Town of Milford v. O'Neil Bros., Inc.

8 Conn. Super. Ct. 403, 8 Conn. Supp. 403, 1940 Conn. Super. LEXIS 141
CourtConnecticut Superior Court
DecidedJuly 22, 1940
DocketFile 56798
StatusPublished
Cited by4 cases

This text of 8 Conn. Super. Ct. 403 (Town of Milford v. O'Neil Bros., Inc.) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Milford v. O'Neil Bros., Inc., 8 Conn. Super. Ct. 403, 8 Conn. Supp. 403, 1940 Conn. Super. LEXIS 141 (Colo. Ct. App. 1940).

Opinion

CORNELL, J.

Prior to December 21, 1935, the plaintiff (hereinafter referred to as the “town”) determined to construct a portion of a system of sanitary sewers in its central area and on the latter date the defendant, O’Neil Bros., Inc. (hereinafter designated the “contractor”) executed a writing known as Contract B-l to build and lay sanitary sewer lines in the following streets: North Street, Plymouth Place, Prospect Street, River Street, West River Street, Daniel Street, Factory Place and a small section of New Haven Avenue; also, an inverted syphon crossing the Wepawaug River just north of the lower dam. On April 15, 1936, the contractor and the town executed another agreement known as Contract B-2 whereby the contractor undertook to build sanitary sewers ■constituting the remainder of the program, in the following streets and locations: Noble Avenue. Reed Street, Seaside Avenue, North Broad Street, South Broad Street, Golden Hill Street, Central Avenue, Greene Street, Union Street; harbor side section with George and Elton Streets, together with a line known as a private right of way consisting of a reinforced concrete pipe running approximately from New Haven Avenue to a pumping station and an eight-inch force main from the pumping station to the sewage disposal plant. In all, inc’u■sive of risers or chimneys, the total length of pipe to be laid under both contracts was about six and thirty-eight one hundredths miles.

In the early part of January, 1936, the contractor commenced the performance of Contract B-l and immediately following April, 1936, did likewise with respect to the project described in Contract B-2. From the respective dates on which work was begun under each, it progressed continuously (with the exception of certain interruptions alleged in the ■contractor’s second and third counterclaims) until early in June, 1937. At the latter time the work described in both contracts was completed with the exception of certain comparatively minor details, e.g., smoothing highways at trench .sites, cleaning out sewer pipes and manholes, etc. In the in *408 stant action, the town claims damages against the contractor-as principal and the defendant, The London 6? Lancashire In' demnity Company of America, as surety, upon performance bonds executed and delivered to the town as was required in each of the contracts. The basis of this claim is that the contractor breached both agreements in three respects, viz.: (1) in that, upon completion, the sewer system built under each, infiltrated in excess of the quantities named in each of the contracts; (2) that the contractor has failed to properly perform the work of backfilling the trenches; and (3) a large number of manhole seats and covers do not conform to the specifications.

The most important aspect of the controversy is that which-relates to the alleged failure on the contractor’s part to con' struct the sewer lines so that they would not infiltrate in excess of the maximum daily quantities prescribed in the specifica' tions. The pertinent provisions' relating to this subject are; the same in both agreements and- occur in section 1:21 of Contract B4, and section 1:34 of Contract B'2. They read as follows: “The pipe lines will be tested by measuring the infiltration. These tests will be made by the engineer on sections of the pipe lines or on the entire system as he may elect. The amount of infiltration so measured by the engineer shall not exceed the rate of ten thousand gallons per mile on any two hundred feet sections of the sewers in twenty'four hours..

“If the flow of the ground water on tests exceeds the amount specified above, the contractor shall excavate and uncover such-' portions of the pipe lines, manholes, etc., as give indication of leakage and shall repair or rebuild those portions in full accordance with these specifications. Such repairing and replacing shall be carried on until the complete system meets the requirements for tightness specified above. The contractor shall furnish the engineer with necessary assistance in making the tests and shall include all such costs in the price bid for the completed work. All repairs or reconstruction necessary to meet the requirements of the tests shall be made at the contractor’s own expense.”

The function of the combined systems is to collect sanitary-sewage in the areas serviced by them and conduct it by gravity to'a pumping station built by another contractor, from which point it is forced through a main to a disposal plant aIso> erected by a different concern than the contractor’s. As orig *409 inally designed, the pumping station was to be equipped with two electric pumps, each capable of pumping 400 gallons of fluid per minute, but this was later changed so that there were installed, instead, two electric pumps capable of pumping 600' gallons per minute, but in practice operated alternately. The term “infiltration” as used in the quoted paragraph of the specifications means water which gains entrance to the pipe lines from sources exterior to them. The importance of avoid' ing an excessive amount of this is to obviate placing an urn necessary load upon the pumps, thereby increasing the cost of operation of the pumping plant. The latter is equipped with a device called a Venturi. meter which measures the flow of liquid coming to the pumping station from the system.

During July, August and September, 1937, a firm other than the contractor’s installed 361 house laterals, i.e., pipes connected onto the risers on top of the sewer lines and of the same material and running thence to the curb lines, at which point property owners could connect with buildings on their premises. On September 1'2, 1937, at which time the Venturi meter was operating, the resident engineer made a test at certain points to determine the extent of infiltration in the system. At one place which covered lines 3,'950 feet in length it was then indicated that the maximum flow was excessive by a very great percentage. This, the resident engineer attributed to leakage in the pipe lines. The condition was brought to the contractor’s attention and the request made of him that he cause certain repairs to be effected, on North Street, the-precise character of which does not appear. However, noth' ing was done in response to the resident engineer’s demands, by the contractor up to October 11, 1937.

On the latter date the resident engineer made other tests at two different points which, also, yielded evidence of heavily excessive flow. Following November 16, 1937, the contractor V president came to Milford in response to a letter written him on that date by the resident engineer and put a force of men to work at places indicated by the resident engineer, as well' as at other locations where it was considered that measures might be taken to reduce the assumed leakage. However, both the resident engineer’s and contractor’s efforts were unavailing because the Venturi meter at the pumping station in a reading taken about the middle of November, 1937, showed similar-excessive flow, while an observation made about December 21,. *410 1937, pointed to an increase rather than a diminution of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. Prete Son Cons. v. Town, Madison, No. Cv 91-03103073-S (Oct. 4, 1994)
1994 Conn. Super. Ct. 10068-D (Connecticut Superior Court, 1994)
Salowitz v. Squillacote
10 Conn. Super. Ct. 220 (Connecticut Superior Court, 1941)
Salowitz v. Squillacote
10 Conn. Supp. 220 (Pennsylvania Court of Common Pleas, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
8 Conn. Super. Ct. 403, 8 Conn. Supp. 403, 1940 Conn. Super. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-milford-v-oneil-bros-inc-connsuperct-1940.