rates. Claimant could rely on the outside completion date of 730 days as a reasonable completion date.

The delays in this case were beyond being reasonable. Respondent had the responsibility for the damages sustained by the Claimant due to the delays. However, the damages are difficult to ascertain exactly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fru-Con Corp. v. State