Consolidated Airborne Systems, Inc. v. The United States

348 F.2d 941, 172 Ct. Cl. 588, 1965 U.S. Ct. Cl. LEXIS 151
CourtUnited States Court of Claims
DecidedJuly 16, 1965
Docket389-61
StatusPublished
Cited by19 cases

This text of 348 F.2d 941 (Consolidated Airborne Systems, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Airborne Systems, Inc. v. The United States, 348 F.2d 941, 172 Ct. Cl. 588, 1965 U.S. Ct. Cl. LEXIS 151 (cc 1965).

Opinion

PER CURIAM.

This case was referred pursuant to Rule 54(b) to Trial Commissioner Roald A. Hogenson with directions to make his recommendation for conclusion of law on plaintiff’s motion and defendant’s cross-motion for summary judgment. The commissioner has done so in an opinion filed April 12, 1965, wherein he recommended that plaintiff’s motion for summary judgment be denied, defendant’s cross-motion for summary judgment be allowed as to the petition but denied as to the counterclaim and that plaintiff’s petition and defendant’s counterclaim be dismissed. It appears to the court that neither party has filed a request for review pursuant to Rule 55(b), that the time for so doing has expired, and that on May 18, 1965, the defendant filed a motion for adoption of the commissioner’s opinion and recommended conclusion of law. Since the court is in agreement with the recommendation of the trial commissioner and opinion, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is, therefore, not entitled to recover on its petition and defendant is not entitled to recover on its counterclaim. Plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is allowed as to the petition but denied as to the counterclaim, defendant’s motion to adopt the commissioner’s opinion and recommended conclusion of law is allowed and the petition and counterclaim are dismissed.

OPINION OF COMMISSIONER

This is a suit on a bid contract awarded by defendant’s Aviation Supply Office, Department of the Navy, to plaintiff on June 27, 1958, designated Contract No. N383 (383-MIS) 54267A, pursuant to which plaintiff, a New York corporation, undertook to manufacture and deliver 467 units of electronic equipment called Test Bench Cable Kits at a unit price of $362, and a subordinate item for $450, for a total contract price of $169,504. The invitation for bids and contract divided the 467 items into two lots, Lot I being 267 items intended for Navy use, and Lot II being 200 items for the Army Signal Corps, As re *943 quired by the invitation, plaintiff’s bid was submitted on the total contract quantity, not as a separate bid on each lot. Plaintiff was required to submit to defendant for testing one preproduction sample of the contract item prior to the commencement of production and within 120 days after the contract award, and to make deliveries of the 467 items in quantities and intervals set forth in a contract schedule within a period of from 300 to 420 days after such contract award. As provided by the invitation and contract, the defendant was allowed 60 days after submission of the prepro-duction sample, within which to notify plaintiff whether such sample was approved, or plaintiff would be entitled to extensions of delivery dates by the number of days by which such notification was delayed.

On October 15, 1958, defendant’s contracting officer on plaintiff’s application extended the time for submission of the preproduction sample from 120 to 210 days provided that such extension would not affect delivery of the contract items. Plaintiff failed to fabricate and deliver the preproduction sample or commence production of any of the contract items. By written notice to plaintiff, dated January 26, 1959, the contracting officer after a preliminary warning dated December 16, 1958, terminated the contract for plaintiff’s default, finding that plaintiff had failed to make progress so as to endanger performance of the contract. Plaintiff was advised that the contract items would be procured on the open market against its account and that plaintiff would be held liable for any excess costs.

Defendant thereafter awarded a repro-curement contract to Avionics Corporation of America for the same equipment but for a quantity of only 267 units. The reduction from 467 units resulted from advice from the Army Signal Corps that its 200 units were no longer required. Avionics’ total contract price on 267 units at a unit price of $697.47 was $186,224.-49, less an allowable discount of 1 percent, or the net amount of $184,362.25.

By letter dated July 2, 1959, the contracting officer requested payment by plaintiff of . the excess costs of reprocurement in the amount of $88,191.52, presenting a computation of the net repurchase contract price of $184,362.25 (as stated above), and deducting therefrom $96,170.73, computed as plaintiff’s unit price of $362 applied to 267 units for $96,654, less an allowable discount of 0.5 percent.

Plaintiff took timely appeals on both actions of the contracting officer, and the issues on the termination of the contract for default and the assessment of excess costs of reprocurement were heard and decided by the Armed Services Board of Contract Appeals, pursuant to the standard Disputes article of the contract (ASBCA Docket No. 5498).

The record of the trial de novo held in this case has been abandoned by the parties. See Stein Bros. Mfg. Co. v. United States, Ct.Cl. No. 389-59, decided July 12, 1963, 337 F.2d 861. After such trial, they presented and filed their motions for summary judgment and briefs on the theory that the decision of the Supreme Court in United States v. Carlo Bianchi & Co., 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963), was applicable to this case, and that this court is limited to a review of the administrative record to test the finality of the Board’s decision on questions of fact. It is undisputed that the Board’s decision is not accorded finality on questions of law. 41 U.S.C. § 322. Accordingly, this opinion and recommended conclusion of law are based solely upon consideration of the administrative record, applying the test as to the finality of the Board’s findings of fact as provided in 41 U.S.C. § 321, but with independent consideration of the law applicable to the established facts.

It is my opinion that plaintiff’s motion should be denied, that defendant’s motion be granted as to plaintiff’s petition but denied as to the counterclaim, and that plaintiff’s petition and defendant’s counterclaim should be dismissed.

By its Findings of Fact and Decision, dated January 31, 1961, the Board found *944 and decided that plaintiff’s failure to perform did not result from excusable causes, but that the Government action in substantially decreasing the repurchase quantity of contract items was prejudicial to plaintiff to the extent that it re-culted in an increase in the repurchase unit price, that such increase was measurable and not properly includable in the computation of excess costs, and the correct amount of excess costs was $58,462.-32. Plaintiff’s motion for reconsideration was denied by the Board on April 14, 1961.

Thereafter, defendant demanded payment by plaintiff of the $58,462.32 plus interest at 5 percent from May 5, 1960, and plaintiff paid the demanded amount plus interest thereon, or a total of $61,-596.56. The parties then agreed that such payment was without prejudice to plaintiff’s right to proceed in this court.

By its petition herein, plaintiff seeks recovery of $61,596.56 with interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Seaboard Lumber Co. v. United States
48 Fed. Cl. 814 (Federal Claims, 2001)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Engle Investors v. United States
35 Cont. Cas. Fed. 75,757 (Court of Claims, 1989)
Eagle Aviation, Inc. v. United States
33 Cont. Cas. Fed. 74,055 (Court of Claims, 1985)
Tgc Contracting Corporation v. United States
736 F.2d 1512 (Federal Circuit, 1984)
Golden Eagle Refining Co. v. United States
31 Cont. Cas. Fed. 72,190 (Court of Claims, 1984)
Southeastern Airways Corp. v. United States
673 F.2d 368 (Court of Claims, 1982)
Churchill Chemical Corp. v. United States
602 F.2d 358 (Court of Claims, 1979)
National Eastern Corp. v. United States
477 F.2d 1347 (Court of Claims, 1973)
Astro-Space Laboratories, Inc. v. United States
470 F.2d 1003 (Court of Claims, 1972)
United States v. Wegematic Corporation
360 F.2d 674 (Second Circuit, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
348 F.2d 941, 172 Ct. Cl. 588, 1965 U.S. Ct. Cl. LEXIS 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-airborne-systems-inc-v-the-united-states-cc-1965.