A. Prete Son Cons. v. Town, Madison, No. Cv 91-03103073-S (Oct. 4, 1994)

1994 Conn. Super. Ct. 10068-D
CourtConnecticut Superior Court
DecidedOctober 4, 1994
DocketNo. CV 91-03103073-S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 10068-D (A. Prete Son Cons. v. Town, Madison, No. Cv 91-03103073-S (Oct. 4, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Prete Son Cons. v. Town, Madison, No. Cv 91-03103073-S (Oct. 4, 1994), 1994 Conn. Super. Ct. 10068-D (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION CT Page 10069 The parties to the contract action are the plaintiff A. Prete Son Construction Co., Inc. ("Prete") and the defendant town of Madison ("Town").

The complaint is in four counts and has its basis in a written contract, dated June 19, 1987 between Prete and the Town. That contract was one under which Prete was to be paid $1,530,531.00 by the Town for performing certain additions, alterations and construction at the Daniel Hand High School ("Hand") in Madison. The first count alleges that the Town has failed and refused to pay to Prete the balance due and owing it in the amount of $125,706.55 although it has performed the services and provided the materials as agreed upon. This sum is specifically claimed to be due and owing for the services and materials in installing a new gymnasium floor by Prete at Hand. Prete seeks money damages under the first count for the alleged breach.

The second count sounds in unjust enrichment. It refers to the first count and goes on to allege in addition that Prete provided materials and services in good faith expecting to be paid by the Town. However, the Town, it is alleged, although wilfully availing itself of such materials and services, has retained and enjoyed the such benefits without payment and has, therefore, been unjustly enriched. Accordingly, because the Town, at all times, knew or reasonably should have known that Prete expected to be paid, the Town is required in equity to compensate it plus a reasonable allowance for profit.

Going on, the third count alleges that on or before June 19, 1987, Prete was engaged by the Town to perform certain alterations, renovations and construction at Hand and that it did so in good faith expecting to be paid by the Town. Again, alleging that the Town had wilfully availed itself of the plaintiff's services and materials for which it has refused to pay Prete $125,706.55 the alleged reasonable value of such services and materials, the plaintiff seeks to recover the reasonable value of the same in the third count.

The fourth count which essentially alleges that the failure and refusal of the Town to pay Prete as claimed violated General Statutes §§ 42-110a et seq., i.e. Connecticut Unfair Trade Practice Act and seeks relief thereunder. This fourth count CUTPA claim was CT Page 10070 withdrawn in open court at the trial.

In answering the allegations of the complaint the Town, while admitting the execution of the written contract of June 19, 1987, essentially denies the remaining allegations. The Town, however, has setup three special defenses and has also interposed a counterclaim.

The first special defense maintains that the Town "has paid the plaintiff in full for all work and materials performed in accordance with the contract."

The second special defense alleges the following: "1. The plaintiff breached the contract with respect to the installation of the Daniel Hand High School gymnasium floor in that the floor failed to meet the quality standards specified within the contract documents; the floor failed to comply with the plans and specifications and general conditions; the floor was improperly installed; the workmanship of the plaintiff or its subcontractors was defective; 2. The aforesaid gymnasium floor was found to be unacceptable and was rejected and the plaintiff contractor was directed to correct it, but has failed and refused to do so; 3. As a consequence of the aforesaid, the Town has been required to replace the gymnasium floor; 4. As a consequence of the aforesaid, the Town has been required to hire a new flooring contractor at great expense, incur expenses for architectural services, consultant services and for labor and materials and attorney's fees and expenses for removal, storage and disposal of the defective flooring; 5. The cost and expenses incurred by the Town as a consequence of the breach of the contract by the plaintiff contractor exceed the sums claimed by the plaintiff in his Complaint."

The third special defense alleges the following: "The plaintiff breached the contract by failing to provide to the defendant warranties, guarantees, as-built plans and other documentation called for by the contract and the plaintiff, it subcontractors and suppliers have failed to honor any guarantees or warranties with respect to the Daniel Hand High School gymnasium floor." The plaintiff denies each special defense.

