Guarantee Electrical Co. v. State

43 Ill. Ct. Cl. 35, 1991 Ill. Ct. Cl. LEXIS 59
CourtCourt of Claims of Illinois
DecidedMay 30, 1991
DocketNo. 81-CC-2466
StatusPublished
Cited by2 cases

This text of 43 Ill. Ct. Cl. 35 (Guarantee Electrical Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guarantee Electrical Co. v. State, 43 Ill. Ct. Cl. 35, 1991 Ill. Ct. Cl. LEXIS 59 (Ill. Super. Ct. 1991).

Opinion

OPINION

Montana, C.J.

The Claimant, Guarantee Electrical Company, brought this claim seeking $457,933.28 in damages incurred due to delays and other problems encountered in the performance of a construction contract with the Respondent’s Capital Development Board (hereinafter referred to as the “CDB”). The case was tried over many months by the commissioner assigned to the case. The cause was consolidated for trial purposes only with claims by Lippert Brick Contracting, Lowry Electrical Company, and K & S Associates, Inc.

On August 1,1978, .the CDB entered into a contract with Claimant in which Claimant agreed to be the electrical contractor for the construction of two of the three buildings in the East St. Louis Community College project. The project consisted of the Skilled Training Center, the Academic Building, and the Learning Resource Center. Guarantee Electrical Company worked on the Academic Building and the Learning Resource Center. The project was scheduled to begin in August of 1978 and be completed in 730 calendar days and by August 30,1980. Time was of the essence in the contract documents. The CDB gave Claimant bid documents and drawings upon which Claimant testified it relied in computing its bid and planning its work. With these documents and using the customary construction and bidding practices, Claimant’s bid including some change orders, was $505,090.00 and is documented in Claimant’s Exhibit No. 265.

In fact, the project was finally completed in about 1330 calendar days.. Claimant alleged that it was prevented from completing its work within the contractual 730 days due to delays not attributable to Claimant and that Claimant incurred actual costs of $963,023.28.

The Claimant, upon acceptance of its bid, was ready, willing and able to perform. The CDB, in August of 1978, told the contractors to begin the project and authorized the contractors to proceed pursuant to Exhibit 23, the authorization to proceed. Claimant asserts it performed its work under very adverse project conditions and was not responsible for any material delays.

It is apparent from the entire record that Guarantee Electrical Company caused no material delays on this project. The CDB had the obligation to obtain an excavator to begin the project. The project was to start on August 30, 1978. The CDB was unable to obtain a qualified excavator and the excavation was still incomplete over a year after the project began. The CDB’s utter failure to have the excavation start on time and continue was a major problem for over a year and was one of the major delays on the project. Because of the excavation problems, all of the project schedules were off from day one. This had a snowball effect as the delay caused the project to go through four winters rather than the scheduled two winters. Once the project was delayed by the excavation problem all of the coordination and sequencing was out of sync and the architect/engineer (“A/E”) and general contractor were not able to get the project back in sync.

Claimant did everything it could do. It notified the CDB of the delays due to no excavation, the problems of not being able to work outside in the winter, the problems of lack of heat in the buildings, and other problems. The CDB was unable to clear up these problems and the project was delayed almost two years beyond its scheduled completion date for the entire project.

Other acts of the CDB caused substantial delays on this project. The normal CDB project has five prime contractors. The East St. Louis Community College project was broken down to thirty-six prime contractors by CDB to obtain minority participation. CDB officials acknowledged that this number of contractors required increased coordination which the (A/E) and general contractor chosen by CDB were unable to perform. CDB did nothing to rectify the inept coordination even after it was apparent the A/E and general contractor were not up to the job. Another long delay was that the structural steel did not go up in time. The building was not enclosed on schedule so during the second winter the electricians could not work. There was no steel decking on the second floor and roof which caused delays. There was no heat, ice was on the floors, and the building was not weathertight, all of which caused delays. Also, there was no proper sequencing of the trades or proper coordination. Paperwork was not timely processed. There were many CDB personnel changes as the CDB had five different project managers on this project. All of these factors also caused delays.

Once the excavation problem got the project off to a horrendous start, the compression of the schedule caused increased costs and because K & S, the general contractor, failed to provide realistic schedules on time, the sequencing was out of sync. Electricians are at the mercy of the other trades. To be efficient, the electricians need to put in their conduit before other trades do their work. Here the scheduling was so bad that Guarantee was prohibited from efficiently doing its work.

Other delays were caused by the CDB failing to have some of the contractors be prequalified. The original excavator, Eanes Excavating, was unable to obtain a performance bond. Later, rather than obtain a qualified excavator, the CDB change ordered Eanes to work as a subcontractor to K & S, the general contractor. It then became apparent that Eanes just could not do the job. By then months and months were lost and the project was in real trouble. With the number of prime contractors on this project, coordination meetings should have been held once a week. They were held once a month. The CDB was to have people at the meetings with authority. The project managers did not have authority to act on the questions raised at the coordination meetings. Often no decisions on problems were made for months.

In Exhibit 274, the contract documents in Paragraph D state:

“The contractor will not be entitled to any claim for delays or compensation from the CDB on account of any delays except that the contract sum will be adjusted for delays caused by the CDB, the architect/engineer, or the construction manager in the administration of this contract when such delays are for an unreasonable period of time caused by the acts of CDB.”

Most of the preceding delays and particularly the excavating delays are attributable to the CDB. The A/E caused delays by failing to get shop drawings to the contractors on time. Six months after the job was to have started, they were still calling for shop drawings.

The testimony is devoid of any blame for delay on Guarantee Electrical. In fact, CDB officials testified Claimant did good work and was not responsible for delays. As previously stated, this project was unusual in that the CDB usually has five prime contractors. In the instant case, they had 36 prime contractors so that minority contractors could be used. Such a situation required great coordination skills which were not apparent in the CDB, the A/E, and the general contractor. Once the excavation did not proceed as scheduled, the entire project was ill-fated. The CDB failed to take appropriate steps to obtain a competent excavator and the project suffered. CDB officials admitted it was their obligation to obtain an excavator.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stupp Bros. Bridge & Iron Co. v. State
51 Ill. Ct. Cl. 195 (Court of Claims of Illinois, 1998)
Fru-Con Corp. v. State
50 Ill. Ct. Cl. 50 (Court of Claims of Illinois, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
43 Ill. Ct. Cl. 35, 1991 Ill. Ct. Cl. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guarantee-electrical-co-v-state-ilclaimsct-1991.