Stone Forest Industries, Inc. v. The United States, Defendant/cross-Appellant

973 F.2d 1548, 1992 WL 193570
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 17, 1993
Docket91-5120, 91-5121
StatusPublished
Cited by86 cases

This text of 973 F.2d 1548 (Stone Forest Industries, Inc. v. The United States, Defendant/cross-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone Forest Industries, Inc. v. The United States, Defendant/cross-Appellant, 973 F.2d 1548, 1992 WL 193570 (Fed. Cir. 1993).

Opinion

PAULINE NEWMAN, Circuit Judge.

In this appeal and cross-appeal from a decision of the United States Claims Court, 1 Stone Forest Industries (SFI) appeals the portion of the decision refusing refund of certain advance deposits paid by SFI under a timber contract. The United States appeals the court’s assessment of interest on certain sums. We reverse on both of these issues.

Background

In 1977 the United States Forest Service and SFI entered into a contract pursuant to the National Forest Management Act of 1976, 16 U.S.C. § 472a, whereby SFI agreed to purchase, cut, and remove 19,430 MBF (thousand board feet) of timber in the Klamath National Forest in California. The contract was called the “Flathead Sale”. The termination date of March 31, 1980 was extended several times, until the contract finally terminated on September 3, 1985.

On September 28, 1984 the California Wilderness Act, Pub.L. No. 98-425, 98 Stat. 1619, was enacted. On December 6, 1984 the Forest Service notified SFI in writing that this Act impacted upon four of the fourteen units in the Flathead Sale, viz., units 8, 9, 11, and 14. Units 8 and 9 were *1550 in the newly designated wilderness area, and units 11 and 14 were affected by access roads. Access was denied, by written notification, to all four units. On December 21, 1984 SFI requested modification of the contract to delete, the affected area. The Forest Service did not respond. On January 17, 1985 SFI requested cancellation of the entire contract. On February 1, 1985, the Forest Service wrote SFI that they were awaiting instructions, and hoped to respond to SFI’s request by March 1, 1985. No response was issued, then or later.

On April 24, 1985, SFI submitted a written plan to commence operations in units 11 and 14 with work scheduled to begin May 1, 1985. On April 30, 1985, the Forest Service issued written notification to SFI denying access to units 11 and 14. In July 1985, with approximately forty days remaining in the contract term, the Forest Service orally (by telephone) notified SFI that SFI could harvest timber in units 11 and 14. No written confirmation or notification authorizing access to units 11 and 14 was issued, and no timber was harvested in those units. The contract expired, by its terms, on September 3, 1985.

SFI requested refund of its deposits of $468,531, which had been deposited, as required by the Forest Service, as advance payment for the timber in units 8, 9, 11, and 14, the area to which access had been denied. The contracting officer refunded $111,768, the sum applied to units 8 and 9. The contracting officer held that SFI had breached the contract by failing to harvest the timber in units 11 and 14 after the oral notice to proceed in July 1985, and assessed damages of $356,763, the remaining amount of SFI’s advance payment.

In its opinion denying SFI’s motion for reconsideration of the decision granting the government’s motion for summary judgment, the Claims Court held that although denial of access to units 8 and 9 was an anticipatory breach of the contract, this was “a mere pro tanto breach of a divisible contract”. The court also held that the Forest Service’s “temporary” denial of access to units 11 and 14 did not constitute a material breach of the contract. The Claims Court held that since the United States had not breached the contract, SFI was required to perform with respect to units 11 and 14, and was liable for damages for failure to do so. The Forest Service’s assessment of damages of $356,763 was affirmed by the Claims Court.

The Claims Court held the United States liable for statutory interest on the $111,768 that was refunded, and for interest on the unpaid interest.

I

Who Breached the Contract?

The first question is whether the Forest Service materially breached the contract, thereby excusing SFI from all further performance, or whether SFI breached the contract by failing to log units 11 and 14.

The grant of summary judgment by the Claims Court receives plenary appellate review. No material facts were in dispute, and the case was decided as a matter of law. Pine Prod. Corp. v. United States, 945 F.2d 1555, 1558 (Fed.Cir.1991); Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987).

SFI states that the United States materially breached the contract when it withdrew four of the fourteen units from the Flathead Sale, following enactment of the California Wilderness Act. Upon material breach of a contract the non-breaching party has the right to discontinue performance of the contract, and to seek redress in accordance with law. Malone v. United States, 849 F.2d 1441, 1445-46 (Fed.Cir.), modified, 857 F.2d 787 (Fed.Cir.1988); Cities Serv. Helex, Inc. v. United States, 543 F.2d 1306, 1313, 211 Ct.Cl. 222 (1976); Airco, Inc. v. United States, 504 F.2d 1133, 1135, 205 Ct.Cl. 493 (1974).

Not every departure from the literal terms of a contract is sufficient to be deemed a material breach of a contract requirement, thereby allowing the non-breaching party to cease its performance and seek appropriate remedy. The standard of materiality for the purposes of *1551 deciding whether a contract was breached “is necessarily imprecise and flexible.” Restatement (Second) of Contracts ,§ 241 cmt. a (1981) (hereinafter Restatement (Second)). The determination depends on the nature and effect of the violation in light of how the particular contract was viewed, bargained for, entered into, and performed by the parties. See generally Restatement (Second) § 241 cmts. a & b.

A

Units 11 and H

The Claims Court held that the Forest Service’s oral notification to resume logging remedied the prior denial of access to units 11 and 14. The court observed that there was a factual dispute as to whether SFI had requested written confirmation of this oral notice, but found this fact immaterial since SFI did not deny that it had received oral notification. 22 Cl.Ct. at 492. We agree that the factual issue of whether SFI requested written confirmation is immaterial, for in this case as a matter of law written notice from the Forest Service was required, whether or not it was requested. SFI bore no burden to request written confirmation, for the Forest Service contract required that all notices must be in writing, and SFI could not proceed without it. Contract provision

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Philips Lighting North American Corporation
Armed Services Board of Contract Appeals, 2024
United States v. Dyncorp Int'l LLC
282 F. Supp. 3d 51 (D.C. Circuit, 2017)
Franklin-Mason v. United States
126 Fed. Cl. 149 (Federal Claims, 2016)
Highland Al Hujaz Co., Ltd.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Caraballo v. United States
124 Fed. Cl. 741 (Federal Claims, 2016)
Dms Imaging, Inc. v. United States
123 Fed. Cl. 645 (Federal Claims, 2015)
Denise Edwards v. the First American Corp
798 F.3d 1172 (Ninth Circuit, 2015)
Allen Engineering Contractor, Inc. v. United States
115 Fed. Cl. 457 (Federal Claims, 2014)
Eden Isle Marina, Inc. v. the United States 0
113 Fed. Cl. 372 (Federal Claims, 2013)
American Whitewater v. Tidwell
959 F. Supp. 2d 839 (D. South Carolina, 2013)
D'andrea Brothers Llc v. United States
109 Fed. Cl. 243 (Federal Claims, 2013)
United States v. Coalition for Buzzards Bay
644 F.3d 26 (First Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
973 F.2d 1548, 1992 WL 193570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-forest-industries-inc-v-the-united-states-cafc-1993.