Pennsylvania Exchange Bank v. United States

170 F. Supp. 629, 145 Ct. Cl. 216
CourtUnited States Court of Claims
DecidedApril 3, 1959
Docket265-57
StatusPublished
Cited by9 cases

This text of 170 F. Supp. 629 (Pennsylvania Exchange Bank v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Exchange Bank v. United States, 170 F. Supp. 629, 145 Ct. Cl. 216 (cc 1959).

Opinion

WHITAKER, Judge.

The Pennsylvania Exchange Bank and Samuel H. Roseman are assignees for the benefit of creditors of Joseph Lerner & Son, Inc. In this opinion we shall refer to Joseph Lerner & Son, Inc., as the plaintiff.

This suit is for the balance of the contract price withheld by defendant, because of plaintiff’s alleged anticipatory breach of the contract by making an assignment for the benefit of its creditors. Defendant also counterclaims for damages for the breach. It is before us on cross-motions for summary judgment *630 and on assignees’ motion to dismiss defendant’s counterclaims.

As a part of its preparation for industrial mobilization in case of war, or the imminence of war, the Signal Corps of the Army promulgated “Procurement Specification No. 15”, which envisaged the execution of “Industrial Preparedness Contracts.” Such a contract was defined as “a mutual agreement between a contractor and the Government which requires the contractor to undertake realistic preparedness measures to improve his ability to produce the component part in the quantity specified in the contract.”

Pursuant to the plan therein outlined, plaintiff on February 29, 1952, entered into a contract relative to the manufacture of “Microwave Magic Tees.” The ultimate objective of this contract was to have ready, in case of war, a willing manufacturer, who had the facilities and was otherwise qualified, and who was ready to promptly produce microwave magic tees 1 in volume.

To accomplish this, the contractor obligated itself to do three things, called “steps”. Step I required it to secure sufficient information about the manufacture of microwave magic tees, and to make such plans for the volume production of them as were necessary to secure “JAN Qualification Approval” as a manufacturer qualified to make the tees promptly and in the required volume. It also required the contractor, as a further demonstration of such ability, to make a pilot run, that is, to actually manufacture specified quantities of the elements required for these tees. The items to be manufactured were listed and the price to be paid therefor was specified, which price was supposed to reimburse the contractor for the cost of making them. The price specified in the contract proved insufficient to cover the manufacturer’s cost and, hence, it was later increased sufficiently to do so.

Step II of the contract required the contractor to accomplish “all production processes short of procuring tooling and materials and short of actual volume manufacture of the articles.” As a part of Step II the contractor was required to make a report to the Signal Corps of its plan of production and its capacity to produce. In doing so, it was to act “on the assumption that [it] will be required to produce 2,821 complete units in one year period, after activation of Step .IV * * 2 The sum to be paid for the cost of performing this step was also set out in the contract.

Step III of the contract required the “acquisition of all additional tooling and manufacturing aids required to meet the Step II mobilization production schedule.” These machines were acquired by plaintiff at a cost of $37,907.37.

All of this was in preparation for Step IV. This step, which was to be taken only in the case of a national emergency, and after receipt of an order from the Government, required “volume production in accordance with previously planned schedules.”

After the completion of Steps I, II, and III, the plaintiff’s obligation under the contract was to preserve the information acquired under Steps I and II, and to keep the machines acquired under Step III in operable condition. This obligation was to continue for a six-year period in anticipation of a national emergency.

For the performance of Steps I and II of the contract the Signal Corps agreed to pay plaintiff the sum of $117,-226.16, less a cash discount of one per cent for payment in 20 days. Under a price redetermination clause, this was in *631 creased to $135,754.48, because plaintiff’s costs exceeded the estimate.

By October 1, 1953, plaintiff had substantially performed all the requirements of Steps I, II, and III. The Government had made part payments of $92,843.12 for the performance of Steps I and II, and had reimbursed the plaintiff for all, except $1,922.23, of the cost of performance of Step III.

On October 1, 1953, a little over one and one-half years after the contract had been entered into, it became necessary for the plaintiff to make an assignment for the benefit of its creditors, in lieu of bankruptcy. The Pennsylvania Exchange Bank and Samuel H. Roseman, as assignees, sue now for the balance due under Steps I, II, and III of the plaintiff’s contract.

The defendant refuses to pay the amount due under two alternative theories which it asserts in its pleadings. In its first counterclaim defendant maintains that Steps I, II, III and IV constitute an entire, indivisible contract, and thus plaintiff’s incapacity to stand by to perform Step IV constitutes a total breach of the contract, and excuses defendant’s performance. Defendant says also that it has been deprived of the benefits of its bargain, and it counterclaims for $92,843.12, the amount previously paid plaintiff, as damages.

In its second counterclaim the defendant asserts that the assignment for the benefit of creditors constituted a breach of plaintiff’s duty to stand by to perform Step IV and that on account of it, it has been damaged in the sum of $85,858.63, which, it says, is the reasonable value of the six-year standby availability of plaintiff’s manufacturing facility. Under this counterclaim, defendant concedes plaintiff’s right to recover under the contract for its substantial performance of Steps I, II, and III, and it, therefore, deducts the amount due under those steps from its claim for $85,858.63, and asks judgment for $41,025.04, together with interest.

From the foregoing it is perceived that the issue before us is twofold. First, what was the purpose of the contract? Did the Government bargain for the performance of each step separately or did it seek all four steps as an entire, indivisible undertaking? Secondly, did the assignment for the benefit of creditors constitute a breach of the contract?

From the documents before us on these cross-motions, we do not doubt that the purpose of the Signal Corps in entering into the contract was to have available, in case of a national emergency, a manufacturer who had demonstrated its ability to promptly manufacture “magic tees” in the volume the Signal Corps thought it might need them, and who was willing to do so at a price to be agreed upon. This purpose was set out in section 1 of Procurement Specification 15, pursuant to which plaintiff’s contract was entered into. This section reads:

“1. Scope.
“1.1. Purpose
“1.1.1. This specification covers industrial preparedness measures to be undertaken by manufacturers of the parts used in fabricating communications, electronics, and related equipments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Savings Bank, F.A. v. United States
519 F.3d 1316 (Federal Circuit, 2008)
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)
Hansen Bancorp, Inc. v. United States
67 Fed. Cl. 411 (Federal Claims, 2005)
Alexey T. Zacharin v. United States
108 F.3d 1391 (Federal Circuit, 1997)
Hemet Valley Flying Service Co. v. United States
32 Cont. Cas. Fed. 73,278 (Court of Claims, 1985)
Pennsylvania Exchange Bank
161 Ct. Cl. 874 (Court of Claims, 1963)
Bushnell, Receiver v. KRAFFT
183 N.E.2d 340 (Indiana Court of Appeals, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
170 F. Supp. 629, 145 Ct. Cl. 216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-exchange-bank-v-united-states-cc-1959.