J.F., Inc. v. S. M. Wilson & Co.

504 N.E.2d 1266, 152 Ill. App. 3d 873, 105 Ill. Dec. 748, 1987 Ill. App. LEXIS 2094
CourtAppellate Court of Illinois
DecidedFebruary 3, 1987
Docket5-81-0620
StatusPublished
Cited by7 cases

This text of 504 N.E.2d 1266 (J.F., Inc. v. S. M. Wilson & Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.F., Inc. v. S. M. Wilson & Co., 504 N.E.2d 1266, 152 Ill. App. 3d 873, 105 Ill. Dec. 748, 1987 Ill. App. LEXIS 2094 (Ill. Ct. App. 1987).

Opinion

JUSTICE WELCH

delivered the opinion of the court:

Following a jury verdict in the circuit court of Madison County, the defendant, S. M. Wilson & Company, appeals and the plaintiff, J.F., Incorporated, cross-appeals. The jury returned a verdict in favor of the plaintiff on the theory of third-party beneficiary in the contract between defendant and the Illinois Capital Development Board (Capital). On appeal, defendant raises the issue of whether the contract between Capital and defendant for certain portions of a construction project conferred third-party-beneficiary status upon the plaintiff, who contracted with Capital for other portions of the construction project. We find that the plaintiff was not a third-party beneficiary to the contract between defendant and Capital and accordingly reverse.

In September 1973 Capital awarded separate prime contracts for the construction of two buildings for the Alton Area Career Development Center. In the contract, Capital was called the owner. The Alton Community Unit School District No. 11 became the ultimate user. Capital awarded to plaintiff the heating and electrical contract and to defendant, the general construction contract. Both contracts were for fixed amounts, with identical language and completion dates. General obligations of the parties'were set out in the contracts, and the specific contractual requirements were established in the specification book and the drawings. The contract documents specified 500 calendar days for completion, which would have been January 25, 1975. However, because of various delays on the project, the project did not receive a certificate of final acceptance until August 1976.

Since plaintiff incurred costs for various delays, it filed suit against defendant on the contract between defendant and Capital alleging that it had third-party-beneficiary status. Plaintiff also sued the architect and the soils engineer for negligence and Capital on the contract. Plaintiff voluntarily dismissed the soils engineer. The trial court dismissed the suit against Capital, finding that the Court of Claims had exclusive jurisdiction over suits against the State. Defendant counterclaimed on the same theory as the plaintiff.

At the conclusion of the jury trial, the jury returned a verdict against the defendant on the contract count for $37,000 and $5,000 against the plaintiff on the defendant’s counterclaim. From this verdict the parties appeal.

Although defendant raises several issues on appeal, the issue which this court finds significant is whether the construction contract between Capital and defendant conferred third-party-beneficiary status upon another prime contractor (J.F., Incorporated) contracting to do other portions of the same project and as such permits J.F., Incorporated to sue upon the contract for delay damages.

The Illinois Supreme Court held in Carson Pirie Scott & Co. v. Parrett (1931), 346 Ill. 252, 258,178 N.E. 498, 501:

"The rule is, that the right oí a third party benefited by a contract to sue thereon rests upon the liability of the promisor, and this liability must affirmatively appear from the language of the instrument when properly interpreted and construed. The liability so appearing can not be extended or enlarged on the ground, alone, that the situation and circumstances of the parties justify or demand further or other liability.” (346 Ill. 252, 258, 178 N.E. 498, 501.)

It is not necessary that the contract identify the third party, but rather define the third party by description of a class or be identified at the time of performance is due. (Altevogt v. Brinkoetter (1981), 85 Ill. 2d 44, 55-56, 421 N.E.2d 182, 187.) However, since Carson, the courts have recognized that the intention of the parties must be gleaned from the contract as a whole and the circumstances surrounding the parties at the time of its execution. Metro East Sanitary District v. Village of Sauget (1985), 131 Ill. App. 3d 653, 657, 475 N.E.2d 1327, 1330; Illinois Housing Development Authority v. Sjostrom & Sons, Inc. (1982), 105 Ill. App. 3d 247, 254-55, 433 N.E.2d 1350, 1356.

Since the facts of this case are rather unique to Illinois courts, it is important to present an overview of the established cases in the area. In our search, this court has found that the courts have followed a strict interpretation of the rule granting third-party-beneficiary status in construction contract cases.

In Carson, the court stated that Carson did have third-party-beneficiary status in the contract between the Danville Hotel and Caldwell & Company. In the contract, Carson was listed as a supplier of linens to the hotel. When the hotel did not pay Carson for the linens, the court stated that the intention of the parties to the agreement was not only to install the listed furnishings into the hotel but also to pay for them if the hotel company did not. Thus, the court found that the parties intended to directly benefit the third party, Carson.

In Searles v. City of Flora (1906), 225 Ill. 167, 80 N.E. 98, the court did not find third-party-beneficiary status for the subcontractors and materialmen. When Searles entered into a bond contract with National Surety Company to secure the city of Flora from liens for labor and equipment furnished on the city project, the court found that when Searles bought material on credit for the project, it lacked authority. The court stated that the contract between the city of Flora and Searles intended Searles to pay for the items upon delivery. The court did not find that the materialmen had third-party-beneficiary status and as such did not permit the subcontractors and materialmen to sue on the bond agreement.

In the recent case of Metro East Sanitary District v. Village of Sauget, this court has continued to strictly interpret third-party-beneficiary status. In Metro East, this court did find that the contract between the village of Sauget and the various municipal corporations did intend to directly benefit the third party — the attorney — because the agreement specifically referred to the payment of such fees. The court found that “the parties anticipated that attorney services would be provided on credit and desired to make express arrangement for payment thereof.” (Metro East Sanitary District v. Village of Sauget (1985), 131 Ill. App. 3d 653, 658, 475 N.E .2d 1327, 1330.) Thus, the court found that the attorney had third-party-beneficiary status and may sue on the contract.

From these cases, this court finds that it must look at the circumstances surrounding the contract when the parties entered into the contract and must look at the contract itself in order to properly assess the intentions of the parties. This court will not extend liability or interpret the contract to extend liability because the situation and circumstances of the parties demand further or other liability. The record reveals the following facts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Lowry Electric Co. v. State
43 Ill. Ct. Cl. 52 (Court of Claims of Illinois, 1991)
Lippert Brick Contracting v. State
43 Ill. Ct. Cl. 71 (Court of Claims of Illinois, 1991)
K & S Associates, Inc. v. State
43 Ill. Ct. Cl. 117 (Court of Claims of Illinois, 1991)
Altman Construction Co. v. State
44 Ill. Ct. Cl. 7 (Court of Claims of Illinois, 1991)
Barth Electric Co. v. Traylor Bros., Inc.
553 N.E.2d 504 (Indiana Court of Appeals, 1990)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
504 N.E.2d 1266, 152 Ill. App. 3d 873, 105 Ill. Dec. 748, 1987 Ill. App. LEXIS 2094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jf-inc-v-s-m-wilson-co-illappct-1987.