Pora Construction Co. v. Capital Development Board

37 Ill. Ct. Cl. 54, 1984 Ill. Ct. Cl. LEXIS 4
CourtCourt of Claims of Illinois
DecidedNovember 9, 1984
DocketNo. 79-CC-0721
StatusPublished
Cited by2 cases

This text of 37 Ill. Ct. Cl. 54 (Pora Construction Co. v. Capital Development Board) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pora Construction Co. v. Capital Development Board, 37 Ill. Ct. Cl. 54, 1984 Ill. Ct. Cl. LEXIS 4 (Ill. Super. Ct. 1984).

Opinion

Holderman, J.

The final hearing on the above-entitled claim was held on June 13, 1983, in the Court of Claims hearing room, 188 W. Randolph Street, Chicago, Illinois.

From the evidence introduced at the hearings it appears that in February of 1975, Claimant, Pora Construction Company, entered into a contract with Respondent, Capital Development Board, to act as general contractor in the construction of Phase II of the Morraine Valley Community College (MVCC). This was an addition to an existing college facility, which had been Phase I. The contract price was initially $5,156,626.00.

The addition to be constructed by Pora consisted of two two-story structures, connected by an enclosed bridge, as well as adjacent parking areas, landscaped areas, walkways and the like, all totalling approximately 199,000 square feet. The buildings were to include classrooms, laboratories, study units, computer areas and a library.

For construction purposes, the project was designated by area and by various unit numbers. The building which was to connect to the two existing MVCC facilities and which therefore would be put to use first, was designated Units 3 and 5. The other building was labelled Units 1 and 2. The enclosed bridge between the two buildings, which was to connect with Units 3 and 2, was to be Unit 4. Unit 4 was to span a scenic drive running north and south through the campus, which had theretofore been a public highway known as 88th Avenue.

Caudill Rowlett Scott (CRS), a Houston, Texas, firm, was appointed by CDB to act as its architect/engineer (a/e) for the MVCC project. According to article 2 of the general conditions of the contract documents, CRS, as a/e, was to provide general administration of Pora’s contract, to interpret the contract, to judge Pora’s performance, to accept or reject work, and to act as the owner’s representative with respect to the project. Accordingly, as the owner’s representative, CRS prepared and published the plans and specifications for the project. The CDB, as owner, had authority to stop the work, or any portion thereof, and was responsible for promptly furnishing all surveys, easements, information and instructions, pursuant to article 3 of the general conditions.

Pora, as required by article 4 of the general conditions, submitted an estimated progress schedule of the entire MVCC project for the a/e’s approval, indicating dates for starting and completion of all stages of construction. According to that schedule, based on the plans and specifications as originally provided by the owner, the project was to be constructed between March 17, 1975, and June 19, 1976, within the 420 days’ completion time specified in the contract. A subsequent revision of the schedule extended the completion date to October 1, 1976. Claimant contends that various owner-caused delays caused a job overrun of Pora’s work for approximately eight months from this extended completion date.

Pora’s plan of construction anticipated a certain orderly and logical sequence to the construction of the Phase II facility. As a result of meeting with representatives of the college, it was decided that the building designated Units 3 and 5 would be completed and ready for occupancy first, as it was the building adjacent to the existing facility. Work would then proceed in steps progressing away from the existing college, with the bridge next and finally the other building (Units 1 and 2). The specific construction sequence, then, was to be 5-3-4-2-1.

As a result of various delays occasioned by the alleged action, omissions and changes by the CDB, the final completion of Pora’s work under the contract, as amended from time to time, occurred approximately 242 days after the completion date, as extended. Those alleged owner-caused delays were the focal point of the evidence adduced in this case. It is claimed, that as a result of the alleged owner-caused delays, Pora’s work schedule was altered and impeded to such an extent that Pora incurred $379,045.00 of compensable damage flowing directly from the impact of the delays and obstructions caused by the CDB.

The complaint in this case specifies the manner in which several separate actions or omissions of CDB combined to cause delay and unwarranted expense to Pora and alleges actionable breaches of express or implied covenants of the contract between Pora and CDB. Specifically, the four contractural breaches, and therefore the four legal issues involved herein, were as follows:

1. A breach of the implied warranty of the accuracy and sufficiency of the plans and specifications;

2. a breach of the implied covenant to facilitate the progress of the work;

3. a breach of the implied warranty of access to the job site; and

4. a breach of certain express provisions of the general conditions of the contract.

In the present situation the contract documents did not set a fixed time for completion but required the contract to be completed in 420 days. The length of the contract was established by the Claimant. The contract reserved the right to CDB to stop work, change specifications and reject the work of the contractor. (Sections 12.1 and 2.2.12 of the general conditions.) The contract documents provided that if the Respondent exercised its rights previously stated or if delay in the progress of the work was caused by the Respondent, then the contract would be modified by extending the completion time of the contract and/or adjusting the contract price for any changes or delays. This project also ran into unexpected bad weather, unfavorable soil conditions and changes in the specifications.

The Claimant in the present case did modify the contract by using the change order provisions of the contract. Claimant is now requesting additional compensation for costs due to the delay and damages caused by the decrease in labor effectiveness because the work was done in winter months.

Claimant is claiming reimbursement for additional costs it claims it sustained as a result of lack of accessibility to the site; problems concerning the removing of certain telephone and Commonwealth Edison lines and poles; delays to work as a result of pile driving difficulties; delay due to switchgear revision and elevator installation; and also delays due to handicap ramp installations and the revision of the expansion joints to be used in the concrete.

When Claimant began driving piles it was determined that more soil tests were needed. This caused some delay. The job site was intersected by a heavily travelled highway known as 88th Avenue, which road was not vacated prior to the start of construction. This caused some inconvenience to the work progress on the project. The same applies to the delay in the removal of the telephone lines and poles and the electric lines and poles which were situated on the job site.

The switchgear to be used in the building had to be reordered. This caused some delay. A delay was also occasioned by a change in the plans calling for the installation of an elevator and handicap ramps. Intermingled with the delays and contributing thereto was extremely bad weather which caused a delay of 56 days out of the first three months. Certain other delays were also encountered, some attributable to the Respondent, and some to the Claimant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Johnson County Asphalt, Inc. v. State
39 Ill. Ct. Cl. 36 (Court of Claims of Illinois, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
37 Ill. Ct. Cl. 54, 1984 Ill. Ct. Cl. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pora-construction-co-v-capital-development-board-ilclaimsct-1984.