The defendant has interposed a counterclaim seeking money damages. That counterclaim which alleges the execution of the written contract of June 19, 1987 incorporates all the allegations of its second special defense and then adds these additional CT Page 10071 allegations: "8. As a result of the breaches of contract as aforesaid, the Town of Madison has refused to honor the contractor's application for payment in the amount of $125,706.55; 9. As a result of the breaches of the contract by the A. Prete Son Construction Co., Inc., the Town of Madison has suffered damages in excess of the aforesaid sum of $125,706.55 and the plaintiff contractor is indebted to the Town of Madison; 10. Although many times requested to do so, the plaintiff contractor A. Prete Son Construction Co., Inc. has neglected and refused to correct the defective floor as its own expense." Essentially, the plaintiff denies the allegations of the counterclaim. At the trial counsel stipulated that all the evidence adduced at the trial would apply to both the plaintiff's complaint and the defendant's counterclaim.

I.
By way of broad background this complex case which was presented in an eighteen day trial at which about one hundred and seventy exhibits were introduced stems from a written contract between Prete and the Town of Madison dated June 19, 1987 which concerned the construction of an addition and alterations to the Hand High School including the installation of a gymnasium floor at that school. It is with the installation of that floor with which this case is basically concerned. The plans and specifications for this addition and alteration project, including the gym floor were drawn by Kosinski Construction Management Inc., a New Haven firm of architects, planners, engineers and construction. The Town had selected that firm for that purpose after the execution of a written contract in October 1985 between Kosinski Associates and the Town. Peter Kosinski, ("Kosinski") a practicing Connecticut architect since 1965, is a principal in Kosinski Associates.

At the time Prete was working at Hand that company was also under contract with the Town and working on additions and the like to the Jeffrey Elementary School in Madison ("Jeffrey School"). The Jeffrey School building was close by to the building housing the Hand High School. Prete's office trailer, during the Hand and Jeffrey schools jobs was on the premises in front of the gym entrance to Hand.

After the original floor subcontractor left the job, Prete retained the firm of A. Dion Son from Massachusetts in the Spring of 1987 as the new subcontractor to install the gym floor. The witness Donald Dion ("Dion") was a principal of A. Dion Son. In CT Page 10072 June 1988 when Prete and Dion agreed that Dion would install the floor at Hand, Prete gave Dion a copy of that portion of the General Conditions of the Contract for Construction which was entitled "Gym Wood Flooring" which was Section 09560 of that contract and contained the specifications for the gym floor. Prete also gave him a copy of the Kosinski blueprints of the Hand gym.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bak-A-Lum Corp. of America v. Alcoa Building Products, Inc.
351 A.2d 349 (Supreme Court of New Jersey, 1976)
Carpenter v. Josey Oil Co.
26 F.2d 442 (Eighth Circuit, 1928)
Lar-Rob Bus Corp. v. Town of Fairfield
365 A.2d 1086 (Supreme Court of Connecticut, 1976)
F.A. Gray, Inc. v. Weiss
519 A.2d 716 (Supreme Judicial Court of Maine, 1986)
Victoria Bank & Trust Co. v. Brady
779 S.W.2d 893 (Court of Appeals of Texas, 1989)
In Re Fahnders
66 B.R. 94 (C.D. Illinois, 1986)
Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Colonial Discount Co. v. Avon Motors, Inc.
75 A.2d 507 (Supreme Court of Connecticut, 1950)
Cecio Bros., Inc. v. Feldmann
287 A.2d 374 (Supreme Court of Connecticut, 1971)
Gosselin v. Better Homes, Inc.
256 A.2d 629 (Supreme Judicial Court of Maine, 1969)
Burns v. Gould
374 A.2d 193 (Supreme Court of Connecticut, 1977)
Bertozzi v. McCarthy
323 A.2d 553 (Supreme Court of Connecticut, 1973)
Stanton v. Grigley
418 A.2d 923 (Supreme Court of Connecticut, 1979)
Secondino v. New Haven Gas Co.
165 A.2d 598 (Supreme Court of Connecticut, 1960)
Dooley v. Leo
440 A.2d 236 (Supreme Court of Connecticut, 1981)
H. B. Toms Tree Surgery, Inc. v. Brant
446 A.2d 1 (Supreme Court of Connecticut, 1982)
Grenier v. Compratt Construction Co.
454 A.2d 1289 (Supreme Court of Connecticut, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 10068-D, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-prete-son-cons-v-town-madison-no-cv-91-03103073-s-oct-4-1994-connsuperct-1994.