Thomas G. Snavely Co. v. Brown Constr. Co.

239 N.E.2d 759, 16 Ohio Misc. 50, 45 Ohio Op. 2d 41, 1968 Ohio Misc. LEXIS 244
CourtAllen County Court of Common Pleas
DecidedAugust 30, 1968
DocketNos. 49332 and 49333
StatusPublished
Cited by9 cases

This text of 239 N.E.2d 759 (Thomas G. Snavely Co. v. Brown Constr. Co.) is published on Counsel Stack Legal Research, covering Allen County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas G. Snavely Co. v. Brown Constr. Co., 239 N.E.2d 759, 16 Ohio Misc. 50, 45 Ohio Op. 2d 41, 1968 Ohio Misc. LEXIS 244 (Ohio Super. Ct. 1968).

Opinion

Hitchcock, J.

(By assignment from Paulding County.) These two cases have different plaintiffs but the same defendants. Counsel for defendant Brown Construction Company (Brown) have withdrawn and although Brown was notified of a hearing held April 26, 1968, to consider motions to dismiss the second amended petition of each plaintiff filed by the other defendants, no one appeared for Brown.

The motions to dismiss will be overruled.

As demurrers to an amended petition were sustained by another judge, defendants Ohio Steel Foundry Company (Foundry) and American Bridge Company (American) contend that both of the second amended petitions now before the court contain no essential new material so should be dismissed as the equivalent of a failure to plead further. Consequently, each motion to dismiss is the equivalent of a demurrer addressed to the second amended petition, and both are treated as such.

The court has considered these cases anew and has reached the conclusion that the motions to dismiss should be overruled, even though the second amended petition differs little from the prior amended petition. The petitions now before the court repeat the general allegations and make it clear beyond peradventure of doubt that all contracts involved used “American Institute of Architect printed form contracts, all containing identical conditions with the exception of the typed in provisions” and all “provided for the cooperation and coordination of all of the defendants, as to the timing of their individual work phase in the construction, so that the job might be completed as scheduled, all of which contract document schedules” each “plaintiff relied upon.”

The motions are based upon the theory that plaintiffs have not as to them stated a cause of action as third party beneficiaries of a contract or contracts to which plaintiffs were not a party. They require the court to consider the [52]*52facts plead as true and in that light determine if they are of legal consequence. With Brown, of course, plaintiffs had their individual subcontracts.

The amended petitions tell us that sometime prior to early 1961 defendant Foundry determined to build a size-able factory building in Lima, Ohio. It made a general written contract with defendant Brown for this purpose which was reduced to writing June 8, 1961. This general contract contained provisions reserving to Foundry the right to award other contracts it “might desire,” pursuant to which it made one contract with defendant American for the fabrication and erection of structural steel. These two contracts recite that time is of the essence and provide schedules for the accomplishment of various sections of the work required. They further provide that mentioned time schedules apply to “all of the various sub-trades.” Plaintiff Thomas Gk Snavely Company (Snavely) on May 15, 1961, entered into a contract with Brown to do for $78,500 the required masonry work which was to be begun July 17, 1961; the exterior work was to be complete by October 16, 1961; and the interior by December 1, 1961. Plaintiff Lake Erie Electric, Inc. (Electric), also entered into a contract with Brown to do for $129,000 the required electric work which was to be started July 1, 1961, and be completed by December 1, 1961. This contract was made in May 1961, but not reduced to writing until November 7, 1961. The contracts of the plaintiffs were, as the others, written on standard A. I. A. forms reciting that time was of the essence and providing time schedules for beginning and completion of the various kinds of work necessary to be accomplished. Said time schedules bear this inscription: “Submitted 5-3-61.”

By reason of delay caused by nonobservance of the time schedules in the contracts with Foundry, upon which each plaintiff relied when making its subcontract with Brown, plaintiff Snavely was unable to begin work required under its subcontract on July 17, 1961, as scheduled. It actually began work on August 20,1961, which was further delayed so that it was not completed until in June 1962. [53]*53For the same reason Electric was unable to begin work required under its subcontract about July 1, 1961, as scheduled. It actually began work on August 1, 1961, which was further delayed so that it was not completed until early September 1962.

That the delay caused by the nonobservance of the time schedules set out in these contracts caused plaintiffs substantial increase in their costs by reason of winter work, labor, supervision, material, payroll, taxes, insurance, travel, and subsistence, general overhead, and other miscellaneous items to the damage of Snavely in the amount of $17,375.78 and to the damage of Electric in the amount of $41,628.58, all of which is prayed for with interest from May 16, 1963.

In part, the Restatement of the Law of Contracts, 1932 recites:

“Section 133. (1) Where performance of a promise in a contract will benefit a person other than the promisee, that person is, except as stated in subsection (3):
i C # * *
“(b) a creditor beneficiary if no purpose to make a gift appears from the terms of the promise in view of the accompanying circumstances and performance of the promise will satisfy an actual or supposed or asserted duty of the promisee to the beneficiary, or a right of the beneficiary against the promisee which has been barred by the Statute of Limitations or by a discharge in bankruptcy, or which is unenforceable because of the Statute of Frauds;
“(c) An incidental beneficiary if neither of the facts stated in Clause (a) nor those stated in Clause (b) exist.
e í * * #
“Section 134. The statements in Sections 135-147 are applicable both to absolute and conditional promises in either formal or informal contracts.
# #
“Section 136. (1) Except as stated in Sections 140, 143.
“(a) a promise to discharge the promisee’s duty creates a duty of the promisor to the creditor beneficiary to perform the promise;
[54]*54“(b) a promise to discharge the promisee’s duty creates also a duty to the promisee;
“(c) whole or partial satisfaction of the promisor’s duty to the creditor beneficiary satisfies to that extent the promisor’s duty to the promisee;
ti# # #
“ (2) Whether the extent of the promisor’s duty to the creditor beneficiary is measured by the promisee’s actual, supposed, or asserted duty to the beneficiary at the time of the making of the contract, or at some other time, depends upon the interpretation of the promise.
“Section 139. It is not essential to the creation of a right in a donee beneficiary or in a creditor beneficiary that he be identified when a contract containing the promise is made.
u* # *
“Section 141. (1) A creditor beneficiary who has an enforceable claim against the promisee can get judgment against either the promisee or the promisor or against each of them on their respective duties to him. Satisfactoin in whole or in part of either of these duties, or of judgments thereon, satisfies to that extent the other duty or judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hagedorn v. Veritas Software Corp.
250 F. Supp. 2d 857 (S.D. Ohio, 2002)
Morrison v. Circuit City Stores, Inc.
70 F. Supp. 2d 815 (S.D. Ohio, 1999)
Trumbull v. Century Marketing Corp.
12 F. Supp. 2d 683 (N.D. Ohio, 1998)
Barth Electric Co. v. Traylor Bros., Inc.
553 N.E.2d 504 (Indiana Court of Appeals, 1990)
Midwest Dredging Co. v. McAninch Corp.
424 N.W.2d 216 (Supreme Court of Iowa, 1988)
J.F., Inc. v. S. M. Wilson & Co.
504 N.E.2d 1266 (Appellate Court of Illinois, 1987)
CH Leavell & Co. v. Glantz Contracting Corp. of La., Inc.
322 F. Supp. 779 (E.D. Louisiana, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
239 N.E.2d 759, 16 Ohio Misc. 50, 45 Ohio Op. 2d 41, 1968 Ohio Misc. LEXIS 244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-g-snavely-co-v-brown-constr-co-ohctcomplallen-1968.